We’re at NCSEA in San Francisco, Oct 28–29 · Booth 110NCSEA · Booth 110 · Oct 28–29

Sample AI plan review report

What Groundbook found in one real drawing set and its specs

A real, anonymous review of a school athletic complex. Groundbook checked 109 drawing sheets against each other and against the 591-page spec book. Every finding shows the page it came from.

Highlights

Four findings, with the pages behind them

18 of the 79 findings are places where a drawing and the spec book ask for different things. The rest compare sheets with each other. Click a page to enlarge it.

HighCivil · Architectural

The accessible-route slopes conflict between G1.11 and C4.1

C4.1 grading6.5% running, 2.5% cross slope

G1.11 limit5% running, 2.08% cross slope

Drawing C4.1 · Grading along the accessible route
Sheet C4.1, Grading along the accessible route, with the cited text highlighted
Drawing G1.11 · Accessible path of travel note
Sheet G1.11, Accessible path of travel note, with the cited text highlighted
Why it matters
The marked accessible route cannot follow the shown grading and meet its stated slope limits. The grading or route layout needs coordination before this paving is built.
Recommended fix
Coordinate the path location and grading between G1.11 and C4.1. Revise the affected slopes or provide a fully detailed alternative accessible route.
Read the full finding

G1.11 marks an accessible path through the paved corridor east of the tennis courts and south past the fountain. At that location, C4.1 shows a 6.5% slope along the corridor and a 2.5% slope across the north–south branch beside the fountain.

G1.11 requires this path to have a running slope no steeper than 1:20 (5%) and a cross slope no steeper than 1:48 (about 2.08%). The grading shown at this part of the route conflicts with those stated limits.

MediumCivil

Two water crossings cannot meet the specified 6-inch clearance

Crossing table2.8 in and 4.2 in clear, at most

Specification6 in minimum

Drawing C5.1 · Utility crossings table
Sheet C5.1, Utility crossings table, with the cited text highlighted
Specification Section 33 11 00 · Paragraph 3.04.B.2
Specification section 33 11 00, Paragraph 3.04.B.2, with the cited text highlighted
Why it matters
The two pipes cannot be installed at the scheduled elevations with the specified crossing clearance.
Recommended fix
Coordinate the water and storm-drain elevations at crossings 1 and 2 to provide the required clear separation, and update the crossing table.
Read the full finding

The C5.1 crossing table puts a 6-inch storm drain at invert 125.80 above the 2-inch water line at 125.40 at crossing 1. Their maximum clearance is (125.80 − 125.40) × 12 − 2 = 2.8 inches. At crossing 2, the water invert is 125.40 above a 12-inch storm drain at 124.05, giving at most 4.2 inches. Both values exclude pipe walls, which further reduce the gap, and are below the 6 inches required by Section 33 11 00, paragraph 3.04B.2.

MediumCivil · Landscape

The demolition notes and specification require different tree-protection fences

C3.14 ft orange fence on driven stakes

Specification6 ft chain link, no driven posts

Drawing C3.1 · Demolition note 7
Sheet C3.1, Demolition note 7, with the cited text highlighted
Specification Section 32 01 90 · Paragraph 2.01.A
Specification section 32 01 90, Paragraph 2.01.A, with the cited text highlighted
Why it matters
The drawing and specification call for different fence materials, heights and supports for protecting retained trees.
Recommended fix
Coordinate demolition note 7 with the specified tree-protection fence and support requirements.
Read the full finding

Demolition note 7 on C3.1 requires 4-foot orange safety fencing secured with driven metal stakes around plants to remain. The same sheet’s tree-protection legend refers to Section 32 01 90. Paragraph 2.01A of that section requires 6-foot self-supporting chain-link fencing and expressly prohibits driven support posts.

LowStructural

Round HSS yield strength differs between S1.01 and the specification

S1.01Fy = 50 ksi

SpecificationFy = 46 ksi

Drawing S1.01 · Structural steel note 2.E
Sheet S1.01, Structural steel note 2.E, with the cited text highlighted
Specification Section 05 12 00 · Paragraph 2.01.A.5
Specification section 05 12 00, Paragraph 2.01.A.5, with the cited text highlighted
Why it matters
The round-column material requirements contain two different minimum yield strengths.
Recommended fix
Coordinate the round HSS yield strength in the structural notes and specification with the structural engineer’s design basis.
Read the full finding

The structural-steel notes on S1.01 assign ASTM A500 Grade C round HSS a yield strength of 50 ksi. Section 05 12 00, paragraph 2.01A.5, assigns the same material 46 ksi. S2.01 uses round HSS for three columns, so the discrepancy applies to the building. The set’s stricter-requirement rule makes 50 ksi govern.

79 findings

HighCivil · Architectural#3The accessible-route slopes conflict between G1.11 and C4.1G1.11 · C4.1

G1.11 marks an accessible path through the paved corridor east of the tennis courts and south past the fountain. At that location, C4.1 shows a 6.5% slope along the corridor and a 2.5% slope across the north–south branch beside the fountain.

G1.11 requires this path to have a running slope no steeper than 1:20 (5%) and a cross slope no steeper than 1:48 (about 2.08%). The grading shown at this part of the route conflicts with those stated limits.

Why it matters

The marked accessible route cannot follow the shown grading and meet its stated slope limits. The grading or route layout needs coordination before this paving is built.

Recommended fix

Coordinate the path location and grading between G1.11 and C4.1. Revise the affected slopes or provide a fully detailed alternative accessible route.

See the cited evidence
HighCivil · Structural#8The 12-inch site walls lack coordinated heights and structural detailsD2.2 · S5.02 · D2.5 · C7.1 · D2.1 · D1.2

H/D2.2 shows a 12-inch retaining wall with a 3-foot maximum height and sends its reinforcement and footing to the structural drawings. D2.5’s B-B′ elevation gives a top of 138.00 feet and a bottom of 134.50 feet at one step; C-C′ gives 138.50 and 135.00 feet at another, making both walls 3½ feet high.

C7.1 key 6 instead sends the 12-inch wall to H/D2.1, an 18-inch-maximum tall-curb detail. The available structural retaining-wall typical, 2/S5.02, shows an 8-inch wall with undefined “A” vertical bars; the structural foundation plan, notes and typical details do not resolve the 12-inch wall reinforcement.

A/D1.2 also shows 12-inch planter walls but leaves their footing reference as X/DX.X.

Why it matters

The wall heights, reinforcement and footings cannot be selected consistently from the referenced drawings, which prevents reliable wall detailing and fabrication.

Recommended fix

Coordinate the site-wall heights and civil references, and provide matching structural details for the 12-inch retaining and planter walls, including footing dimensions and all reinforcement sizes and spacing.

HighCivil · Structural#15The flagpole and foul-pole footing references do not resolveD2.4 · D2.3

The footing schedule on D2.4 refers the 30-foot flagpole foundation to the structural drawings and the 40-foot foul-pole foundation to the netting manufacturer's drawings. The building structural sheets do not contain a flagpole foundation, and SFS-1/SFS-2 detail netting poles without identifying a foul-pole foundation. Detail A/D2.3 also refers the flagpole footing to those missing structural requirements.

Why it matters

The required pole foundations cannot be selected from the sheets cited by the footing schedule.

Recommended fix

Provide or identify the engineered flagpole and foul-pole foundation details and link them from the D2.4 footing schedule.

MediumCivil#1Four storm-drain pipes on C5.1 and C5.2 run uphill or flatter than their labeled minimum slopeC5.1 · C5.2

On C5.1, the 12-foot JB04–JB03 pipe is labeled for a minimum 2% fall. Its endpoint inverts are 126.25 and 126.85 feet, which instead make it rise 5% in the indicated flow direction.

The next 18-foot pipe, JB03–CB01, also requires a minimum 2% fall. Its inverts of 124.50 and 124.60 feet instead make it rise 0.56%.

On C5.1, the 112-foot TDCB #01–JB #02 pipe requires a minimum 0.5% fall. Its inverts of 126.11 and 125.90 feet give only a 0.1875% fall.

On C5.2, the 151-foot COIT03–JB12 pipe requires a minimum 0.5% fall. Its inverts of 130.13 and 129.87 feet give only a 0.17% fall.

Why it matters

The contractor cannot set these inverts and also meet the labeled slopes. Two pipes would rise in the indicated direction of gravity flow.

Recommended fix

Have the civil engineer reconcile the connected invert elevations, lengths and minimum slopes for these four pipes and their adjacent structures before setting the drain levels.

MediumCivil#2Two water crossings cannot meet the specified 6-inch clearanceC5.1 · Spec 33 11 00

The C5.1 crossing table puts a 6-inch storm drain at invert 125.80 above the 2-inch water line at 125.40 at crossing 1. Their maximum clearance is (125.80 − 125.40) × 12 − 2 = 2.8 inches. At crossing 2, the water invert is 125.40 above a 12-inch storm drain at 124.05, giving at most 4.2 inches. Both values exclude pipe walls, which further reduce the gap, and are below the 6 inches required by Section 33 11 00, paragraph 3.04B.2.

Why it matters

The two pipes cannot be installed at the scheduled elevations with the specified crossing clearance.

Recommended fix

Coordinate the water and storm-drain elevations at crossings 1 and 2 to provide the required clear separation, and update the crossing table.

See the cited evidence
MediumElectrical#4DP-A model does not match its scheduled circuit capacity and enclosure ratingE4.1 · E0.2

E4.1 lists DP-A as Schneider NQ442L4C with an MH50WP enclosure. E0.2 requires NEMA 4X and schedules 14 three-pole lighting circuits, three single-pole circuits and one three-pole restroom feeder: 14 × 3 + 3 + 3 = 48 occupied pole spaces. The NQ442L4C data sheet provides 42 spaces, and the MH50WP data sheet gives a Type 3R/5/12 enclosure rating. Both selections differ from the panel schedule.

Why it matters

The listed panel cannot accommodate the scheduled breakers and does not provide the specified enclosure rating.

Recommended fix

Select a panel and enclosure that meet the reviewed circuit count and environmental rating, then coordinate the model, dimensions, mounting and panel schedule.

MediumElectrical#5E0.2 gives two ratings for the new main-switchboard breakerE0.2

On E0.2, the one-line diagram labels the new main-switchboard breaker “400/3” and points to keynote 1. That same keynote specifies a new 250 A, three-pole breaker. These are different ratings for the same breaker.

Why it matters

The breaker cannot be selected consistently from the one-line diagram and its installation note.

Recommended fix

Have the electrical engineer select the intended breaker rating and make the one-line diagram and keynote agree.

MediumElectrical#6The site plans refer to feeder sizes that E0.2 does not provideE2.0 · E0.2

Keynote 2 on E2.0 directs the contractor to E0.2 for conduit and conductor sizing. The E0.2 one-line diagram labels the new MSB-to-DP-A and downstream feeders only as "(N) FEEDER", without sizes. The E0.2 schedules and E0.3 sports-lighting feeder schedule do not identify sizes for the MSB-to-DP-A feeder or the restroom-panel feeder.

Why it matters

The main site and restroom feeder conduit and conductors cannot be selected from the referenced information.

Recommended fix

Add the feeder conductor and conduit sizes to the one-line diagram or a keyed feeder schedule, and coordinate the site-plan references.

MediumStructural#7The S5.22 column-base detail has conflicting hole counts and undefined dimensionsS5.22

Detail 1/S5.22 calls for two anchor holes, while its plan shows an anchor at each of the four plate corners. The adjacent base-plate schedule also gives dimensions C, D and E that the detail does not identify. The schedule and complete base detail therefore leave both the anchor quantity and the application of those dimensions unresolved.

Why it matters

The plate fabricator and anchor installer cannot reliably establish the intended hole quantity and layout from this detail.

Recommended fix

Reconcile the anchor-rod and hole quantities, then identify dimensions C, D and E on the base detail or remove any unused schedule columns.

MediumCivil · Structural#9The netting-post curb detail conflicts with the required pole separationD2.1 · SFS-2 · C7.1 · D2.4

C7.1 key 18 sends baseball netting posts to K/D2.1 and the structural drawings. K/D2.1 shows the netting post surrounded by a widened concrete curb with 4-inch concrete margins and a transverse expansion joint. Detail 9/SFS-2 instead says not to encase the pole in the curb and requires a 1/2-inch to 1-inch gap filled with compressible material and sealant. The transverse joint in K/D2.1 does not show that separation between the pole and the surrounding curb.

Why it matters

The civil and netting details give different construction for the curb-to-pole interface, so the installer cannot follow both details as drawn.

Recommended fix

Coordinate K/D2.1 with 9/SFS-2 and show one consistent curb termination and pole-separation detail.

MediumArchitectural#10A10.41 roof anchorage criteria differ from the roof plan and reference specificationA10.41 · A2.12 · Spec 07 41 13.16

A10.41 bases its 16-inch clip spacing on 24-gauge galvanized-steel panels at a 3.5:12 roof pitch. The roof plan on A2.12 shows 2.5:12 on both roof planes. Reference Section 07 41 13.16, 2.02.B.2 lists aluminum sheet panels, although thickness and other selections remain open. The printed anchorage criteria therefore differ from the roof plan and the material listed in the reference specification.

Why it matters

The clip layout has a different panel and slope basis from the other roof documents, leaving the intended anchorage assembly unclear.

Recommended fix

Coordinate the roof-panel material and pitch, then provide anchorage criteria and clip spacing for that selected assembly.

MediumMechanical · Electrical#11RHP-1 has conflicting voltages and no assigned heater circuitsM0.02 · E0.2

M0.02 schedules eight RHP-1 radiant panels at 375 W and 120 V each. E0.2 lists RHP-1 at 208 V and leaves its circuit field blank. The E0.2 equipment and PB-A panel schedules do not assign circuits to the eight heaters.

Why it matters

The heater voltage and circuit arrangement remain unresolved, preventing reliable wiring and panel-load coordination.

Recommended fix

Coordinate the RHP-1 voltage with the selected heaters, assign circuits serving all eight panels, and update the mechanical and electrical schedules and plans.

MediumArchitectural · Civil#12Gate sizes and schedule coverage disagree between architecture and civil drawingsA9.11 · A1.21 · C7.1 · A1.11

A9.11 schedules all thirteen gates at 8 feet high. C7.1 instead requires 7-foot single gates at G101, G103, G105, G107, G108, G109, G110 and G111; 12-foot double gates at G102, G104, G106 and G112; and a 10-foot double gate at G113.

The civil double gates are also 12 feet wide, but A9.11 gives each of their two panels a width of 3 feet 11 inches, totaling 7 feet 10 inches.

C7.1 also keys two additional pedestrian gates without separate architectural tags or schedule rows: one beside G101 and one at the east end of the middle tennis-court fence.

Why it matters

The conflicting sizes can produce incorrect gate fabrication, openings and adjoining fence assemblies; the two unlisted gates have no corresponding architectural schedule selection.

Recommended fix

Coordinate all gate locations, tags, heights and double-gate widths across A1.11/A1.21, A9.11 and the civil plans and details, including the two additional civil gates.

MediumElectrical#13E0.3 sports-lighting feeder assignments disagree with both pole diagramsE0.3

The SPORTS LIGHTING FEEDER SCHEDULE on E0.3 defines the circuits and conductors for the M-numbered lighting runs. Ten pole branches name contactors absent from their scheduled runs: for example, M11 serves T2/C2 but lists C1 and C13, while M17 serves A2/C14 but lists C9.

Eight connecting runs also omit contactors assigned to the poles downstream of them. The baseball and softball diagram labels M22, but the complete feeder schedule ends at M21.

Why it matters

The schedule cannot reliably define the circuits and conductors for the affected sports-lighting branches and connecting runs.

Recommended fix

Reconcile all M01-M22 runs with the pole diagrams and control summary, add the M22 entry, and update any conductor and conduit selections affected by the corrected assignments.

MediumCivil · Electrical#14D1.1 and E4.1 require different spacing between power conduit and irrigation pipingD1.1 · E4.1 · E2.0

Detail J/D1.1 places the irrigation mainline and power/data conduit 1 foot apart, center to center, beside the field-perimeter subdrain. The site conduit keynotes on E2.0 refer to detail 4/E4.1, which requires 3 feet minimum clear separation from a parallel pipe or conduit. The dimensioned shared-trench arrangement cannot provide that clearance.

Why it matters

The civil and electrical details give incompatible utility spacing for the shared field-perimeter trench.

Recommended fix

Coordinate the shared-trench dimensions and the applicable electrical separation requirement on D1.1 and E4.1.

MediumCivil#16Two drainage details assume an existing base instead of the new turf assemblyD1.1 · D2.2

Detail I/D1.1 labels a 4-inch existing rock base to remain and points to C/D2.2 as “synthetic turf over existing base.” That referenced detail instead shows a 5-inch permeable base and 1-inch composite layer over treated subgrade. The midfield subdrain detail therefore does not match the turf assembly it cites.

E/D1.1 also labels an “existing synthetic turf base” while pointing to that same new turf assembly.

Why it matters

The subdrain and cleanout interfaces could be built using an existing-base assumption that does not match the turf assembly they cite.

Recommended fix

Revise I/D1.1 and E/D1.1 to match the new turf assembly on C/D2.2, including the base depths and drainage interfaces.

MediumCivil · Landscape#17Referenced planting and irrigation plans are missing from the drawing setC3.1 · C7.1 · Spec 32 80 00 · Spec 32 90 00

C3.1 refers existing irrigation water lines and flow-sensor wiring to an irrigation plan, and the C7.1 material legend refers planting and stormwater-management areas to planting plans. Neither plan appears in the submitted 109-sheet drawing set. Sections 32 80 00 and 32 90 00 leave equipment and plant selections to the drawings, so the specifications do not replace those plans.

Why it matters

The referenced irrigation layout and planting selections cannot be coordinated with the demolition and new site work.

Recommended fix

Provide the referenced planting and irrigation plans and coordinate them with C3.1, C7.1 and the applicable specifications.

MediumArchitectural#18A9.11 refers to a door-hardware schedule that is not providedA9.11

The A9.11 door schedule leaves the hardware-group column blank for all nine doors. General note 16 refers the hardware schedule to the specifications. The submitted specification has no hardware schedule or Section 08 71 00 to supply those assignments.

Why it matters

The hardware sets for the nine doors and the corresponding frame preparations remain undefined.

Recommended fix

Provide the referenced hardware schedule and assign a hardware group to each door on A9.11.

MediumStructural · Architectural#19S2.02 refers exposed-steel requirements to an unbound specification sectionS2.02 · Spec 05 12 00

Framing-plan note 13 on S2.02 requires visually exposed steel to meet architecturally exposed structural steel (AESS) requirements. Section 05 12 00 refers those members to Section 05 12 13. The submitted specification contains no Section 05 12 13, and the inspected architectural and structural sheets do not provide the referenced AESS requirements.

Why it matters

The required exposed-steel finish and fabrication standard cannot be established from the referenced documents.

Recommended fix

Provide the referenced AESS requirements and identify their application to the exposed members.

MediumCivil · Landscape#20The demolition notes and specification require different tree-protection fencesC3.1 · Spec 32 01 90

Demolition note 7 on C3.1 requires 4-foot orange safety fencing secured with driven metal stakes around plants to remain. The same sheet’s tree-protection legend refers to Section 32 01 90. Paragraph 2.01A of that section requires 6-foot self-supporting chain-link fencing and expressly prohibits driven support posts.

Why it matters

The drawing and specification call for different fence materials, heights and supports for protecting retained trees.

Recommended fix

Coordinate demolition note 7 with the specified tree-protection fence and support requirements.

See the cited evidence
MediumCivil#21C3.2 gives both retain and remove instructions to one fence and wall segmentC3.2

At the northeast corner of the field, C3.2 groups protected-item keys B and CC with demolition keys 8 and 15 on one leader to the short angled fence/wall segment. B and CC require the existing fence and wall to remain and be protected; 8 and 15 require those same types of elements and their footings to be removed. The callout gives no separate limits for the opposite instructions.

Why it matters

The contractor cannot determine which portion of this fence and wall to retain or demolish from the combined callout.

Recommended fix

Separate the retain and remove leaders and show the intended demolition limit for the northeast fence/wall segment.

MediumCivil#22The integrated foul pole is specified at both 30 and 40 feetD2.3 · D2.5

Detail C, FOUL POLE - RIGHT FIELD, on D2.3 specifies a 40-foot foul pole integrated into the retaining wall. WALL ELEVATION - C-C′ on D2.5 labels that right-field wall pole 30 feet tall. The detail and wall elevation therefore require different heights for the same pole.

Why it matters

The pole height cannot be selected consistently for procurement and its supporting design.

Recommended fix

Coordinate the integrated foul-pole height between the detail, wall elevation and supplier’s pole design.

MediumCivil#23D/D2.1 gives two dowel spacings for concrete expansion jointsD2.1

The CONCRETE JOINTS detail D on D2.1 specifies 24-inch smooth dowels at 36 inches on center in the expansion-joint sections. The CONSTRUCTION / EXPANSION JOINT plan in that same detail specifies those dowels at 18 inches on center. The plan and sections therefore require different dowel spacing for the expansion joints.

Why it matters

The two instructions require different dowel quantities and joint layouts.

Recommended fix

Select the intended expansion-joint dowel spacing and make the plan and section notes agree.

MediumCivil#24C7.1 calls for a presloped trench drain, but its D1.1 detail specifies a neutral-sloped drainC7.1 · D1.1 · Spec 33 40 00

C7.1 material key 1 identifies the site trench drain as presloped and refers to detail M/D1.1. That detail is titled “NEUTRAL-SLOPED TRENCH DRAIN.” Specification Section 33 40 00 also specifies a presloped channel for trench drains outside a running track, so the drawing detail and referenced requirements do not agree on the channel type.

Why it matters

The trench-drain channel type cannot be selected consistently for procurement and installation.

Recommended fix

Have the civil engineer select the intended channel type and coordinate the C7.1 material key, C5.1 drainage legend, M/D1.1 detail and Section 33 40 00.

MediumArchitectural#25The downspout detail uses steel pipe instead of the specified formed sheet metalA10.41 · A5.11 · Spec 07 60 00

Detail 5/A10.41 shows a steel-pipe downspout with welded mounting tabs, and A5.11 calls it Schedule 40 metal pipe. Section 07 60 00, paragraphs 2.07B and 2.07C, describes downspouts formed from aluminum or coated-steel sheet. The drawing and specification describe different downspout construction.

Why it matters

The downspout and its mounting assembly could be priced and fabricated from different material systems.

Recommended fix

Coordinate the downspout construction and mounting detail with Section 07 60 00.

MediumPlumbing · Electrical#26EWH-141’s scheduled current conflicts with its power ratingP0.02 · E0.2

P0.02’s ELECTRIC WATER HEATER SCHEDULE lists EWH-141 at 1,500 W total heating power, 208 V, single phase, and 25 A. For that resistive heating load:

Current = power ÷ voltage = 1,500 W ÷ 208 V ≈ 7.2 A.

E0.2’s ELECTRICAL EQUIPMENT SCHEDULE also lists 7 A full-load current. The 25 A entry does not agree with the scheduled total power and voltage.

Why it matters

The plumbing and electrical schedules give different operating-current data for selecting and connecting the water heater.

Recommended fix

Confirm the water heater’s intended power and operating current, then correct the inconsistent schedule entry.

MediumElectrical#27P5 and C3 list the same fixture model but incompatible input powerE0.2

E0.2’s LIGHTING FIXTURE SCHEDULE lists the same RNDS-2-L25/840-FXA-DIM-UNV model and 2,500-lumen output for C3 and P5, but gives 24 W for C3 and 3,257 W for P5. The P5 model and input-power entry are inconsistent.

Why it matters

P5’s model and wattage cannot both be used as written for fixture selection and load calculations.

Recommended fix

Confirm the intended P5 fixture, then coordinate its model, description and input power in the schedule.

LowStructural#28S1.02 requires 8 inches of grout around embeds inside 8-inch CMU wallsS1.02 · S2.01 · S5.12

CMU (concrete masonry unit) note 20 on S1.02 requires at least 8 inches of grout around embedded items within a block cell. S2.01 specifies 8-inch CMU walls, and S5.12 provides embedded-anchor details for those walls. An 8-inch clearance around an embed cannot fit within an 8-inch wall.

Why it matters

The grout-clearance note cannot be followed for the specified CMU walls and conflicts with the supplied embed geometry.

Recommended fix

Have the structural engineer correct the grout clearance within the block cell and coordinate it with the embed details.

LowStructural#29The W18 anchor layout cannot fit the plate height in 5/S5.12S5.12

Detail 5 on S5.12 schedules eight headed anchors and a 21½-inch plate height for its W18 beam row. Its one-sided plate detail arranges the anchors in two columns at 8-inch vertical centers.

Eight anchors require four rows. With 8 inches between rows, the outer rows are 24 inches apart, exceeding the 21½-inch plate height before edge distances.

Why it matters

If the W18 typical is used, its scheduled anchor count, plate height and illustrated spacing cannot all be fabricated as shown.

Recommended fix

Have the structural engineer reconcile the W18 plate height, anchor count and spacing in detail 5.

LowStructural#30The netting-pole footing detail does not show where S2 tie spacing appliesSFS-2

Detail 2 on SFS-2 schedules two tie spacings for both 40-foot netting-pole footing types: S1 at 4 inches and S2 at 9 inches. The section labels ties only with S1; it gives no S2 zone or transition point.

Why it matters

The reinforcement cage cannot be detailed with both scheduled spacings without deciding where S2 applies.

Recommended fix

Show the extent of each tie-spacing zone in detail 2, or remove S2 if it is not intended to apply.

LowStructural#31S5.32 requires deck-opening angles for widths its sizing note does not coverS5.32

Detail 1 on S5.32 requires reinforcing angles for deck openings wider than 8 inches through 24 inches and refers to detail 2. Detail 2 gives angle sizes only for 12 < W1 < 18 inches and 18 < W1 < 24 inches. Openings wider than 8 inches through 12 inches, and the exact 18- and 24-inch widths, therefore have no angle size in the cited detail.

Why it matters

The cited detail does not provide an angle size for every opening width covered by the reinforcing criteria.

Recommended fix

Have the structural engineer provide sizes for the full required range and reconcile the boundary conditions in details 1 and 2.

LowCivil#32B/D2.1 gives conflicting reinforcement depths for the 4-inch pedestrian slabD2.1

The lower section in B/D2.1 shows a 4-inch pedestrian concrete slab. It calls for 2½ inches of clear cover above the reinforcement and also requires the reinforcement in the middle of the slab. The middle of a 4-inch slab is 2 inches below its surface, so the stated clear cover cannot produce that placement.

Why it matters

The detail gives two different instructions for setting the reinforcement height in the pedestrian paving.

Recommended fix

Revise B/D2.1 to give a consistent reinforcement position and cover for each slab-thickness option.

LowStructural#33S2.02 directs HSS roof-beam connections to a wide-flange beam detailS2.02 · S5.21

The roof plans on S2.02 specify HSS (hollow structural section) beams, but framing note 10 directs typical beam-to-HSS-column connections to 1/S5.21. That detail is titled “WF BEAM TO HSS COLUMN” and connects a wide-flange beam web to a shear plate. Separate HSS connection details are present on S5.21, so the stated typical reference needs to identify the intended connection for these roof beams.

Why it matters

The stated typical reference points to a different beam type and does not reliably identify the intended roof connection.

Recommended fix

Have the structural engineer replace note 10 with the applicable HSS beam connection reference and identify any location-specific variants.

LowArchitectural#34CMU wall section points to metal-stud head and base detailsA6.21 · A10.11

Wall section 4/A6.21 shows a CMU (concrete masonry unit) wall between Gender Neutral 147 and Common 153, but its head calls for 3/A10.11 and its base for 1/A10.11. Those details show a metal-stud head with a deflection track and a nonstructural metal-track wall base. A10.11 separately contains detail 11, titled CMU WALL BASE.

Why it matters

Following the called-out details would apply metal-stud construction to the masonry wall.

Recommended fix

Replace both references with the intended CMU head and base details, and coordinate the masonry support with structural drawings.

LowElectrical#35Sports-lighting pull-box bedding differs from the specificationE2.0 · E4.1 · Spec 26 56 68

E2.0 refers the site pull boxes to detail 1/E4.1, which shows a 6-inch gravel base. Section 26 56 68, paragraph 2.2D, requires 12 inches of compacted aggregate beneath sports-lighting handholes. The referenced detail provides half the specified bedding depth.

Why it matters

The two requirements give different excavation depths and bedding quantities for the sports-lighting pull boxes.

Recommended fix

Coordinate the sports-lighting pull-box detail with the required aggregate depth in Section 26 56 68.

LowElectrical#36Six sports-lighting fixtures have a lower color-rendering rating than specifiedE5.1 · Spec 26 56 68

The Fixture Type Summary on E5.1 lists six Cree OSQ fixtures at a color rendering index (CRI) of 70. Section 26 56 68, paragraph 1.2B, requires a CRI of 75 for the lighting system. The selected fixture rating is lower than that requirement.

Why it matters

The six listed fixtures would not provide the specified color-rendering quality.

Recommended fix

Select fixtures that meet the specified CRI, or have the designer revise and coordinate the lighting requirement and fixture schedule.

LowPlumbing#37L-1’s cold-water-only schedule conflicts with the hot-water piping on P2.01P0.02 · P2.01

P0.02’s PLUMBING FIXTURE SPECIFICATION & CONNECTION SCHEDULE describes L-1 as “COLD WATER ONLY” and gives no hot-water connection. P2.01 draws a 1-inch hot-water supply and 3/4-inch hot-water return loop at the group labeled “(3) L-1”. The fixture schedule and the drawn water-supply arrangement do not agree.

Why it matters

The drawings do not give a consistent basis for selecting the lavatory faucet connections and their water supply.

Recommended fix

Reconcile the L-1 faucet and connection schedule with the water-supply arrangement on P2.01.

LowElectrical#38Egress lighting calculation is below the specified average targetE5.4 · Spec 26 56 68

E5.4’s Egress grid reports a maintained horizontal average of 25.31 footcandles (fc), using 16 points at 10-foot spacing. Section 26 56 68, paragraph 1.2.A, specifies a 26 fc average target for that same 16-point, 10-foot grid. The submitted calculation is below the specified target.

Why it matters

The lighting calculation does not demonstrate the specified average illumination for the egress area.

Recommended fix

Reconcile the egress lighting calculation and the specification target with the electrical designer and lighting supplier.

LowElectrical · Structural#39E0.1’s anchorage note uses a different CBC edition from G0.11G0.11 · E0.1

G0.11’s CODES block identifies the 2025 California Building Code for the project. E0.1’s MEP COMPONENT ANCHORAGE NOTE instead directs component anchorage to the 2022 CBC. These are competing editions of the same code for work covered by the project’s stated code basis.

Why it matters

The anchorage note gives the electrical designer and installer an inconsistent governing-code reference.

Recommended fix

Update E0.1’s anchorage note and its associated section references to the project’s governing code basis.

LowStructural#40Rebar-welding electrode grades differ between S5.01 and the specificationS5.01 · Spec 03 20 00 · S1.01

Detail 2/S5.01 requires E80-series electrodes for A706 Grade 60 reinforcing bars and E90-series electrodes for A615 Grade 60 bars. Section 03 20 00, paragraph 2.01M, instead specifies E70XX-series electrodes. The set’s stricter-requirement rule makes the drawing minimums govern, but the specification still names a lower electrode grade.

Why it matters

The rebar-welding submittal requirements contain conflicting electrode grades.

Recommended fix

Revise Section 03 20 00 to agree with the electrode requirements on 2/S5.01.

LowStructural#41Round HSS yield strength differs between S1.01 and the specificationS1.01 · Spec 05 12 00 · S2.01

The structural-steel notes on S1.01 assign ASTM A500 Grade C round HSS a yield strength of 50 ksi. Section 05 12 00, paragraph 2.01A.5, assigns the same material 46 ksi. S2.01 uses round HSS for three columns, so the discrepancy applies to the building. The set’s stricter-requirement rule makes 50 ksi govern.

Why it matters

The round-column material requirements contain two different minimum yield strengths.

Recommended fix

Coordinate the round HSS yield strength in the structural notes and specification with the structural engineer’s design basis.

See the cited evidence
LowStructural#42The column-base detail and specification name different anchor-rod washersS5.22 · Spec 05 12 00 · S1.01

Detail 1/S5.22 calls for F844 washers above and below the column base plate. Section 05 12 00, paragraphs 2.01F.6d and 2.01F.7c, requires ASTM F436 hardened washers for anchor rods. The detail names a different washer grade from the specification. S1.01 makes the stricter requirement govern, but the base detail still names F844.

Why it matters

The anchor-rod washer selection differs between the base detail and the submittal requirements.

Recommended fix

Have the structural engineer coordinate the required anchor-rod washer grade in 1/S5.22 and Section 05 12 00.

LowCivil#43D2.4 gate posts and latch model differ from the specificationD2.4 · Spec 32 31 13

The D2.4 footing schedule specifies round 4-inch pipe posts for the 7-foot-high pedestrian gates. Section 32 31 13, paragraph 2.04C.4a, instead requires 4-inch square posts for pedestrian gates 8 feet high and under. Detail M/D2.4 also names latch CL-FULCRUM-SNG, while paragraph 2.02D.7c specifies STRONG-ARM-SNG.

Why it matters

The gate fabrication and hardware submittals have different post-shape and latch requirements.

Recommended fix

Coordinate the pedestrian gate post shape and latch selection between D2.4 and Section 32 31 13.

LowStructural · Civil#44The netting-pole primer differs between SFS-1 and the specificationSFS-1 · Spec 11 65 00

Structural-steel note 6 on SFS-1 requires a TGIC polyester primer for exposed steel. Section 11 65 00, paragraph 2.02B.1b, requires a zinc gray epoxy primer for the netting poles. These are different primer systems for the same poles.

Why it matters

The netting-pole coating submittal has conflicting primer requirements.

Recommended fix

Coordinate the netting-pole primer system in SFS-1 and Section 11 65 00.

LowCivil#45The bound City standards give different sidewalk finish and joint requirementsC7.3 · D1.1 · D1.3

C7.3 refers the new sidewalk to the City concrete-work notes in D/D1.1. Note 13 requires broom texture along the sidewalk, while section 2003.5A of the City standard on D1.3 requires broom strokes perpendicular to the curb when a broom finish is used.

Note 9 of the concrete-work notes requires weakened-plane joints at least 1½ inches deep. Section 2003.6A of the City standard gives approximately one-fifth of the slab thickness—about 0.8 inch for the 4-inch sidewalk in F/D1.1.

The standards allow matching existing finishes or an approved direction, but the supplied offsite sheets do not identify which requirements govern these differences.

Why it matters

The sidewalk finish direction and joint depth cannot be selected consistently from the two bound standards.

Recommended fix

State the governing sidewalk finish direction and joint depth, and record any approved departure under section 2001.1A on D1.3.

LowCivil#46A tennis-court offset dimension disagrees with its layout coordinatesC6.1

On C6.1, the fence line between the tennis-court rows is at northing 1102.81 feet, and the north edge of the southern court row is at northing 1084.81 feet. These coordinates give an 18-foot offset, but the dimension between the same lines reads 18 feet 2 inches.

Why it matters

Using the dimension instead of the coordinates would shift the court layout by 2 inches.

Recommended fix

Reconcile the dimension and coordinate values so they give one fence-to-court offset.

LowCivil#47Pitcher's mound detail uses both 9-inch and 10-inch starting elevationsD3.1

H/D3.1 labels the flat mound surface 10 inches above home plate, but the note beside its descending elevation marks says those changes start from an area 9 inches above home plate. Note 3 gives a total elevation difference of 10 inches, with the final inch between the mound and home plate.

Why it matters

The starting elevation for setting the mound is inconsistent by 1 inch.

Recommended fix

Confirm the intended starting elevation and make the flat-area label, elevation-change note and note 3 consistent.

LowCivil#48Drip pressure indicator is shown at the supply connection but required at the flush endD4.2

E/D4.2 connects the operating pressure indicator beside the control valve at the center supply header. Its callout points to L/D4.2, which requires one indicator per zone at the flush end. E shows the flush valves at the two outer exhaust headers.

Why it matters

The layout and installation detail give different locations for the pressure indicator.

Recommended fix

Coordinate E/D4.2 and L/D4.2 to show the intended indicator connection for the center-feed arrangement.

LowCivil#49The trench-drain catch-basin detail specifies both light and medium broom finishesD1.1

In N/D1.1, section B–B′ calls for a light broom finish lengthwise on the concrete surround. Note 1 requires a medium broom finish lengthwise for the same concrete.

Why it matters

The detail gives two different surface textures for the same concrete surround.

Recommended fix

Make the section leaders and note 1 specify the same finish.

LowArchitectural#50A2.21 leaves room finish assignments blank and refers to an absent scheduleA2.21

The finish-plan legend on A2.21 refers wall, base and floor finishes to a finish schedule. The room tags on that sheet leave those finish fields blank, and the submitted drawing set contains no finish schedule to complete them. The specification describes finish systems without assigning them to these room tags.

Why it matters

The wall, base and floor finish selections cannot be determined for the tagged rooms.

Recommended fix

Provide the referenced finish schedule and complete the room finish assignments on A2.21.

LowArchitectural#51A2.11 wall-type marks have no definition on the referenced sheetA2.11 · G0.11 · A10.11

A2.11 uses wall-type marks AS4Z and ZM8Z. The wall-type legend on G0.11 points to A10.11, but that sheet contains typical details referring back to the plans without defining either mark. No definition of these marks was found in the submitted drawing set.

Why it matters

Readers cannot resolve the tagged wall assemblies through the drawing references.

Recommended fix

Define AS4Z and ZM8Z on the referenced wall-type sheet and coordinate the plan tags.

LowCivil#52D2.1 refers to a chemical-treatment plan that is not in the setD2.1 · Spec 31 20 00

Detail B/D2.1 refers the limits of chemical treatment to a “Chemical Treatment Plan.” No sheet with that title or an identified substitute is provided in the 109-sheet drawing set. C7.1 and C7.2 identify treated surface types, but do not resolve that plan reference. The earthwork specification incorporates a separate geotechnical report, which was not supplied for this review.

Why it matters

The detail’s reference for selecting the treated-to-untreated paving edge cannot be followed.

Recommended fix

Identify the sheet that defines the chemical-treatment limits, or provide the referenced plan and coordinate it with the geotechnical requirements.

LowCivil#53The referenced offsite grading plan is not includedC4.1 · C0.0

C4.1 directs grading within the city right of way to the offsite plans. C0.0 lists C4.3 as “GRADING PLAN (NOT INCLUDED)”; the submitted offsite sheets contain no grading plan for the new sidewalk and curb-ramp work.

Why it matters

The right-of-way grading and its tie-in to the onsite accessible route cannot be coordinated from the submitted set.

Recommended fix

Include C4.3 when that scope is issued, or identify another supplied drawing that gives the right-of-way grading.

LowCivil#54C3.1 applies demolition key T to two ramps but defines T as not usedC3.1

On C3.1, boxed key T points to two existing curb ramps at the northwest street corner. The protected-or-relocated-items legend defines T as “NOT USED.” General note 5 says existing items remain unless otherwise noted, but these two specific leaders have no defined instruction.

Why it matters

The two ramp leaders cannot be matched to a valid instruction in the legend.

Recommended fix

Give key T the intended ramp instruction or replace the two leaders with the correct defined key. Coordinate with the applicable off-site work.

LowArchitectural#55A10.81 sends sign mounting to detail 16 instead of detail 6A10.81

Note 1 in the Signage Materials and Color Keynotes on A10.81 directs sign mounting to detail 16/A10.81. Detail 16 is Fire Rated Wall Identification in Concealed Spaces; the sign-attachment instructions are in detail 6, Sign Mounting.

Why it matters

The stated reference takes the sign installer to fire-wall labeling rather than the required attachment instructions.

Recommended fix

Change the mounting-method reference to the intended sign-mounting detail.

LowStructural#56S1.01 sends the concrete-strength requirement to the wrong noteS1.01

Concrete note 1 on S1.01 directs the 28-day compressive-strength requirement to note 28. Note 28 only requires 48-hour notice before concrete placement; the concrete strengths and mix properties are in note 32.

Why it matters

The cross-reference sends the reader to a placement notice instead of the applicable strength schedule.

Recommended fix

Change the strength reference in concrete note 1 from note 28 to note 32.

LowArchitectural#57Lavatory clear-space keynote points to a door-landing detailA2.11 · A10.71

A2.11 uses keynote 34.01 at the three lavatory approach spaces and defines it as a 30-by-48-inch accessible clear space, referring to 3/A10.71. That detail is titled “DOOR LANDING AND CLEARANCES” and depicts door swings and latch-side landing dimensions, rather than the lavatory approach referenced by the keynote.

Why it matters

The reference leads to a different clearance condition instead of the intended fixture approach detail.

Recommended fix

Point keynote 34.01 to the intended lavatory clear-space detail and retain the coordinated 30-by-48-inch approach requirement.

LowCivil#58The turf-on-concrete detail points to asphalt paving instead of the turf notesD2.2

Note 3 in F/D2.2 sends the reader to the synthetic-turf notes in A/D2.2. Detail A is Asphalt Paving; the Synthetic Turf Notes are detail B on the same sheet.

Why it matters

The reference sends the reader to an unrelated paving assembly when looking for the turf requirements.

Recommended fix

Correct note 3 in F/D2.2 to reference the intended synthetic-turf notes, B/D2.2.

LowCivil#59The basketball plan points to a footing schedule with no basketball entryD2.3 · D2.4

The basketball striping detail F/D2.3 points the basketball post to Footing Schedule B/D2.4. That schedule lists fences, gates, netting, foul poles and the flagpole, but no basketball post. The basketball footing is shown in B/D2.3.

Why it matters

The basketball-post reference does not lead to its footing requirements.

Recommended fix

Point the basketball-post callout to the intended basketball footing detail, B/D2.3, and confirm its application.

LowCivil#60The planter overflow callout points to a blank detailD1.2

The overflow-riser callout in A/D1.2 points to detail E on the same sheet. That slot is blank. The overflow riser with grate/standpipe is shown in detail D.

Why it matters

The planter callout does not lead to its overflow-riser construction detail.

Recommended fix

Correct the callout to detail D if that is the intended assembly.

LowCivil · Structural#61Wall-padding references on D2.3 and D2.5 do not resolveD2.3 · D2.2 · S1.00 · D2.5

Detail E, PADDING ATTACHMENT - WALL / CHAIN LINK FENCE, on D2.3 directs the Z-clip mounting to 7/S8.1 and the home-run-wall padding condition to F/D2.2. The submitted drawing inventory and structural index contain no S8.1. F/D2.2 is SYNTHETIC TURF ON CONCRETE PAVING, so it does not show the referenced wall-padding condition. D2.5 also leaves the wall-padding attachment reference as “DETAIL XX, SHEET XX.”

Why it matters

The mounting and home-run-wall instructions cannot be followed through the printed detail references.

Recommended fix

Replace the incorrect and placeholder references on D2.3 and D2.5 with the intended wall-padding details, and include the referenced mounting information in the set.

LowCivil · Landscape#62D4.1 refers the tree grate to a sheet that is not in the setD4.1 · C7.1

Detail A/D4.1 refers the tree grate to material plan CS-702. The submitted drawing set has material plans C7.1 and C7.2, but no CS-702. C7.1 item 32 refers back to A/D4.1, so the reference does not lead to additional grate information.

Why it matters

The tree-grate reference cannot be followed to its intended material information.

Recommended fix

Correct the CS-702 reference to the intended sheet and provide any grate information it is meant to supply.

LowArchitectural#63A6.21 uses three keynote codes without definitionsA6.21

The wall sections on A6.21 use keynote codes 05.01, 05.02 and 08.61. The sheet’s keynote list is empty, and no definition of these three codes was found elsewhere in the submitted drawing set.

Why it matters

The section references do not identify the intended requirements for the tagged elements.

Recommended fix

Add the definitions for 05.01, 05.02 and 08.61 to A6.21 and check that each leader identifies the intended element.

LowArchitectural#64The Kalwall and mural keynote leaders are swapped on A5.11A5.11

On the south elevation of A5.11, the 08.31 leader points to the painted mascot and the 09.87 leader points to the clerestory panel. The keynote list defines 08.31 as the Kalwall panel assembly and 09.87 as the wall mural. The two leaders identify the opposite elements.

Why it matters

The elevation assigns the panel-system and mural notes to the wrong surfaces.

Recommended fix

Correct the leaders so 08.31 identifies the Kalwall panel and 09.87 identifies the mural.

LowArchitectural#65GN149 wall and bench are labeled as restroom signsA8.12

In 8/A8.12, GN149 west elevation, two 10.20 leaders point to the bench and the masonry wall. The same sheet defines 10.20 as a UNISEX RESTROOM ID WALL SIGN. These leaders therefore assign a sign to two different building elements.

Why it matters

The elevation gives the wrong material or accessory instruction at the wall and bench.

Recommended fix

Correct the two keynote leaders to identify the intended bench and wall, using the coordinated material and furniture definitions.

LowArchitectural#66A5.12 labels downspouts as guttersA5.12 · A5.11

The west and east elevations on A5.12 use keynote 07.82 for downspout components. The same sheet defines 07.82 as GUTTER; A5.11 separately defines 07.84 as DOWNSPOUT.

Why it matters

The drainage component is identified inconsistently between the elevations and the keynote legends.

Recommended fix

Correct the downspout leaders on A5.12 and include the coordinated downspout keynote definition.

LowArchitectural#67Toilet and service-sink diagrams point to drinking-water fixture keynotesA10.71

In the typical mounting-height details on A10.71, the wall-mounted water closet is labeled 22.07. The same sheet defines 22.07 as an accessible hi-lo drinking fountain.

The service sink is labeled 22.09, but that keynote is defined as an accessible bottle filler.

Why it matters

The fixture illustrations and their keynote definitions direct the reader to different plumbing fixtures.

Recommended fix

Correct both diagram keynotes and coordinate the definitions with the water-closet and mop-sink tags used on A2.11 and A8.13.

LowArchitectural#68The section callout on A2.11 has overlapping sheet numbersA2.11

The west-side section callout on A2.11’s FLOOR PLAN prints A6.12 and A6.14 over each other beneath section number 1. The overlapping last digit makes the destination sheet ambiguous.

Why it matters

The reader cannot follow the section reference reliably.

Recommended fix

Remove the superseded sheet number and leave one clear reference to the intended section.

LowArchitectural#69Two door-frame notes on A10.21 end without a detail referenceA10.21

Details 4, EXTERIOR DOOR HEAD/ JAMB @ CMU, and 5, EXTERIOR DOOR HEAD @ LOUVER, on A10.21 each state “FOR FRAME DIMENSIONS AND DETAIL, SEE”. In both details, the note ends without a detail number, sheet number or reference bubble.

Why it matters

Readers must infer which detail governs the exterior door-frame dimensions.

Recommended fix

Complete both notes with the intended frame-dimension detail reference.

LowMechanical · Plumbing#70Mechanical and plumbing schedules refer to absent detail sheetsM0.02 · P0.02

M0.02 refers the exhaust fan to X/M5.01 for mounting and X/M6.01 for controls, and the radiant panels to --/M5.01 for mounting. P0.02 refers the water heater and expansion tank to x/P5.01.

The submitted 109-sheet drawing set was checked: M5.01, M6.01 and P5.01 are absent, and the detail numbers remain placeholders. These schedule references cannot be followed.

Why it matters

Readers cannot reach the installation information named by the schedules and must obtain clarification of the intended references.

Recommended fix

Replace the placeholders with valid detail references and include the referenced sheets, or revise the schedules to identify the applicable manufacturer instructions and general notes.

LowGeneral · Civil · Structural · Electrical#71Master and discipline sheet indexes disagree with the submitted setG0.11 · C0.0 · S1.00 · E0.1

G0.11’s SHEET INDEX lists the offsite detail sheets as D1.01–D1.03 and the structural cover as S0.00. C0.0’s offsite index uses D1.1–D1.3, and S1.00’s structural index identifies the cover as S1.00. E0.1’s electrical index omits the bound sheets E0.3, E3.1, E3.2, E4.1, E4.2 and E6.1, all listed in G0.11. It also lists E5.5, which is absent from G0.11 and the submitted 109-sheet set. These lists give inconsistent identifiers and coverage for the submitted drawings.

Why it matters

A reader using the indexes cannot reliably reconcile the named sheets and confirm the electrical drawing inventory.

Recommended fix

Make the master and discipline indexes agree with the sheet numbers and drawings included in this submission.

LowStructural#72The cold-formed steel legend on S1.02 gives incorrect conversion instructionsS1.02

The cold-formed steel member legend on S1.02 says thickness callouts are in “1/1000 MILS,” although its next line correctly defines 1 mil as 1/1000 inch.

Its 1⅝-inch width example also incorrectly multiplies 1.625 by 1/100 instead of converting a hundredths-of-inch designation.

Why it matters

The conversion instructions misstate how the member width and thickness designations are read.

Recommended fix

Correct the thickness unit to thousandths of an inch and replace the erroneous width example with a conversion that matches the legend.

LowCivil#73The grading notes leave their existing-grade source blankC4.1 · C4.2 · C1.1

Note 1 on both C4.1 and C4.2 leaves blank the source on which the existing grades are based. C1.1 names the aerial and topographic survey provider, but the grading notes do not identify their selected source.

Why it matters

The grading notes do not state which source was used for the existing elevations.

Recommended fix

Complete note 1 on both grading sheets with the survey or other information used as their basis.

LowCivil#74D2.2 gives conflicting rules for cleanout openings through the turfD2.2

Synthetic-turf note B-5 on D2.2 says quick couplers are the only utilities to be cut through the turf. Note F-2 on the same sheet permits both quick couplers and cleanouts. The notes give different rules for cleanout access.

Why it matters

The turf installer receives conflicting instructions about cutting access openings at cleanouts.

Recommended fix

Make the turf-cutout notes agree on whether and where cleanout openings are required.

LowElectrical#75The vertical spill-light calculation uses a different height from the specificationE5.2 · Spec 26 56 68

The calculation summary on E5.2 reports maximum vertical illuminance for "Project Spill @ 5ft". Section 26 56 68, paragraphs 1.3B and 1.3C, require the vertical spill-light scan at 3 feet above grade. The 5-foot result does not demonstrate compliance at the specified height.

Why it matters

The submitted vertical spill-light result cannot be compared directly with the specified 3-foot acceptance criterion.

Recommended fix

Provide the vertical spill-light calculation at 3 feet above grade and update the summary and supporting scan.

LowElectrical#76The softball outfield calculation uses fewer grid points than specifiedE5.3 · Spec 26 56 68

The Softball Illuminance report on E5.3 uses 73 outfield calculation points. Section 26 56 68, paragraph 1.2A, requires at least 75 outfield grid points. The submitted calculation therefore does not use the specified minimum sampling count.

Why it matters

The softball outfield calculation does not demonstrate lighting performance on the required sampling grid.

Recommended fix

Revise the softball outfield calculation to include at least 75 points at the specified spacing, or coordinate an approved alternative calculation basis.

LowArchitectural#77Keynote 12.63 refers to a furniture schedule that is not providedA8.11

A2.11 and the restroom elevations on A8.11–A8.13 use keynote 12.63 for furniture and refer to a “FURN SCHEDULE.” No furniture schedule is included in the submitted drawing set. The tagged furniture therefore cannot be resolved through the stated reference.

Why it matters

The referenced furniture selections are unavailable for coordinating the room layouts and procurement.

Recommended fix

Provide the furniture schedule for keynote 12.63 or replace the reference with the intended furniture requirements.

LowElectrical#78The photometric views have inconsistent scale and north indicatorsE3.1 · E3.2 · D2.3 · E2.1

E3.1 and E3.2 label their photometric site views at 1/2 inch = 1 foot. The plotted court geometry is about one-twelfth that scale. For example, the 78-foot tennis court dimensioned in G/D2.3 is drawn about 3.25 inches long on E3.1; at the stated scale it would be 39 inches long.

E3.1 also shows the same courts rotated about 79 degrees from E2.1, while both views show the same unqualified north arrow pointing up the page. The arrows therefore indicate different north directions for the same site without identifying a different north basis.

Why it matters

The scale captions give incorrect measured distances, and the inconsistent north arrows make orientation between the electrical and photometric views unclear.

Recommended fix

Correct both scale captions to match the plotted views, or label the views not to scale if measurement is not intended. Coordinate the north arrows with the site geometry, or clearly distinguish any intended plan-north and true-north conventions.

LowCivil#79The upper tee in G/D4.2 is labelled as an elbowD4.2

G/D4.2, “Techline Start Connection (PVC to Tee),” shows the upper fitting joining dripline to the left, right and below. Its leader calls that three-way fitting “TECHLINE ELBOW.”

Why it matters

The fitting label does not match the connection drawn.

Recommended fix

Correct the upper fitting label to match the tee shown in G/D4.2.

Questions, answered

FAQs

Is this a real review?

Yes, an anonymous one. These are the findings from a Groundbook review of a 50% construction documents set for a school athletic complex, completed in September 2026.

What did Groundbook review?

A 109-sheet drawing set covering civil, site details, structural, architectural, mechanical, plumbing, and electrical work, plus the 591-page project manual. Groundbook compared the sheets with each other and with the specification sections they rely on.

How do I check a finding?

Each finding names the sheets and specification sections it relies on. In Groundbook, each reference opens the page with the cited text highlighted, like the excerpts on this page, so a reviewer can confirm or dismiss it without searching the set.

Are these confirmed errors?

They are findings for the design team to review. Some may be intentional or resolved elsewhere; the cited evidence lets the responsible designer decide which ones need a change.

Can I run a review like this on my project?

Yes. Upload your drawing set and specifications and Groundbook checks them together. Pay per project.

Bring your next set into focus

Set up a review or talk through your project with our team.

Get a report like this on your own set

Trusted by hundreds of professionals

Product screenshot