The drawings add a basement level the soil report never assessed, and dig sump pits below the raft it limits.

The basement and ground-floor drawings for a residential building over four basement levels and an automated parking system were read against the soil report and the waterproofing details, and the excavation, the pits and the shafts are drawn differently from what the report and the other disciplines allow.

  • Soil report compliance
  • Deep basement excavation
  • Shoring piles
  • Sump pits
  • Basement waterproofing
  • Smoke exhaust shafts
  • Document health
120 pagesBasement drawings, waterproofing details and soil report
Code check enabledCoordination and code-reference checks
30 findingsPotential issues surfaced for verification
12 examplesConcise review details below

Deep basement and soil report

Architectural, structural, plumbing and drainage, electrical, HVAC and elevation drawings for four basement levels and the ground floor of a residential building, with the waterproofing detail book, read against one another and the soil investigation report supplied as a reference.

What the review compared

The review read the architectural, structural, plumbing and drainage, electrical and HVAC plans for four basement levels and the ground floor of a residential building, its elevations and the waterproofing detail book, with the soil investigation report supplied as a supporting reference. Its instructions asked for coordination conflicts, missing or inconsistent information and code concerns likely to cause permit comments, RFIs or field rework, with a document health check. Code checking was enabled.

Where the drawings outrun the soil report

The soil report was written for a shallower basement. The drawings add a general basement level below it, dig three sump pits and the automated parking pit below the raft, and note shoring piles around the pits shallower than the report requires, while the report asks its engineer to review any of these changes. Between the disciplines, two plumbing sump pits sit where the raft is continuous, two of three pump panels on one level have no feed, smoke shafts rise over the shoring wall with no slab openings, and slab bars cross a membrane the waterproofing details show unbroken.

What to verify next

The structural engineer should send the planned basement, raft, pit and excavation levels to the geotechnical engineer for an updated report before shoring and foundations are built, then settle the pits, shafts and waterproofing connections with the plumbing, HVAC and waterproofing consultants in one revision. Examples that cite a requirement follow the soil report and the fire regulations the review cited; every example is a question for the responsible designers and the authority having jurisdiction.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

Soil report assumes one basement fewer

The drawings add a basement level below the lowest floor the soil report assessed.

Why it matters: The report requires a new review when excavation deepens.

What to check: Send the levels to the geotechnical engineer for an update.

Structural · Architectural
02High priority

Sump pits go below the raft

Three sump pits on the structural plans extend below the raft underside.

Why it matters: The soil report forbids excavation below the raft.

What to check: Obtain the geotechnical engineer’s written review, or raise the pits.

Structural · Plumbing
03High priority

Shoring piles at the pits are short

A plan note embeds shoring piles below the pits less than the report requires.

Why it matters: Piles could be drilled too short.

What to check: Set the depth from the report, or obtain written approval.

Structural
04High priority

Parking pit has no perimeter shoring

The raft steps down to the automated parking pit with no shoring around it.

Why it matters: The report requires shoring around a pit this deep.

What to check: Add the shoring, or obtain written approval.

Structural
05High priority

Plumbing pits are not where structure puts them

The plumbing plan places two sump pits where the structural raft is continuous.

Why it matters: Pits, pumps and piping would be built in different places.

What to check: Redraw the pits at the agreed locations.

Plumbing · Structural · Architectural
06High priority

Smoke shafts sit on the shoring wall

Four smoke exhaust shafts rise over the perimeter wall and piles; the slab has no openings.

Why it matters: The shafts cannot be built as drawn.

What to check: Move the shafts inside and add the slab openings.

Mechanical · Structural · Architectural
07Medium priority

Parking smoke shaft is undersized

The parking smoke shaft and its intake grilles are smaller than the cited fire regulations require.

Why it matters: They would grow at permit review.

What to check: Enlarge them, or cite an engineering analysis the fire authority approved.

Mechanical · Fire Protection
08Medium priority

Slab bars pierce the waterproofing

Slab anchor bars into the shoring piles cross a membrane the waterproofing details show unbroken.

Why it matters: Each bar becomes an unsealed leak path.

What to check: Detail a connection that avoids or seals the membrane.

Structural
09Medium priority

Water tank joint detailed two ways

Structural and waterproofing details give the tank’s floor-to-wall joint different pour joints and waterstops.

Why it matters: The contractor cannot tell which joint to build.

What to check: Agree one joint and update both details.

Structural
10Medium priority

Two pump panels have no power

Plumbing shows three sump pump panels on one level; electrical feeds only one.

Why it matters: Two pits would be built without power to their pumps.

What to check: Feed every pump panel the plumbing plan shows.

Electrical · Plumbing
11Medium priority

Section marks point to missing details

Five section marks on the structural plans refer to details no sheet contains.

Why it matters: Walls at the shoring edge cannot be built from the set.

What to check: Issue the details, or redirect the marks to existing ones.

Structural
12Low priority

Sprinkler spacing written as a minimum

A plumbing note calls one sprinkler spacing a minimum; the next clause makes it a maximum.

Why it matters: Read literally, it requires sprinklers too far apart.

What to check: Change minimum to maximum in that clause.

Plumbing · Fire Protection

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Structural, Plumbing, Mechanical, Electrical, Architectural, and Fire Protection

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your basement drawings against the soil report

Trusted by hundreds of professionals