Ducts drop from the roof units to the ground floor, but the ground-floor HVAC plan is blank.

The drawings for a two-storey laboratory annex linked to an existing hospital by a bridge were read across architecture, ceilings, HVAC, storm drainage, fire extinguishers, fire alarm, security and data, and several systems are drawn at different levels, by different routes or not at all.

  • Healthcare laboratory
  • Floor and roof levels
  • Storm drainage inverts
  • Low-voltage systems
  • Egress doors
  • Fire extinguishers
  • Document health
30 pagesMultidiscipline drawings
Code check enabledCoordination and code-reference checks
34 findingsPotential issues surfaced for verification
14 examplesConcise review details below

Hospital laboratory annex

Architectural plans, sections and elevations, ceiling plans and details, HVAC, storm drainage, lighting, fire extinguisher, fire alarm, CCTV, access control, voice and data, and audio and video drawings for a hospital laboratory annex, read against one another and the building and workplace safety regulations the review cited.

What the review compared

The review read one drawing package for a two-storey laboratory annex joined to an existing hospital by a bridge: architectural plans, sections, facade sections and elevations, ceiling plans and details, the HVAC layout, storm drainage plans, the lighting study, the fire extinguisher plans and the fire alarm, CCTV, access control, voice and data, and audio and video drawings, including the routes that connect the annex to the hospital. Its instructions asked for missing or inconsistent information across disciplines, the information needed for permitting, pricing and construction, and document health issues such as missing sheets and broken references. Code checking was enabled, so egress doors, accessibility, stairs and extinguishers were also read against the building and workplace safety regulations the review cited.

Where the disciplines part ways

Levels are the common thread. The HVAC and drainage sheets put the roof slab above the level the architectural plans and sections give, the storm drainage plan states its inverts on a different datum from its own floor levels, and the exterior grade and a toilet floor differ from the architectural plan. The roof plan gives one parapet a level below the upper floor, and general notes repeated across the consultant sheets state levels in two different units. The ground-floor HVAC plan is blank although ducts drop to it. The links to the hospital are routed differently on different sheets or not drawn at all, and two cable schedules describe cabling the system does not use. The bridge slabs are still marked pending, and an exit door, a doorway step, the toilet door, a missing handrail and extinguisher spacing raise permit questions.

What to verify next

The architect should fix the roof, floor and exterior levels and the north point, and every consultant should redraw from that base. The HVAC engineer needs to complete the ground-floor plan and equipment schedule, the drainage designer needs to restate the inverts on the building datum, and the low-voltage designer needs to draw each link to the hospital once, with its cable. Examples that cite a requirement follow the regulations the review cited; every example is a question for the responsible designer and the authority having jurisdiction.

14 selected examples from the review

Fourteen distinct findings, summarized for professional verification.

01High priority

Ground-floor HVAC plan is blank

Roof unit and exhaust ducts drop to the ground floor; its HVAC plan view is empty.

Why it matters: Ground-floor ducts, outlets and exhaust cannot be priced or built.

What to check: Draw the ground-floor ductwork, outlets and airflows.

Mechanical
02Medium priority

Roof slab set at two levels

HVAC and drainage sheets set the roof slab higher than the architectural plans and sections.

Why it matters: Equipment bases and roof drains would follow different slab levels.

What to check: Confirm one roof level and correct every sheet.

Architectural · Mechanical · Plumbing
03Medium priority

Storm inverts on a different datum

Manhole covers and inverts carry negative levels beside positive floor levels on one sheet.

Why it matters: Excavation depths and cover levels cannot be set.

What to check: Give inverts on the building datum, or note the benchmark.

Plumbing
04Medium priority

Collector arrives below the manhole outlet

The last storm collector reaches its manhole lower than the manhole floor and outlet.

Why it matters: The final run cannot drain by gravity as drawn.

What to check: Lower the manhole and outlet, or regrade the collector.

Plumbing
05Medium priority

Alarm link to the hospital routed two ways

Two fire alarm sheets route the link differently, and neither shows the vertical run.

Why it matters: The installer cannot price or trace the interconnection.

What to check: Unify the route and draw the riser.

Fire Protection
06Medium priority

Network link scheduled as power cable

The network link sheet’s legend and cable schedule describe power cabling, not data cable.

Why it matters: The link cannot be priced, and power cable could be ordered.

What to check: Schedule the data cable type and count.

Electrical
07Medium priority

Magnetic-lock doors miss two cables

Runs to magnetic-lock doors omit the lock power and door sensor cables the legend defines.

Why it matters: Access control wiring would be priced incomplete.

What to check: Add both cables and recheck conduit size.

Electrical
08Medium priority

Bridge exit door narrow and unrated

The upper-floor exit to the bridge is a plain glass door below the cited width.

Why it matters: The door would need replacing for the permit.

What to check: Specify the cited width and fire rating.

Architectural
09Medium priority

Step at a ground-floor exit door

The sidewalk outside one exit door sits below the floor, with no ramp.

Why it matters: The cited rules require one level on both sides.

What to check: Match the levels or add a dimensioned ramp.

Architectural
10Medium priority

Only toilet door swings inward

The building’s only toilet opens inward; the cited rules require an accessible outward swing.

Why it matters: The building would lack a compliant accessible toilet.

What to check: Swing the door outward and dimension its width.

Architectural
11Medium priority

Freezer room too far from an extinguisher

Travel from the freezer room to the nearest extinguisher exceeds the cited limit.

Why it matters: The extinguisher plan fails a distance the permit checks.

What to check: Add an extinguisher inside the room.

Fire Protection
12Medium priority

Bridge slabs left pending

Both bridge slabs are labelled specification pending; no sheet gives their system or thickness.

Why it matters: The slabs and their bearings cannot be priced or built.

What to check: Define system, thickness and material on a structural sheet.

Architectural · Structural
13Low priority

Stair has no handrail

The only stair is walled on both sides, with no handrail drawn or detailed.

Why it matters: The cited standard requires a handrail here.

What to check: Draw the handrails and add a detail.

Architectural
14Low priority

North arrows point three ways

Architectural, fire protection and low-voltage plans each point north differently.

Why it matters: Elevation names and orientation references are unreliable.

What to check: Set true north and align every family.

Architectural · Fire Protection · Electrical

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Mechanical, Plumbing, Electrical, Fire Protection, and Structural

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your hospital set for levels, links and systems that disagree

Trusted by hundreds of professionals