The sloped glass roof over the dining room is tempered glass, with no screen or laminated lite beneath it.

The permit drawings for enclosing a restaurant patio with a sloped glass roof and curtain walls were checked before submission, and the overhead glazing, the structural design basis, the code data and the fire protection scope are not ready for plan review.

  • Restaurant
  • Patio enclosure
  • Sloped glazing
  • Curtain wall
  • Design loads
  • Occupant load
  • Permit readiness
15 pagesArchitectural permit drawings
Code check enabledCoordination and code-reference checks
18 findingsPotential issues surfaced for verification
12 examplesConcise review details below

Restaurant patio glass enclosure

Architectural permit drawings for a patio enclosure at an existing restaurant: code and area data, demolition plans, plans, elevations and sections of the glass roof and curtain walls, a glazing schedule and details, read against one another and the building, fire and energy code sections the review cited.

What the review compared

The review read the architectural permit drawings for enclosing an existing restaurant patio with aluminum-framed curtain walls and a sloped glass roof: code and area data, demolition plans, the enclosure plan, elevations, sections, a glazing schedule and details. Its instructions asked for missing or inconsistent information, drawings checked against specifications, missing compliance before permit and conflicts across disciplines. Code checking was enabled.

Where the set is not ready for plan review

The glass roof is the center of the project and the least resolved part of it. It is tempered glass over a dining area with nothing below it, it has no roof, snow or wind loads, and the elevations and section disagree on its height. Around it, the code sheet prints an altered area larger than the building, the title blocks certify to an outdated code edition and are unsigned, and the new room has no occupancy, occupant load, sprinkler or alarm scope, door schedule or energy compliance path. The glazing schedule and its own basis of design describe different glass.

What to verify next

The architect should settle the overhead glazing makeup and the roof geometry, have the structural design criteria added or the glass roof listed as a delegated design, and complete the code data for the enclosed room before submission. Examples that cite a requirement follow the building, fire and energy code sections the review cited; every example is a question for the architect, the engineer and the building department.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

Tempered glass overhead with nothing below

The sloped roof glass is tempered, with no screen or laminated inner lite shown.

Why it matters: A broken lite could fall onto diners below.

What to check: Use a laminated inner lite or add screens.

Architectural
02High priority

No design loads for roof or footing

No sheet gives roof, snow or wind loads, soil bearing or footing reinforcing.

Why it matters: The roof and footing cannot be checked to a known load.

What to check: Add the design criteria and reinforcing.

Structural
03High priority

Altered area larger than the building

The code sheet’s altered area is over three times the building area it lists.

Why it matters: As printed, the whole restaurant falls under new-building rules.

What to check: Recalculate both areas from the drawings.

Architectural
04Medium priority

Sprinkler and alarm work unassigned

The sprinklered building gains a roofed room; no sprinkler, alarm or deferred submittal is listed.

Why it matters: That work can drop out of bids and the permit.

What to check: Add it to the scope or defer it.

Fire Protection · Electrical
05Medium priority

No occupant load for the new room

The enclosure and the dining room exiting through it have no occupancy or occupant load.

Why it matters: Exits, hardware and egress lighting cannot be checked.

What to check: Add a code plan with loads and exits.

Architectural · Electrical
06Medium priority

Certified to an outdated code, unsigned

Every title block certifies to a code edition no longer enforced; signature lines are blank.

Why it matters: The set cannot be accepted for permit.

What to check: Cite the adopted codes, then seal and sign.

Architectural
07Medium priority

Roof heights differ by view

Elevations and a section through the same end give different wall and roof heights.

Why it matters: Roof slope and attachment height are unsettled.

What to check: Fix both heights and align every view.

Architectural
08Medium priority

Clear glass scheduled, tinted unit specified

The schedule calls clear tempered glass; the basis of design is a tinted low-e unit.

Why it matters: Bidders may price plain glass.

What to check: Name each type’s full insulating unit.

Architectural
09Medium priority

Energy compliance path missing

The heated glass room has no stated compliance path or framed-assembly U-factor.

Why it matters: The energy review cannot be completed.

What to check: State the path and assembly values.

Architectural
10Medium priority

New doors have no schedule

The legend’s door schedule sheet number is blank; both new doors lack size and hardware.

Why it matters: Exit doors cannot be checked or ordered.

What to check: Issue a schedule for both doors.

Architectural
11Medium priority

Index lists sheets never issued

The sheet index lists many more sheets than the set, including trades with no work.

Why it matters: Reviewers cannot tell what scope exists.

What to check: Match the index to the issued sheets.

Architectural
12Low priority

Rafter spacing label wider than drawn

A detail prints a wider rafter spacing than the roof plan and the detail draw.

Why it matters: Rafters laid out to the label would overrun the roof.

What to check: Correct the label and dimension the plan.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, Fire Protection, and Electrical

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your glass enclosure set before permit