Doors on a signed assembly exit route have no panic hardware.

The renovation set leaves gaps in assembly room egress, new accessible fixtures and the structure under a leveled floor.

  • Egress
  • Accessibility
  • Renovation structure
  • Lighting coordination
25 pagesRenovation bid drawings
Code check enabledCoordination and code-reference checks
35 findingsPotential issues surfaced for verification
7 examplesConcise review details below

Classroom renovation life safety

Architectural, structural and electrical renovation drawings for classrooms, nursing rooms and an assembly room in an existing building.

What the review compared

The review followed the code plan’s occupant loads and exits into the door schedule, hardware and electrical demolition, and traced the new nursing room and toilet fixtures from the plans into the enlarged elevations and accessibility diagrams.

Where the renovation needs answers

One assembly room exit loses its sign and other exit doors lack panic hardware. New sinks and a grab bar fall short of the accessibility requirements the review checked, and the structural sheets leave the new pier footings and floor leveling undefined.

What to verify next

The architect and engineers should confirm the exit hardware and signage, the accessible fixtures and the footing design before bidding. Code checking was enabled; the examples are questions for the responsible designers and the building official.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01High priority

Assembly exit doors lack panic hardware

Doors on a signed exit route from the assembly room have no panic hardware scheduled.

Why it matters: Occupants may not get the required panic release.

What to check: Schedule panic hardware on the doors along that route.

Architectural · Electrical
02High priority

An assembly room exit loses its sign

Demolition removes the exit sign at one assembly room exit and shows no replacement.

Why it matters: That exit would be unmarked after the work.

What to check: Show a new or retained exit sign at the door.

Electrical · Architectural
03High priority

New nursing room sinks have no knee clearance

New sinks in two nursing rooms sit over closed base cabinets.

Why it matters: A wheelchair user cannot pull under either sink.

What to check: Detail knee clearance at each sink or document an exception.

Architectural
04Medium priority

New pier footings have no embedment depth

New pier bases are drawn on the crawlspace surface with no depth below undisturbed ground.

Why it matters: Built as drawn, they would bear on surface soil.

What to check: Dimension the footing depth below undisturbed ground.

Structural
05Medium priority

Sink knee clearance is dimensioned as a maximum

The accessible sink diagram labels the knee-clearance height as a maximum rather than a minimum.

Why it matters: A sink installed to the label could sit too low.

What to check: Correct the dimension to a minimum.

Architectural
06Medium priority

Ceiling and lighting plans count fixtures differently

The ceiling and lighting plans show different fixture counts in four spaces.

Why it matters: Fixtures and the ceiling layout cannot be priced reliably.

What to check: Coordinate one fixture layout on both plans.

Architectural · Electrical
07Low priority

Fire alarm riser includes sprinkler switches

The riser calls for flow and tamper switch connections, but the code data lists no sprinklers.

Why it matters: Bidders may price devices that do not exist.

What to check: Confirm the sprinkler status and revise the riser.

Electrical · Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Electrical, and Structural

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check exits, hardware and accessible fixtures in your renovation set

Trusted by hundreds of professionals