The placing plan shows fewer top bars than the structural design.

Bar counts, base-mat sizes and localized reinforcement need reconciliation with the governing structural design.

  • Shop drawing review
  • Reinforcement placing
  • Design revisions
  • Connection details
15 pagesDesign and shop drawing set
Coordination reviewCoordination and completeness within the set
25 findingsPotential issues surfaced for verification
6 examplesConcise review details below

Concrete reinforcement shop drawings

Concrete deck reinforcing shop drawings compared with structural design drawings, general notes and cited design changes.

What the review compared

The review compared concrete reinforcing placing plans with structural design plans, legends and connection details. At one column, the placing plans showed fewer top bars in both directions. A separate base-mat callout used smaller bars than the design.

Why the revision matters

Some shop drawing details relied on design changes absent from the supplied design set. The review requested the governing revision and identified unresolved placing information for support embeds, curtain-wall anchors and future infill connections.

What to verify next

The structural engineer and reinforcing detailer should reconcile the comments against the governing design and identify any separate placing packages. This coordination review did not enable code checking. The comments do not establish fabrication approval.

6 selected examples from the review

Six distinct review comments, summarized for professional verification.

01Medium priority

Governing design revision is missing

The shop drawing review cites approved changes absent from the supplied design set.

Why it matters: Changed reinforcement and connections cannot be verified.

What to check: Provide the governing revision and referenced details.

Structural
02Medium priority

Column top-bar counts are lower

The placing plans show fewer top bars in each direction than the structural design requires.

Why it matters: Column reinforcement does not match the supplied design.

What to check: Reconcile the bar counts or identify an approved change.

Structural
03Medium priority

Base bottom bars are smaller

A base-mat callout uses smaller bars than the referenced structural design.

Why it matters: The reinforcement callout differs from the design.

What to check: Correct the base bars while retaining the separate additional bars.

Structural
04Medium priority

Embed reinforcement lacks placing callouts

Required local bars around transfer-slab support embeds are not identified in the placing plans.

Why it matters: Embed reinforcement cannot be traced.

What to check: Locate the bars and required edge hooks, or identify their placing package.

Structural
05Medium priority

Curtain-wall hairpins lack coordinated locations

Required hairpin reinforcement is not identified at the applicable curtain-wall mullions.

Why it matters: Anchor reinforcement locations remain unresolved.

What to check: Confirm mullion locations and identify the reinforcement or separate placing package.

Structural
06Medium priority

Future-opening connections are not located

The plan does not clearly locate matching cast-in connection sets for future infill.

Why it matters: Future threaded-bar connections cannot be verified.

What to check: Provide the governing detail and locate the matching sets on every opening side.

Structural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Structural

Check the findings with the responsible discipline designers.

02 · Priorities

Medium and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Related examples and workflows

Apply this review to your project

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Compare reinforcing shop drawings with the structural design

Trusted by hundreds of professionals