Guide · Review process

Close submittal comments against the revised evidence

A response saying “addressed” is a starting point. Close a comment when the revised package supports the agreed correction and the affected interfaces agree with it.

Keep a stable comment ID. Read the original requirement, the contractor’s response and the changed source together, then record closed, partially addressed, open or awaiting a decision using the project’s agreed status terms.

Assemble the three records

Collect the returned package, the response log and the resubmitted files. Keep the drawings and specifications that governed the original review available. If the design changed between reviews, establish that new baseline before deciding whether the contractor corrected the original problem.

Retain the submitted revision and page reference for each comment. A replacement cover sheet can make an unchanged attachment look new. Compare the technical page rather than relying on the transmittal date.

A response is not the closure evidence

For a hypothetical pump submission, a reviewer asks for the selected motor voltage to agree with the electrical schedule. The response says “revised to match,” but the revised catalog still shows several voltage options. The item remains open until the proposed option is identified and compared with the governing schedule.

If the voltage changes, backcheck the starter, circuit, controls and power assumptions. A correction can solve the first comment while leaving a dependent document inconsistent. Record the exact proposed selection and the reviewer’s decision.

Record partial answers clearly

Use one row for one decision. A response may resolve the equipment rating but leave mounting dimensions unanswered. Preserve both parts of the original question and state what remains to be supplied. Avoid closing a compound comment because one attachment was added.

Where a comment requires a design decision, route it to the person authorized to make that decision. The backchecker should be able to read the answer, the accepted change and the verified revision without reconstructing an email chain.

Use the closure worksheet

Use the closure worksheetSwipe or scroll sideways to read all columns.
CheckSourcesReview question
Review baselineOriginal submission, returned comments, governing designCan you identify the exact package and design issue reviewed last time?
Comment identityOriginal log and new response tableDoes every prior comment retain its ID and an answerable response?
Claimed changeResponse wording and revised pageIs the described correction visible at the stated location?
Selected optionRevised product data and equipment scheduleIs the corrected model or option actually selected?
Related commentsOther comments on the same itemDoes one correction resolve the whole condition or leave another question open?
Trade interfacesRevised dimensions, connections and receiving designDid the correction reach the disciplines that depend on it?
New departuresRevision list, prior package and current packageDid the resubmission introduce an unreviewed substitution or requirement?
Closure decisionVerified source, reviewer and dispositionWho confirmed closure, on which revision, with which remaining conditions?

Keep the review history useful

Preserve the prior package and the current one with the log. Record the reviewer, verification date and closure evidence. Use the submittal log for package dates and dispositions, and this worksheet for the technical comments within that package.

The reinforcing shop-drawing case shows why the local bar groups and governing design must be compared. It supplies a real review example; it does not establish that the contractor later completed a correction.

Project procedure and document review

UFGS 01 33 00 is a federal example of submittal procedures. Follow the issued project procedure for your review actions. Source checked October 13, 2026.

Include prior comments as references when defining a shop-drawing review. Groundbook can help compare supplied documents; your reviewer verifies the response and records the final disposition.

Questions, answered

FAQs

Is a resubmittal the same as a new submission?

It is a new issue of an existing package. Keep the package identity and prior comments so the reviewer can backcheck the response.

Can I mark a comment closed from the response letter alone?

Check the changed evidence and dependent documents first. A response letter can identify a change without proving the submitted package contains it.

Does this worksheet automatically maintain the project log?

No. It is an editable CSV for your reviewers to complete and retain with the reviewed documents.

Backcheck your revised submittal package

Compare the new package with the prior comments and governing design. Groundbook flags potential conflicts with links to the source sheets.

Backcheck your revised submittal package

Trusted by hundreds of professionals