Two of the three parapet roofs have no overflow scupper, and the third roof’s sits away from its low point.

The construction drawings for a single-family house with flat parapet roofs, insulated concrete form walls and a steel canopy were checked before permit, and the roof drainage, the parapet and roof assemblies and several structural members disagree across sheets.

  • Single-family house
  • Parapet roofs
  • Overflow scuppers
  • Insulated concrete forms
  • Roof assembly
  • Steel canopy
  • Permit readiness
18 pagesArchitectural and structural drawings
Code check enabledCoordination and code-reference checks
19 findingsPotential issues surfaced for verification
12 examplesConcise review details below

House parapet roof drainage

Architectural and structural construction drawings for a single-family house: plans, a roof plan with drainage notes, building and wall sections, elevations, and foundation, header, roof framing and canopy sheets, read against one another and the residential code sections the review cited.

What the review compared

The review read the construction drawings for a single-family house with flat parapet roofs, insulated concrete form walls and a steel slat canopy: plans, the roof plan and its drainage notes, building and wall sections, elevations, and the foundation, header, roof framing and canopy sheets. Its instructions asked for missing or inconsistent information, drawings checked against specifications, missing compliance before permit and conflicts across disciplines. Code checking was enabled.

Where the roof and walls part ways

Most of the high findings sit at the roof edge. Two of the three parapet roofs have no overflow, the third roof’s scupper is away from its low point, and the elevations draw none of the outlets the roof plan calls. The parapet is wrapped in a vapor barrier where the cited section asks for a permeable cover, and the wall section packs more insulation into the roof bays than the scheduled joists can hold, on a thinner deck than the structural sheets call. The canopy beam has three sizes, and a curb detail swaps its level and sloping ledgers.

What to verify next

The architect should place an overflow at each roof’s low point and show every outlet on the elevations, settle the parapet cover with the building official, and redraw the wall section to the structural deck, joists and lintels; the engineer should confirm the canopy beam size. Examples that cite a requirement follow the residential code sections the review cited; every example is a question for the designer, the engineer and the building department.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

Overflow missing on two roofs

Two parapet roofs have no overflow scupper; the third roof’s sits away from its low point.

Why it matters: Blocked drains could pond water on the roofs.

What to check: Add scuppers at each roof’s low point.

Architectural · Plumbing · Structural
02High priority

Vapor barrier wraps the parapet

The plastered parapet is wrapped in a butyl membrane; the cited section requires a permeable cover.

Why it matters: Moisture can be trapped in the parapet.

What to check: Specify a permeable cover or seek approval.

Architectural
03High priority

Canopy beam sized three ways

The schedule, connection details and building section give the canopy beam three tube sizes.

Why it matters: Connections may be detailed for another tube.

What to check: Confirm one size on every sheet.

Structural · Architectural
04Medium priority

Roof insulation deeper than the joists

The wall section fills the roof bays with insulation deeper than the scheduled joists.

Why it matters: The drawn R-value cannot fit.

What to check: Revise the assembly and restate R-values.

Architectural · Structural
05Medium priority

Section calls another deck and header

The wall section shows thinner roof sheathing and a wood header where structure calls concrete lintels.

Why it matters: Framers could build to the wrong section.

What to check: Match deck and lintel to the structural sheets.

Architectural · Structural
06Medium priority

Level and sloping ledgers swapped

A curb detail labels the level and sloping ledgers the reverse of the curb sections.

Why it matters: Hung joists could sit on a sloping ledger.

What to check: Swap the labels to match the sections.

Structural · Architectural
07Low priority

Thermal barrier over foam not named

The interior layer over the foam wall forms is unlabelled where plaster is the finish.

Why it matters: The required thermal barrier may be left out.

What to check: Label gypsum board or a listed barrier.

Architectural
08Low priority

Drainage note mislabels the roofs

The drainage note labels both side roofs east and misstates two flow figures.

Why it matters: Downspout sizing cannot be traced.

What to check: Correct the labels and flows.

Architectural · Plumbing
09Low priority

Porch wall is block and form

One detail calls a porch wall concrete block; another calls it an insulated concrete form.

Why it matters: The ledger anchor’s base material is unclear.

What to check: Name one wall type and its anchor.

Structural
10Low priority

Revision clouds with no record

Revision clouds appear on several sheets; no revision block lists that revision.

Why it matters: Reviewers cannot tell what changed.

What to check: Add the revision and issue dates.

Architectural · Structural
11Low priority

Callouts to sheets not in the set

Plans cut sections on two sheets the sheet list does not include.

Why it matters: Those sections cannot be found.

What to check: Retarget the callouts or add the sheets.

Architectural · Structural
12Low priority

Elevations omit drainage outlets

Elevations point to scuppers but draw no scuppers, conductor heads or downspouts.

Why it matters: Outlets cannot be located on the walls.

What to check: Draw them at roof-plan positions.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, and Plumbing

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass