The storefront glazing, the barricade and the fire alarm system are each assigned to two different parties in the same bid set.

The bid set for a retail store remodel in a shopping mall was checked for scope gaps, overlaps and pricing information before bids, and several major packages have two owners while structural supports the architecture relies on are not designed.

  • Mall retail store
  • Remodel
  • Bid set
  • Scope overlaps
  • Storefront
  • Structural supports
  • Bid leveling
160 pagesBid set drawings
Code check enabledCoordination and code-reference checks
90 findingsPotential issues surfaced for verification
12 examplesConcise review details below

Mall store bid set scope

A bid set of architectural, structural, mechanical, electrical, plumbing and fire protection drawings for a retail store remodel in a shopping mall, with the responsibility schedule, specification sheets and energy compliance forms, read against one another and the code sections the review cited.

What the review compared

The review read the bid set for a retail store remodel in a shopping mall: architectural, structural, mechanical, electrical, plumbing and fire protection sheets, the responsibility schedule, specification sheets and the energy compliance forms. Its instructions asked for scope gaps and overlaps, conflicting pricing requirements, addenda and revision consistency, and the information needed for pricing and purchasing, without inventing costs, quantities or lead times. Code checking was enabled.

Where bids would not level

Several large packages have two owners. The storefront glazing, the storefront barricade, the fire alarm system and the HVAC disconnects are each assigned to different parties on different sheets, so bidders can carry them twice or not at all. Elsewhere, the architecture relies on structure that is not designed: a steel lintel at a bulkhead cut, a support for chandeliers heavier than the detail they point to, an air handler missing from the support plan, and hanger notes written for bar joists under a concrete plank floor. The mechanical energy compliance form bound into the set reports that it does not comply.

What to verify next

The owner and architect should assign every package once on the responsibility schedule and align the trade notes before bids are due. The structural engineer should design the lintel, the chandelier and air handler supports and a plank anchor detail. Examples that cite a requirement follow the documents and code sections the review cited; every example is a question for the design team.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

Storefront glazing has two buyers

Schedule rows give storefront glazing, mullions and trim to both the contractor and the owner’s vendor.

Why it matters: Bids may carry it twice or not at all.

What to check: Name one furnisher and installer.

Architectural
02High priority

Barricade built by two parties

The schedule gives the storefront barricade to the owner; general notes give it to the contractor.

Why it matters: It may be priced twice or by no one.

What to check: Name one party to build and remove it.

Architectural
03High priority

Fire alarm assigned to two contractors

Electrical notes give the fire alarm system to the electrical contractor and to the mall’s contractor.

Why it matters: The work may be carried twice or missed.

What to check: Name one party for design through testing.

Electrical · Fire Protection
04High priority

Bulkhead lintel never designed

A section calls a new steel lintel at a bulkhead cut; no structural sheet sizes it.

Why it matters: The lintel cannot be priced or fabricated.

What to check: Size and detail it before bids.

Architectural · Structural
05High priority

Chandeliers heavier than their support

Two chandeliers are tagged to a support rated below their weight; their own detail is unfinished.

Why it matters: Their support cannot be priced or installed.

What to check: Issue a support detail for that weight.

Architectural · Structural
06High priority

Main panel breaker rated two ways

The scope and the riser give different ratings for the landlord breaker feeding the main panel.

Why it matters: Whether it must be upsized, and by whom, is unclear.

What to check: State the rating and any change.

Electrical
07High priority

Disconnects assigned to different trades

Condensing unit, air handler and fan disconnects have different installers on different sheets.

Why it matters: Electrical and mechanical bids cannot be leveled.

What to check: Name one party per disconnect.

Mechanical · Electrical
08High priority

Support plan misses an air handler

The structural support plan omits one scheduled air handler and labels another unit twice.

Why it matters: Its hangers and bracing are outside the structural scope.

What to check: Add the unit and fix the labels.

Structural · Mechanical
09Medium priority

Hangers written for joists over plank

Hanger and fixture support notes assume bar joists; the floor above is concrete plank.

Why it matters: Each trade may price its own support method.

What to check: Issue a plank anchor detail.

Mechanical · Electrical · Structural
10Medium priority

Energy form reports noncompliance

The bid set’s mechanical energy compliance form reports two condensing units below the minimum efficiency.

Why it matters: Units or the form may change after award.

What to check: Select complying units or correct the form.

Mechanical
11Medium priority

Air handler without outdoor air

One air handler is scheduled for outdoor air, but the plan shows no duct or damper.

Why it matters: The duct and damper are outside every bid.

What to check: Draw the duct or revise the schedule.

Mechanical
12Medium priority

Window trim kept and removed

Demolition keeps the decorative window trim; storefront notes and the scope remove and re-install it.

Why it matters: Bidders cannot tell what to price.

What to check: State one treatment and align the notes.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, Mechanical, Electrical, Plumbing, and Fire Protection

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass