We’re at NCSEA in San Francisco, Oct 28–29 · Booth 110NCSEA · Booth 110 · Oct 28–29

The drawings replace the largest rooftop unit, but the responsibility schedule treats the HVAC as existing landlord equipment.

The construction set for a retail store fit-out in a shopping mall was read against its own responsibility schedule, and the largest new equipment, the demolition, the exit ramp and the store’s cabling either have no responsible party or have two.

  • Mall retail store
  • Tenant fit-out
  • Responsibility schedule
  • Owner-furnished items
  • Rooftop unit replacement
  • Fixture anchorage
  • Scope gaps
145 pagesFit-out construction drawings
Coordination reviewCoordination and completeness within the set
82 findingsPotential issues surfaced for verification
12 examplesConcise review details below

Mall store responsibility schedule

Architectural, structural, mechanical, electrical, plumbing, fire alarm, security and technology drawings for a mall store fit-out, with the responsibility schedule, technology matrix and specification sheets in the set, read against one another for scope gaps, owner decisions and cost risk.

What the review compared

The review read the construction set for a retail store fit-out in a shopping mall: architectural, structural, mechanical, electrical, plumbing, fire alarm, security and technology sheets, with the responsibility schedule, a technology responsibility matrix and the specification sheets. Its instructions asked for unresolved owner decisions, scope gaps, cross-discipline conflicts and cost or value-engineering risks. Code checking was not enabled.

Where the responsibility schedule and the drawings disagree

The schedule describes a lighter project than the drawings. It treats the HVAC as existing landlord equipment while the drawings replace the largest rooftop unit with new framing and a new curb, and it gives demolition, the prefabricated exit ramp and the electrified locks on an existing exit door to no one. Store cabling and racks belong to the owner’s vendor in one matrix and to the contractor in the specification. Elsewhere, tall wall fixtures point to anchorage drawn for shorter ones, one bay’s floor is not the floor the anchorage details assume, and the only rooftop unit specification describes different equipment.

What to verify next

The owner, landlord and architect should complete the responsibility schedule for every new item and every removal before bids are leveled. The structural engineer should tie each tall fixture and the metal-deck bay to an anchorage detail that fits them, and the mechanical engineer should specify the scheduled unit. Every example is a question for the design team before pricing.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

Largest new unit has no owner

The drawings replace a rooftop unit; the responsibility schedule treats the HVAC as existing.

Why it matters: The unit, curb and roof work may be missed or carried twice.

What to check: Assign who furnishes and installs it.

Architectural · Mechanical · Electrical · Structural
02High priority

Tall wall bays tagged to short anchorage

Tall custom wall bays point to an anchorage detail drawn for much shorter fixtures.

Why it matters: Their attachment and backing may be built wrong.

What to check: Tag them to the detail for their height.

Architectural · Structural
03High priority

Anchorage drawn for the wrong floor

Wall and fixture anchorage assumes plank floors; one bay is concrete on metal deck.

Why it matters: Anchors in that bay have no detail.

What to check: Add metal-deck details for that bay.

Structural
04Medium priority

Demolition assigned to no one

The responsibility schedule gives demolition no party; plans and notes require extensive removals.

Why it matters: Bidders can read demolition as outside the contract.

What to check: Name the party on the schedule.

Architectural
05Medium priority

Racks and cabling owned twice

The matrix gives racks and cabling to the owner’s vendor; specification and plans to the contractor.

Why it matters: They may be priced twice or not at all.

What to check: Choose one party and align the sources.

Technology · Security
06Medium priority

Exit ramp by others, with no other

The prefabricated exit ramp is “by others” and deferred, but no party furnishes or permits it.

Why it matters: The ramp may be left out of every price.

What to check: Add it to the schedule with a party.

Architectural · Structural
07Medium priority

Fire alarm panel new on one sheet

One keynote calls for a new fire alarm panel; the riser and specification keep the existing.

Why it matters: The fire alarm price may change substantially.

What to check: Decide new or existing and align the sheets.

Fire Protection · Electrical
08Medium priority

Slab leveling in base bid and alternate

Slab patching and leveling are base work in three notes and an add alternate in another.

Why it matters: Base and alternate prices cannot be compared.

What to check: Define the alternate and align the notes.

Architectural
09Medium priority

Unit specification for other equipment

The only rooftop unit specification covers small electric-heat units, not the large cooling-only unit.

Why it matters: Its submittal has nothing to match.

What to check: Add a section for the scheduled unit.

Mechanical
10Medium priority

Display platforms sent to missing details

Storefront platform details refer to structural drawings that do not show the platforms.

Why it matters: Their framing and attachment cannot be priced.

What to check: Detail the platform framing.

Architectural · Structural
11Medium priority

Plumbing notes cite another city’s code

The plumbing notes cite another city’s plumbing and fuel gas codes, not the listed code.

Why it matters: The plumber may price the wrong rules.

What to check: Replace them with notes for the adopted code.

Plumbing
12Medium priority

Existing exit door gets electrified locks

The security plan electrifies an existing stair exit pair whose hardware is scheduled as existing.

Why it matters: No bid carries the locks or power transfer.

What to check: Add a hardware group or drop the devices.

Security · Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, Mechanical, Electrical, Security, and Plumbing

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your responsibility schedule against the drawings

Trusted by hundreds of professionals