More than twenty crossings tagged on the plans have no row in the survey’s crossing table.

The final as-built survey of a new neighborhood’s sanitary sewer was read against the record-survey requirements in the utility’s standards manual, and several records the utility needs are missing or disagree.

  • As-built survey
  • Utility crossing separation
  • Force main and wet well
  • Manhole lining
  • Survey certification and accuracy
  • Sewer slopes and inverts
14 pagesAs-built survey drawings
Code check enabledCoordination and code-reference checks
18 findingsPotential issues surfaced for verification
8 examplesConcise review details below

Sanitary sewer as-built survey

A final as-built survey of a new neighborhood’s sanitary sewer: gravity main, manholes and laterals, a force main and a lift station wet well, with plans, profiles and manhole, fitting and crossing tables, read against the utility’s standards manual.

What the review compared

The review read the final as-built survey of a new neighborhood’s sanitary sewer: the cover and surveyor’s notes, the plans and profiles of the gravity main, laterals and force main, and the manhole, fitting and crossing tables. Code checking was enabled, and the utility’s standards manual was uploaded as a reference, so the records were read against its record-survey, lining and slope requirements and the state’s surveying standards the review cited.

What the survey does not record

More than twenty crossings tagged on the plans have no row in the crossing table, some printed rows do not compute, and the force main appears only as design linework. The third manhole up from the wet well has no lined label, and the final survey is unsigned, unsealed and undated, with no statement on the utility’s accuracies. Two inverts disagree where they decide a run’s minimum slope, two turning manholes record drops below the minimum, the wet well inlet has no as-built invert, and the horizontal control uses a superseded datum adjustment.

What to verify next

The surveyor should complete the crossing table, add the surveyed force main, state the accuracies and datum, and sign and seal the set before submittal. The engineer of record should settle the lining, slope and channel drop questions and take any variance to the utility for its written decision. Examples that cite a requirement follow the utility manual and rules the review cited, and every example is a question for the responsible professionals.

8 selected examples from the review

Eight distinct findings, summarized for professional verification.

01High priority

Crossings missing from the table

More than twenty crossings tagged on the plans have no table row, including water crossings.

Why it matters: Vertical separation there cannot be confirmed from this survey.

What to check: Add each crossing with pipes, elevations and measured separation.

Civil
02High priority

Force main has no as-built data

The force main stays gray design linework on every plan and profile.

Why it matters: Its route, valves and tie-in are not recorded here.

What to check: Add the surveyed force main, or name the survey covering it.

Civil
03High priority

Manhole near the wet well not shown lined

The manual requires the last three manholes lined; the third has no lined label.

Why it matters: No record shows whether it was lined.

What to check: Confirm and label the lining, or get the utility’s written decision.

Civil
04High priority

Final survey is unsigned and unsealed

The signature and date lines are blank, and the file carries no seal.

Why it matters: The cover says the survey is not valid without them.

What to check: Have the surveyor sign, seal and date the set before submittal.

Civil
05High priority

Survey has no accuracy statement

The manual requires a statement that the work meets its accuracies; no sheet gives one.

Why it matters: Nothing shows the inverts and coordinates meet the utility’s tolerances.

What to check: Add the statement or list each variance.

Civil
06Medium priority

Conflicting inverts decide minimum slope

Two sheets give one pipe end different as-built inverts; one puts the run below minimum slope.

Why it matters: The set’s notes say substandard slopes will not be accepted.

What to check: Recheck the field notes and print one invert everywhere.

Civil
07Medium priority

Short flow-line drops at turns

At two manholes turning flow over 45 degrees, recorded drops are below the required 0.1 foot.

Why it matters: As recorded, these channels need correcting or a written variance.

What to check: Recheck the inverts, then seek the utility’s decision.

Civil
08Medium priority

Datum uses a superseded adjustment

Horizontal control is on NAD83 (NSRS2007); the utility’s manual requires the 2011 adjustment.

Why it matters: The shift at the control monument exceeds the horizontal tolerance for mains.

What to check: Move the coordinates to NAD83 (2011), or obtain written acceptance.

Civil

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Civil

Check the findings with the responsible discipline designers.

02 · Priorities

High and Medium priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your as-built survey against the utility’s standards

Trusted by hundreds of professionals