The deduct alternate deletes the room holding the new switchboard.

The architectural sheets price a deduct alternate that the structural, electrical and other engineering sheets never mention.

  • Bid alternates
  • Pricing sets
  • Bid scope
  • Trade coordination
90 pagesPricing set
Coordination reviewCoordination and completeness within the set
50 findingsPotential issues surfaced for verification
7 examplesConcise review details below

School addition alternate pricing

A multi-discipline pricing set for a school addition, with code sheets, a deduct alternate and civil, structural and building-services drawings.

What the review compared

The review read the pricing set as a bidder would, looking for scope and pricing ambiguities, bid gaps and overlaps. It followed the deduct alternate through every discipline and compared code sheets, schedules and site plans that describe the same work.

Where the bids would diverge

The alternate is drawn on the architectural sheets only, so each trade would work out its own deduct and add-back. The code sheets give two construction types, and the civil and electrical site plans route the new power and gas service differently.

What to verify next

The architect and engineers should issue alternate notes for every discipline, settle the construction type and align the site utility routes before bids are due. This review did not enable code checking; the examples are questions for the responsible designers.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01High priority

Two construction types on two code sheets

The code sheets give different construction types and fire ratings for columns and roof.

Why it matters: Fireproofing and rated walls cannot be priced.

What to check: State one type, one rating set and one wall design.

Architectural
02High priority

Alternate exterior wall is undefined

The alternate makes a corridor wall exterior with no foundation, window types or door entry.

Why it matters: Bidders price the add-back work differently.

What to check: Issue the wall’s foundation, section and elevation.

Architectural · Structural
03Medium priority

Alternate deletes the switchboard room

The alternate removes the room holding the new switchboard; no electrical sheet shows its replacement.

Why it matters: Electrical bidders cannot price it.

What to check: Show the alternate electrical room and feeder.

Electrical · Architectural
04Medium priority

Engineering sheets never show the alternate

Plumbing, mechanical, fire protection and civil sheets do not mention the alternate.

Why it matters: Each trade will price its share differently.

What to check: List what each trade deletes and adds.

Plumbing · Mechanical · Fire Protection · Civil
05Medium priority

Roof drain note contradicts its plan

The alternate says drain count is unchanged; its roof plan adds one drain and moves others.

Why it matters: The deduct credit may be overstated.

What to check: List the added and moved drains.

Architectural · Plumbing
06Medium priority

Primary feed comes from two streets

Civil and electrical site plans bring the new primary feed from different streets.

Why it matters: Raceway and trenching cannot be priced.

What to check: Agree the route with the utility and match both plans.

Electrical · Civil
07Medium priority

Exterior doors have two materials

An exterior door pair is aluminum on the elevation and hollow metal in the schedule.

Why it matters: It may be priced twice or not at all.

What to check: State one material on both sheets.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, Civil, Mechanical, Electrical, Plumbing, and Fire Protection

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.