Commercial kitchen drawing review checklist

A food-service package is a schedule of equipment that four other disciplines have to serve. Almost every review question is a comparison between the equipment schedule and somebody else’s drawing.

Compare each equipment tag against its utility rough-in on the plumbing and electrical documents, then check hoods against the mechanical air quantities and the fire suppression interlock. Record disagreements with both references. Health, fire, and equipment selection decisions stay with the design team and the reviewing authorities.

Assemble a reviewable package

Collect the food-service equipment plan, schedule, and rough-in drawing, the plumbing and electrical plans serving the kitchen, the mechanical plans and air-balance schedule, the hood and fire suppression drawings, the fire alarm matrix, and the architectural floor sections.

Agree which areas and which design milestone are being reviewed, and record any document you expected and did not receive. A review can only compare what it is given, so a missing sheet is a finding in its own right. The drawing register template gives you somewhere to record the governing issue before you start.

Twelve document checks

Use one worksheet row per condition rather than per sheet. Where a condition repeats, note the locations you sampled and any exception you found. The CSV adds blank fields for the project location, source issue, reviewer, decision, revised sources, and closure evidence.

Commercial kitchen drawing review checklistSwipe or scroll sideways to read all columns.
Review areaSources to compareQuestion to resolve
Equipment identityEquipment plan, equipment schedule, specificationDoes each equipment tag resolve to one item with the same description, size, and location in every source?
Utility rough-inEquipment schedule, plumbing and electrical plans, rough-in drawingDo the connection type, size, and location for each item agree between the food-service and the MEP documents?
Electrical characteristicsEquipment schedule, panel schedules, connection notesDo voltage, phase, and load for each item match between the food-service schedule and the electrical documents?
Exhaust and makeup airHood schedule, mechanical plans, air-balance scheduleDo hood exhaust and makeup air quantities agree between the food-service and mechanical documents?
Hood and suppressionHood details, fire suppression drawings, fire alarm matrixIs each hood shown with its suppression system, and does the interlock appear in the fire alarm matrix?
Grease and wastePlumbing plan, interceptor schedule, site utility planCan grease waste be followed from each fixture to an interceptor and on to the site connection?
Floor constructionArchitectural sections, structural slab plan, finish scheduleAre depressions, drains, slopes, and finishes described consistently across the architectural and structural documents?
Walk-in coolersEquipment plan, refrigeration drawings, structural supportIs each walk-in shown with its condensing unit location, line routing, and structural support?
Clearances and accessEquipment plan, manufacturer clearance data, architectural planIs the service and code clearance around each item achievable in the layout shown?
Ventilation and comfortMechanical plans, room-use plan, kitchen criteriaIs the ventilation strategy for the kitchen described, including transfer air and negative pressure intent?
Delegated and owner-suppliedEquipment schedule, responsibility matrix, contract notesWhich items are owner-supplied, which are contractor-installed, and where is that recorded?
Revision closureResponse, revised equipment schedule, dependent disciplinesDoes the accepted change reach the equipment schedule, the rough-in drawing, and the MEP sheets affected by it?

Record “needs clarification” when a reference is missing, and reserve “resolved” for a decision supported by documents you have read. If a row does not apply to this project, write why: a blank cell cannot tell a skipped check from a completed one.

Work one condition end to end

Take one hood. Read its exhaust and makeup air quantities on the food-service schedule, then find the same hood on the mechanical drawings and compare the numbers. Check the air-balance schedule for the room. Then find the suppression system on the fire protection drawings and its interlock in the fire alarm matrix. Finally, check the electrical connection for the hood controls. Hoods concentrate more cross-discipline questions than any other item in the kitchen.

Working one condition all the way through beats skimming every sheet, because it forces each document to answer the same question. When the answers differ, you have a finding with two references attached, which is what a designer needs in order to decide.

Close the loop

A response saying “coordinated” is the start of verification, not the end. Open the revised sheets, confirm the change, then follow it into the dependent documents: the schedule, the detail, the specification section, and the other discipline that relied on it. Record the sources you checked and the evidence that closed the question.

Where the answer is a decision rather than a correction, record the decision and who made it. The guide to prioritising findings covers how to sort what you have found once the list gets long.

Use AI for a source-linked first pass

Groundbook AI can run these comparisons across the whole set at once, returning each difference with both sheets highlighted and the supporting sources linked. It reads drawings, specifications, reports, checklists, and the building codes you upload, including scanned and hand-drawn sheets. Give the review a defined scope, then verify every cited location before turning a finding into a request.

The findings are questions for your team to settle. Design, engineering, and compliance decisions stay with the responsible professionals and the authority having jurisdiction.

Questions, answered

FAQs

What causes the most kitchen coordination problems?

Equipment that changed after the utility rough-ins were drawn, hoods whose air quantities differ between the food-service and mechanical documents, and owner-furnished items with no recorded installation responsibility.

Do you check health department requirements?

No. The review compares documents against each other and against any criteria you upload. Health, fire, and building determinations belong to the reviewing authorities.

Can I use this checklist in Excel or Google Sheets?

Yes. The CSV has the 12 prompts plus blank fields for the location, source issue, reviewer, decision, revised sources, and closure evidence.