Guide · Bidding and tendering

Follow an addendum through the whole bid package

An addendum can change a requirement without reissuing every document that relies on it. Review the changed source, the affected interfaces and the information bidders must price.

Establish the issued base package and included addenda, identify what each instruction replaces or adds, and trace the change into schedules, details, specifications and trade interfaces. Resolve precedence and open pricing questions before the bid closes.

Separate an instruction from a full reissue

Record each addendum number, issue date, instruction and attachment. A replacement sheet may supersede one drawing while leaving the remainder of the set unchanged. A written clause can revise a requirement without replacing the original PDF.

Keep the base issue available so the reviewer can understand the before-and-after condition. The revision review guide covers this baseline decision; the addendum checklist adds the bidding handoffs.

Trace one changed selection

Suppose a hypothetical addendum changes a rooftop unit. The mechanical schedule reflects the new model, but the electrical circuit and structural support detail still describe the original selection. Review the submitted weights, power and connection data against those receiving documents.

The output should identify the conflicting sources and an answerable question: which selection governs, and which dependent documents need revision? It should not assign a price or assume that a larger unit automatically creates a change order.

Eight checks before the bid closes

Eight checks before the bid closesSwipe or scroll sideways to read all columns.
CheckSourcesReview question
Issue listBase register and addendum transmittalsHave all issued addenda and their attachments been included?
Affected sourceAddendum instruction and original clause or sheetWhat is replaced, added or deleted, and where?
Unclouded effectChanged requirement and dependent documentsWhich unchanged sheets rely on the revised value?
Equipment scopeSchedules, controls, utility and support informationDoes the revised selection agree across the receiving disciplines?
Specification changeAmended clause and drawing requirementsDo the performance, material and installation requirements agree?
Trade boundaryScope instructions and interface detailsWho prices the changed connection, opening or accessory?
Bid responseQuestion log, clarification and bid formHas the team recorded the answer or explicit pricing assumption?
Final baselineComplete review register and accepted clarificationsCan every bidder identify the same governing package?

Make the pricing question answerable

Record the affected item, competing source references and decision needed. Identify the trade scope and the deadline for clarification. An estimator should be able to distinguish a confirmed requirement from an allowance or unresolved assumption.

Track the response in the pre-bid question log. If the response points to another document, include that document in the package and backcheck the affected interfaces. A response that simply says “per drawings” can leave the original discrepancy unresolved.

A published coordination example

The dental clinic review includes equipment and utility information that needed reconciliation across the package. It illustrates the relationships to trace when a selection changes. The published case does not claim the conflicts were introduced by an addendum.

Use a complete set for the comparison where the affected references cross disciplines. The visible change alone may be too narrow to explain the consequence.

Source and review scope

AIA’s A201-2017 summary describes a standard contract framework. Your issued bidding and contract documents determine the project process. Source checked October 13, 2026.

Groundbook can support a document consistency review of the supplied package. The project team establishes document precedence and pricing treatment.

Questions, answered

FAQs

Should I review only replaced sheets?

Include the unchanged documents that depend on the revised requirement, including schedules, details, specifications and other disciplines.

Is an addendum the same as a change order?

Their use depends on the project procedure. Addenda commonly revise bidding documents before contract execution; a change order documents an authorized contract change. Confirm the governing procedure.

Does the checklist estimate the cost of changes?

No. It records document questions and their sources. Your estimating team prices the resolved scope and assumptions.

Check the documents changed by your addendum

Include the base set and the documents that depend on the change. Groundbook flags potential conflicts with links to the source sheets.

Check the documents changed by your addendum

Trusted by hundreds of professionals