The bid form and the product index describe two different operable walls.

The specifications, bid price form and product index give bidders two answers on products, materials and who pays for what.

  • Specification review
  • Bid forms
  • Product selection
  • Trade scope
340 pagesSpecifications and architectural drawings
Coordination reviewCoordination and completeness within the set
65 findingsPotential issues surfaced for verification
7 examplesConcise review details below

Early learning center specifications

A full project manual for an early learning facility, checked with the architectural drawings for assemblies, schedules and details.

What the review compared

The project manual was the checked document, read with the architectural cover, assembly and code sheets. The review compared the bid price breakdown form, the product index, the technical sections and the drawn schedules and details, focusing on what a bidder needs to price, allocate and buy.

Where bidders get two answers

The bid form and the product index name different products for the same items. Technical sections contradict details on frames, flashing, sleepers and plywood, and the general requirements put site security and the building permit in two places at once.

What to verify next

The architect should resolve each conflict by addendum before bids close, choosing one product, one material and one responsible party for each item. This review did not enable code checking; the examples are questions for the responsible designers.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01Medium priority

Rated corridor door has a wood frame

The door schedule gives a fire-rated corridor door a wood frame; the specification requires steel.

Why it matters: An unlabelled frame could be ordered.

What to check: Correct the schedule to the specified steel frame.

Architectural
02Medium priority

Operable wall sound ratings conflict

The bid form and the product index give the operable wall different sound ratings.

Why it matters: Operable wall bids will not be comparable.

What to check: State one required rating by addendum.

Architectural
03Medium priority

Whiteboards are both glass and porcelain

The bid form prices glass whiteboards; the product index names a porcelain markerboard.

Why it matters: The wrong boards may be priced or ordered.

What to check: Name one board product in both.

Architectural
04Medium priority

Radon membrane has two thicknesses

Two clauses of the radon section specify different sheets for the same under-slab layer.

Why it matters: The thinner sheet would not meet the other clause.

What to check: Specify one product and thickness.

Architectural
05Medium priority

Chiller curb uses wood the roofing section rejects

The roofing section rejects wood sleepers; the chiller curb detail is wood-framed.

Why it matters: Bidders have no clear support material to price.

What to check: Choose the support type and revise one document.

Architectural
06Medium priority

Site security is base work and an option

One section includes after-hours security in the base work; another asks for a separate price.

Why it matters: Base bids may not be comparable.

What to check: Keep security in one place.

Architectural
07Medium priority

Building permit has two responsible parties

Consecutive clauses make both the contractor and the owner responsible for the building permit.

Why it matters: Some bids may omit the permit fee.

What to check: Delete the clause that does not apply.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural and Structural

Check the findings with the responsible discipline designers.

02 · Priorities

Medium and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your specifications against the bid form and drawings

Trusted by hundreds of professionals