Guide · Envelope

Curtain wall and facade review checklist

Most of a facade is designed by someone who is not the architect of record. The review is largely about whether the handoff was documented: what criteria were given, what is still outstanding, and who owns each side of every connection.

Identify the delegated design scope and the performance criteria it was given, then trace anchorage into the structure, movement into the joints, and the air and water barrier into the adjoining assemblies. Record gaps with both references. Structural adequacy and performance determinations remain with the responsible engineers.

Assemble a reviewable package

Gather the elevations, wall types, wall sections, facade details, glazing schedule, and the performance specification. Add the structural drawings for slab edges and anchors, the energy compliance documents, and the life-safety plan for rated conditions at the floor perimeter.

Agree which areas and which design milestone are being reviewed, and record any document you expected and did not receive. A review can only compare what it is given, so a missing sheet is a finding in its own right. The drawing register template gives you somewhere to record the governing issue before you start.

Twelve document checks

Use one worksheet row per condition rather than per sheet. Where a condition repeats, note the locations you sampled and any exception you found. The CSV adds blank fields for the project location, source issue, reviewer, decision, revised sources, and closure evidence.

Curtain wall and facade review checklistSwipe or scroll sideways to read all columns.
Review areaSources to compareQuestion to resolve
System boundaryElevations, wall type plan, specification sectionsDoes each facade area resolve to one system, with the boundary between systems located and detailed?
Delegated design scopeGeneral notes, performance specification, submittal listWho designs the system, what performance criteria were given, and which documents remain outstanding?
Anchorage and structureAnchor details, structural drawings, edge-of-slab tolerancesIs each anchor traceable to a structural element, with the assumed slab edge tolerance stated?
MovementJoint details, structural drift criteria, thermal movement notesAre the movements the system must accommodate stated, and is the joint that accommodates them detailed?
Air and water barrier continuityWall sections, transition details, adjacent assembliesCan the air and water barrier be traced continuously into the roof, foundation, and adjacent wall types?
Thermal performanceAssembly schedule, energy compliance documents, thermal break detailsDo the assumed assembly values in the energy documents match the assemblies detailed on the drawings?
Glazing and performanceGlazing schedule, elevations, specificationDoes each glass type resolve to one specification, with the locations requiring safety or fire-rated glazing identified?
Opening interfacesDoor and window schedules, facade elevations, head and sill detailsDoes every opening in the facade appear in a schedule and resolve to a detailed head, jamb, and sill?
Fire and smokePerimeter fire barrier details, rated assemblies, life-safety planIs the perimeter joint between the facade and each floor detailed, with the rated condition identified?
Maintenance accessRoof plan, anchor plan, facade access notesIs the means of access for cleaning and maintenance described, with its supports coordinated to the structure?
Mock-ups and testingSpecification, submittal schedule, test criteriaWhich mock-ups and tests are required, when, and what acceptance criteria and documents accompany them?
Revision closureResponse, revised elevations and details, structural interfaceDoes the accepted change reach the elevations, the wall sections, and the structural and energy documents?

Record “needs clarification” when a reference is missing, and reserve “resolved” for a decision supported by documents you have read. If a row does not apply to this project, write why: a blank cell cannot tell a skipped check from a completed one.

Work one condition end to end

Take one typical bay at a floor line. Follow the anchor from the facade detail to the structural element it lands on, and read the slab edge tolerance the detail assumes. Then trace the air and water barrier through that same junction into the floor construction. Finally, check whether a perimeter fire barrier is detailed there and whether the life-safety plan calls for one. That single junction touches four disciplines and is where most facade questions live.

Working one condition all the way through beats skimming every sheet, because it forces each document to answer the same question. When the answers differ, you have a finding with two references attached, which is what a designer needs in order to decide.

Close the loop

A response saying “coordinated” is the start of verification, not the end. Open the revised sheets, confirm the change, then follow it into the dependent documents: the schedule, the detail, the specification section, and the other discipline that relied on it. Record the sources you checked and the evidence that closed the question.

Where the answer is a decision rather than a correction, record the decision and who made it. The guide to prioritising findings covers how to sort what you have found once the list gets long.

Use AI for a source-linked first pass

Groundbook AI can run these comparisons across the whole set at once, returning each difference with both sheets highlighted and the supporting sources linked. It reads drawings, specifications, reports, checklists, and the building codes you upload, including scanned and hand-drawn sheets. Give the review a defined scope, then verify every cited location before turning a finding into a request.

The findings are questions for your team to settle. Design, engineering, and compliance decisions stay with the responsible professionals and the authority having jurisdiction.

Questions, answered

FAQs

Who designs a curtain wall?

Typically a specialist under a delegated design arrangement, working to performance criteria stated by the design team. The review checks that the criteria, the responsible party, and the outstanding submittals are documented rather than assumed.

What is a perimeter fire barrier joint?

The joint between the edge of a floor and the back of the facade. It is detailed to maintain the floor’s rating. Whether one is required, and to what standard, is a determination for the responsible professionals and the authority having jurisdiction.

Can I use this checklist in Excel or Google Sheets?

Yes. The CSV has the 12 prompts plus blank fields for the location, source issue, reviewer, decision, revised sources, and closure evidence.