ICC 300 bleacher, telescopic seating, and grandstand plan review

Bleachers are often drawn twice: once by the architect, who shows the room, the exits, and the wheelchair spaces, and once by the seating supplier, who shows the rows, aisles, and structure. Groundbook can compare those documents with the ICC 300 edition you upload and flag where they disagree.

Confirm that the seating is a bleacher or grandstand under ICC 300, meaning tiered seating on its own structural system rather than seats fixed to a stepped floor, and which ICC 300 edition the adopted code references. Then trace egress within the seating, wheelchair spaces, stepped-aisle handrails, spaces under the seating, and any press box or camera platform between the architectural drawings and the supplier’s layout. AI can flag conflicts; the architect, the supplier’s engineer, and the building official decide compliance.

What does ICC 300 cover?

The ICC store page for ICC 300-2023 says the standard addresses new and existing installations of all types of bleacher seating, including fixed and folding bleachers for indoor, outdoor, temporary, and permanent use, and is intended to coordinate with the means of egress systems in the building codes. ICC’s Building Safety Journal explains that it covers seating supported on a dedicated structural system, that single or bench seats bolted to a stepped floor are not bleachers, and that its criteria include construction, egress within the bleacher system, inspection and maintenance of existing bleachers, and relocation.

ICC’s bleacher safety committee page says the final ballot for the 2023 edition closed July 31, 2023 and ANSI approval followed on September 18, 2023, and the Building Safety Journal says the 2023 edition is referenced in the 2024 IBC, IFC, and IEBC. The store still lists the 2017 and earlier editions. Checked October 21, 2026. A jurisdiction on an earlier I-Code edition references an earlier ICC 300, so record the edition the adopted code names and any local amendments rather than assuming 2023.

ICC 300 relies on IBC Chapter 10 for some provisions: the Building Safety Journal notes that exits from the bleacher are set in ICC 300 while exits from the room it sits in follow the IBC, and that spaces under bleachers such as ticket booths, toilet rooms, concessions, and storage are addressed by the IBC. Accessibility follows the IBC and ICC A117.1. See the IBC Chapter 10 egress guide and the ICC A117.1 guide.

Gather the architectural set and the seating supplier’s drawings

Collect the code analysis and life safety plans, the floor plans and sections through the seating, the seating supplier’s layout, elevations, and structural drawings, the handrail and guard details, the accessible seating plan, any press box or platform drawings, the structural drawings for floor or wall support, the fire protection and fire alarm drawings for the room, and the bleacher specifications.

For existing or relocated bleachers, add the existing conditions survey and the scope of alterations, because the 2023 edition addresses where aisles and handrails are added and where open risers are infilled.

Trace the seating through the room and the supplier set

ICC 300 document coordination checksSwipe or scroll sideways to read all columns.
Review questionSources to compareDecision to record
Is it a bleacher?Sections, seating supplier drawings, structural drawings, code analysisRecord whether the seating sits on its own structural system or on a stepped floor, and which code path the code analysis follows.
Egress within the seatingSupplier layout, life safety plan, code analysisMatch aisle, cross aisle, and exit locations on the supplier layout to the life safety plan, and confirm the room’s exits are counted separately.
Wheelchair spaces and accessible egressAccessible seating plan, supplier layout, life safety planCheck that the wheelchair spaces, companion seats, and accessible routes on the architectural plans exist in the supplier layout, including at raised exterior bleachers.
Handrails and guardsHandrail and guard details, supplier elevations, specificationsFind stepped aisles, open sides, and rear edges where the architect and supplier show different rails or none.
Spaces under the seatingFloor plans, sections, fire protection drawings, code analysisRecord any booth, toilet, concession, or storage space under the bleacher and the separation or protection the code analysis assigns to it.
Press boxes and platformsPress box drawings, supplier layout, life safety planConfirm access and egress for press boxes and camera, audio, or security platforms are drawn and agree between documents.

Room egress continues in the IBC Chapter 10 guide and fire code items in the IFC guide. Bleachers are common on K–12 school and sports and recreation projects.

Example: telescopic seating replaced in a high school gym

Hypothetical example. A high school replaces its telescopic bleachers. The architectural plan shows wheelchair spaces cut into the front row at two locations and aisles aligned with the gym doors, while the supplier layout shows a continuous front row, aisles shifted to suit its standard module, and no handrails along two of the stepped aisles.

The architectural plan shows two wheelchair space cutouts in the front row and aisles aligned with the gym exits, but the supplier layout shows a continuous front row, shifted aisles, and no handrails at two stepped aisles. Confirm the seating layout and coordinate the accessible seating, aisles, and handrails with the life safety plan.

The architect and the supplier reconcile the layout before fabrication. The finding is a disagreement between documents; the building official decides compliance.

Review bleacher drawings with Groundbook

Upload the current drawings and specifications to Groundbook, and state the edition, amendments, and review scope in your instructions. Add the ICC 300 edition the project uses from a copy you are licensed to use, where the license permits uploading it, and the jurisdiction’s published amendments. See how Groundbook works with local and licensed codes.

Compare the code analysis, life safety plans, floor plans, sections, accessible seating plan, handrail and guard details, seating supplier layout, elevations, and structural drawings, press box drawings, fire protection drawings, and bleacher specifications. Flag a conflicting ICC 300 edition, seating whose classification differs between documents, aisles and exits that differ between the supplier layout and the life safety plan, wheelchair spaces missing from the supplier layout, stepped aisles without handrails, and spaces under the seating with no stated separation. Use the supplied ICC 300 and cite both sources.

Groundbook links each potential finding to the sheets and documents involved. It does not calculate egress capacity, design the bleacher structure, or check loads.

Document review does not certify compliance or approve a permit. Those remain with the architect, the supplier’s engineer, and the building official.

Questions, answered

FAQs

What is the current edition of ICC 300?

ICC sells ICC 300-2023, which ICC says received ANSI approval on September 18, 2023 and is referenced in the 2024 IBC, IFC, and IEBC. Earlier I-Codes reference earlier editions.

Does ICC 300 apply to seats on a stepped floor?

ICC’s Building Safety Journal says single or bench seats bolted to a stepped floor are not a bleacher or grandstand; ICC 300 covers tiered seating on its own structural system.

Can Groundbook check bleacher drawings against ICC 300?

It can compare architectural drawings, supplier drawings, and specifications with the ICC 300 edition you upload and flag potential conflicts. It does not design or approve the seating.

Bring your next set into focus

Set up a review or talk through your project with our team.

Check your bleacher layout against ICC 300 and the life safety plan

Trusted by hundreds of professionals