Start with the opening note of the issued Section 22 60 70: only the drawings carry capacities, dimensions, equipment locations, and maintenance space, and they must show the configuration, slope, and location of every piping system and every sectionalizing valve. Confirm that each system the specifier kept in the Category 1, 2, and 3 lists appears on the piping plans with a source, a riser, zone valves, outlets or inlets, and alarms, and that no outlet on the schedule belongs to a system the section deleted.
Assemble the review package
Gather the medical gas and vacuum floor plans, risers, and piping diagrams, the outlet and inlet schedule or room data sheets, the zone valve box and alarm panel locations, the source equipment room plans, details, and schedules, the roof plan with compressor intakes and vacuum exhausts, the site plan with any bulk oxygen pad and emergency oxygen connection, the dental treatment room utility box details and laboratory casework drawings, the electrical panel schedules and one-line for the essential electrical system, the architectural partition types, and the issued Section 22 60 70 with Sections 01 91 00.15, 13 48 73, 23 05 48.19, and 23 09 00, plus the NFPA 99 risk assessment and the edition the project follows. Trace one zone from its source to its last outlet before assuming the others match.
WBDG publishes UFGS 22 60 70: Gas and Vacuum Systems for Healthcare Facilities as a public guide-specification reference (accessed November 18, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| Systems kept and their categories | System Description category lists and note (category chosen by patient dependency; Category 2 or 3 by a documented risk assessment under NFPA 99; Category 3 systems kept entirely separate from Category 1) + Design Requirements (patient care gases and vacuums for patient care only; nitrogen and dental, instrument, laboratory, and process air as support utilities) + outlet schedule, piping diagrams, and risk assessment | Does every system on the outlet schedule and piping diagrams appear in one of the category lists the specifier kept, is a risk assessment on file for any Category 2 or 3 system, and are Category 3 dental systems shown as piping entirely separate from the Category 1 medical systems? |
| What the drawings must show | Part 1 drawing note (capacity, efficiency, dimensions, plan views, sections, elevations, equipment locations, and maintenance space on drawings only; configuration, slope, and location of each piping system; location of each sectionalizing valve) + Accessibility of Equipment note (designer lays out equipment, control devices, and access doors) + piping plans, risers, and source room plans | Do the plans show each system’s routing above or below ceilings, floors, roofs, or grade, each sectionalizing valve, the source equipment with its capacity and service clearance, and an access door wherever a concealed valve or device needs one? |
| Source equipment and the equipment schedule | Bulk Liquid Oxygen (usually leased; not part of the contract) + Emergency Oxygen Supply Connection (only for Category 1 where supply is remote; coordinate accessibility) + Cylinder Manifold (cylinder counts left blank; location and power with Division 26; heated nitrous oxide and carbon dioxide supply on emergency power) + compressor and vacuum pump sources with receivers, dryers, filters, and control panels + equipment schedules and source room plans | Has the specifier filled every cylinder count blank, does the equipment schedule list each kept source with the pump or compressor type the bracket keeps, is the emergency oxygen connection shown on the site plan where a truck can reach it, and does the panel schedule give the manifold heaters an emergency power circuit? |
| Zone valve boxes | Zone Valve Assemblies (recessed box, transparent door, gauge on each valve; valve count and single-valve box sizes; surface boxes only where specifically indicated; valve order from top to bottom) + stud depth note (coordinate with architects) + Valves and Assemblies execution (recessed on the corridor side of the partition; mounting height; label naming the rooms served) + floor plans and partition types | Are the zone valve boxes on the corridor side of the partition at each zone the area alarms serve, do the partition types give the stud depth the box needs, is any surface box shown as such, and does each box’s room list match the outlets downstream on the plans? |
| Master, area, and local alarms | Warning Systems (locate as specified and indicated; normal and emergency power) + Master Alarm Panels (life safety branch power; alarm point list by installed system; UMCS contacts under Section 23 09 00; location note) + Area Alarm Panels (only where NFPA 99 designates unless the facility requires more; nursing units as indicated) + Warning System execution (master alarm room blanks; no daisy-chaining; area designations coordinated with zone valve designations; panel power by the electrical contractor) + electrical panel schedules | Are the master alarm room blanks filled and shown on the plans, does each area alarm panel sit with the zone valves it monitors and carry matching designations, does the alarm point list cover only the systems kept, and do the electrical drawings give each panel a life safety branch circuit while the section supplies the sensor wiring? |
| Outlets, inlets, and room elevations | Station Outlets/Inlets (DISS unless the using facility requires otherwise; quick-disconnect coupler bracket; WAGD inlet connection; recessed unless specified otherwise) + ceiling hose assemblies to the ceiling height indicated + vacuum slides coordinated with room elevations + Dental Compressed Air Outlets (dental laboratory locations with the casework supplier) + Laboratory Compressed Air Termination + Wall Outlets/Inlets execution (height “or as indicated”) + outlet schedule and room elevations | Does the outlet schedule list each outlet type and count per room that the room elevations, headwalls, and ceiling plans show, does the coupler choice match the facility’s mobile equipment, are ceiling outlets coordinated with the reflected ceiling plan height, and are dental lab and lab air outlets located on the casework drawings? |
| Piping, intakes, exhausts, and mounting | Pipe and Fittings (copper for medical gas and vacuum; PVC for oral evacuation and dust evacuation; service entrance “same as indicated for outside utilities”) + Piping Systems execution (lab and process air separate from dental and medical air; intake and exhaust to the outside, turned down and screened; oral evacuation and vacuum exhaust slopes; protection of underground piping) + Vibration-Absorbing Features note (designer indicates resilient mounting) + Sections 13 48 73 and 23 05 48.19 + roof plan, site plan, and equipment details | Do the roof and site plans show each compressor intake and vacuum exhaust terminating outside, turned down and screened, do the oral evacuation and exhaust lines show their slope direction, are lab and process air piped separately from medical and dental air, and do the equipment details show the isolation and seismic mounting the note asks the designer to indicate? |
| Testing, verification, and the section’s own wording | Commissioning and I,T&V agency (Section 01 91 00.15; agency reviews drawings and witnesses brazing) + Camera Inspection bracket + Category 1 and Category 3 testing + OE System Test (show vacuum gauge No. 1 on the contract documents; metric and inch-pound pressure drop and gauge accuracy disagree) + WAGD pump bracket and lag settings + Plastic Pipe Markers (ANSI A108.11, a backer board standard, cited for markers) + Dental Oral Evacuation Inlets (truncated paragraph) + pipe colour table (“Laboratory Vacuum” not defined) | Is vacuum gauge No. 1 shown on the oral evacuation diagram, are existing-system tie-in tests kept only where the plans show new-to-existing connections, and has the specifier corrected the pipe marker reference, the WAGD blower and test conversions, the WAGD lag settings, the motor temperature rise conversion, and the missing dental oral evacuation inlet text? |
Worked example: a combined medical and dental clinic with a procedure suite
Illustrative example: a two-story clinic has a medical floor with exam rooms and a small procedure suite, and a dental floor with treatment rooms and a dental laboratory. The issued Section 22 60 70 keeps oxygen, medical air, and medical-surgical vacuum as Category 1, and dental air, dental surgical vacuum, oral evacuation, and laboratory dust evacuation as Category 3. The outlet schedule lists WAGD inlets in the procedure rooms although WAGD was deleted from every category list, the zone valve boxes for the procedure suite are drawn on the room side of the partition, the master alarm room blanks are still empty, the dental laboratory air is shown teed from the medical air main, the oral evacuation diagram shows no vacuum gauge No. 1, and the nitrous oxide manifold heater appears on a normal power panel.
Ask the engineer of record to confirm whether the procedure rooms need WAGD and either keep it in the Category 1 list with a source, zone valves, and alarms or remove the inlets from the schedule. Ask the architect and engineer to move the zone valve boxes to the corridor side and confirm the stud depth, fill the master alarm locations, repipe dental laboratory air from the dental air source as a separate system, and add vacuum gauge No. 1 to the oral evacuation diagram. Ask the electrical engineer to put the manifold heater on emergency power and the alarm panels on the life safety branch.
Avoid a false conflict
Section 22 60 70 covers piped medical and dental gas, support gas, and vacuum systems. Fuel gas follows Section 23 11 20 and the facility gas piping guide, compressed gas storage rooms follow NFPA 55, room requirements follow the FGI document the project adopts, essential electrical system branches follow NFPA 99 and the electrical sections, alarm integration follows Section 23 09 00, and seismic bracing follows Sections 13 48 73 and 23 05 48.19, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the pipe marker paragraph cites a backer board standard, the WAGD blower and oral evacuation test values do not convert consistently, the WAGD lag pump stops at its area alarm point, the WAGD pump options are mislabelled, a motor temperature rise is converted as a temperature, and the dental oral evacuation inlet paragraph is truncated. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.