Wood truss drawing review checklist

Roof and floor trusses are designed by the supplier from the drawings they are sent. When the house changes after that, or when the drawings never stated a load, the truss package and the permit set describe two different buildings.

Review truss drawings by checking the layout against the current architectural roof and floor plans, then checking the loads the supplier designed to against what the set actually builds: the roof covering, floor finishes and attic equipment. Then follow each truss reaction to a wall, header, girder or beam the drawings show, confirm one uplift tie per bearing, and check that bracing and the approval route are on the sheets.

Check the loads the trusses were designed for

A truss is only as right as its design loads. The supplier designs roof trusses to the dead load the drawings give, and floor trusses to the floor loads they give. Two failures are common: the roof covering changes (from shingles to tile or slate) after the framing is designed, and the design notes never state the floor loads at all.

In the two-story house roof load and shear wall review, the roof framing note covered a composition or metal roof while every architectural sheet specified slate tile, and the structural notes gave roof and wind loads but no second-floor live or dead load for the floor truss supplier to design to.

Twelve questions for truss drawings

Work through the layout, the truss design drawings and the permit set in this order. The CSV has columns for the location, the source references, the reviewer, the status, the decision and the closure evidence. It contains no design values; those come from the truss designer and the engineer of record.

Wood truss drawing review checklistSwipe or scroll sideways to read all columns.
Review areaOpen these sources togetherQuestion to resolve
Truss layout matches the architectural roof and floor plansTruss layout, architectural roof plan, floor plans, sectionsDo truss spans, overhangs, pitches, ridges, hips and valleys on the layout match the architectural roof and floor plans of the current issue?
Roof covering and design dead loadTruss design drawings, structural design notes, roof assemblies, elevationsDoes the dead load on the truss and rafter design cover the roof covering the architectural sheets specify, such as tile or slate rather than shingles?
Floor design loads given to the supplierStructural design notes, floor truss drawings, finish schedule, partitionsAre the floor live and dead loads, including heavy finishes, partitions and equipment, stated on the drawings the truss supplier designs to?
Bearing walls and girder trussesTruss layout, structural framing plan, foundation plan, architectural plansIs every truss bearing on a wall, beam or girder the drawings actually show, and does each girder truss land on a post with a load path to the foundation?
Headers and lintels under truss bearingsLintel and header schedules, wall framing, truss layout reactionsWhere trusses bear over a door, window or garage opening, is the header in the schedule sized for that roof load and that span?
Uplift connectionsTruss drawings (reactions), structural notes, connector schedule, wind dataDoes each truss or rafter have one named tie to the wall, sized for the uplift the truss drawings or calculations give?
Attic equipment and openingsMechanical plans, truss layout, attic access, electrical plansAre attic units, platforms, access openings, ducts and chases shown on the truss layout and accounted for in the truss loads?
Scissor, vaulted and special trussesSections, reflected ceiling plans, truss layout, roof assembly scheduleDo the sections and ceiling plans show the same scissor, vaulted or stepped ceilings the layout designs, with matching assembly marks?
Floor truss depth and penetrationsFloor truss drawings, sections, plumbing and duct layoutsDoes the floor truss depth fit the section heights, and do ducts and drains run through open webs or chases rather than through chords?
Permanent bracingTruss drawings, structural notes, bracing detailsAre the permanent lateral and diagonal bracing the truss drawings call for shown or referenced on the structural sheets?
Revision and issue matchTruss layout title block, structural and architectural sheet index and revisionsWere the truss drawings designed from the current architectural and structural issue, and are later changes reflected?
Who approves the truss packageSpecifications or general notes, submittal requirements, truss sealDo the notes say who reviews the truss package and whether a sealed design is required, and is that reflected in the submittal?

Mark a row not applicable only after recording why. A simple gable roof still needs its bearings, ties and loads checked.

Follow every reaction down

Truss drawings list a reaction at each bearing. Each one has to land on something the drawings design: a wall, a header over an opening, a girder truss, a beam or a post. Openings under truss bearings are where this breaks. In the house permit set review, the lower roof trusses bore on a wall over a wide garage door, and the scheduled lintel there was rated for a shorter span than the opening.

Check uplift the same way: one named tie per bearing, sized for the uplift the truss drawings give. The same two-story house review found the rafter-to-plate tie named as three different models across three sheets. The structural drawing checklist and the calculations versus drawings checklist cover the rest of the structure.

Match the truss package to the current issue

The truss layout title block names the drawings it was designed from. Compare that with the current sheet index and revisions. Roof pitches, ceiling heights, attic units and plumbing walls move during design, and each move can change a truss. Check the specifications or general notes for who reviews the truss package and whether a sealed design is required; the submittal review checklist covers the approval workflow.

Where Groundbook fits

Groundbook compares the architectural and structural drawings with the truss layout and truss design drawings you upload as references, and returns potential conflicts with links to each source, such as a roof covering on the elevations that differs from the one the framing was designed for. It does not design trusses, check their capacity or approve a truss submittal. Each finding is a question for the truss designer and the engineer of record. See cross-discipline coordination review for the workflow.

Questions, answered

FAQs

Who checks truss drawings against the house plans?

Usually the engineer of record or the designer reviews the truss submittal, and the contractor checks that it matches the current set. The truss designer is responsible for the trusses themselves.

What happens if the roof covering changes after the trusses are designed?

The roof dead load changes, so the truss or rafter design may no longer cover it. Ask the truss designer or engineer to confirm or redesign for the new covering before the trusses are built.

Do floor trusses need design loads on the drawings?

Yes. The supplier designs to the loads it is given. State the floor live and dead loads, including heavy finishes and partitions, in the structural notes.

Can I review truss drawings myself?

You can find where the truss package and the permit set disagree. Truss capacity and connection design belong to the truss designer and the engineer of record.

Keep exploring

Continue your review

Structural drawing review checklist

Review structural notes, framing plans, schedules, details, and support interfaces with a practical checklist, worked example, and free editable CSV.

Explore

Trace structural calculation criteria into the drawings

Compare structural calculation references, loads, member labels and schedules with issued plans and details. Includes an editable consistency checklist.

Explore

AWC National Design Specification (NDS) for Wood Construction: plan review

Review wood structural drawings against the NDS: design basis, species and grade, members, connections, and engineered products. See checks and limits.

Explore

International Residential Code (IRC) plan review

Review house plans against the IRC: scope, egress, stairs, framing, energy, and MEP coordination for one- and two-family dwellings and townhouses.

Explore

Two-story house roof load and shear walls

A permit review of a two-story house finds roof rafters designed for a lighter roof than the slate tile specified and a shear wall standing on the slab.

Explore

House permit set: lintels, radon, energy

A permit review of a two-storey house finds a garage door lintel too short for its span, alarms placed on no plan and a radon rough-in that skips a slab.

Explore

Cross-discipline coordination

Find potential conflicts across architectural, structural, and MEP drawings. Review levels, openings, equipment, and references with linked document evidence.

Explore

Check rough carpentry specifications against framing plans, shear wall schedules, and roof nailer details

Compare lumber grades, glulam, sheathing and shear wall panels, treatment, anchors and nailing, bracing, and roof nailers with UFGS 06 10 00.

Explore

Bring your next set into focus

Set up a review or talk through your project with our team.

Check your truss drawings against the roof, floor and structural sheets

Trusted by hundreds of professionals