The electrical diagram is three-phase; the budget prices a single-phase supply.

The drawings, the project report, the written specification and the priced budget describe the same house, and they price different materials and quantities.

  • Bill of quantities
  • Written specification
  • Residential
  • Structural levels
  • Electrical supply
400 pagesDrawings and written project
Coordination reviewCoordination and completeness within the set
56 findingsPotential issues surfaced for verification
7 examplesConcise review details below

House drawings, budget and specification

A full project for a single-family house: architectural, structural and services drawings, with the project report, written specification and priced bill of quantities.

What the review compared

The review read the drawings with the project report, the written specification and the priced budget for a single-family house. Its instructions asked for consistency between drawings, specification and quantities, missing details, dimension conflicts and gaps between the plans and the priced items.

Where the documents disagree

A structural level and a structural opening do not fit the architecture. The budget prices a different electrical supply, different light fittings and fewer beams than are drawn, and the specification requires pipe materials that neither the drawings nor the budget use.

What to verify next

The architect should reconcile the drawings, specification and budget item by item before tender, and attach the soil study the report cites. This review did not enable code checking; the examples are questions for the responsible designer.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01High priority

Slab level leaves no room for the floor

The structural slab level sits just below finished floor, leaving no depth for the specified layers.

Why it matters: Floor, stair and threshold levels would change.

What to check: Confirm the slab level and align sections.

Structural · Architectural
02High priority

Stair opening cuts into the plant room

The top floor’s structural stair opening extends past the stair into the plant room.

Why it matters: A wall would sit over the opening.

What to check: Match the opening to the attic plan.

Structural · Architectural
03Medium priority

Three-phase on the drawings, single-phase in the budget

The diagram and calculation design three-phase; the budget prices a single-phase meter, feeder and board.

Why it matters: The supply cannot be priced or requested.

What to check: Decide the supply and align all three.

Electrical · Specifications
04Medium priority

Specification requires pipes the drawings do not use

The written specification requires copper water pipe and cement drains; drawings and budget use plastic.

Why it matters: The specification governs, so unpriced materials could be required.

What to check: Correct the specification articles.

Specifications · Plumbing
05Medium priority

Soil report cited but not attached

The report says the soil study is attached; it is not, and deeper footings are unmeasured.

Why it matters: Bidders cannot check the ground assumptions.

What to check: Attach the study and price deeper digging.

Structural · Specifications
06Medium priority

Budget prices fluorescent fittings for LED downlights

The lighting plan draws recessed LED points; the budget prices surface fluorescent fittings instead.

Why it matters: Type, mounting and lamp all differ.

What to check: Define each fitting and adjust the budget.

Electrical · Specifications
07Medium priority

Budget measures one of two tie beam lines

The foundation plan draws two lines of tie beams; the budget measures only one.

Why it matters: Excavation and concrete for one line are unpriced.

What to check: Add the second line to the budget items.

Specifications · Structural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural, Structural, Electrical, Mechanical, Plumbing, and Specifications

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your drawings, specification and budget agree

Trusted by hundreds of professionals