Closet walls tagged one-hour on the floor plans are two-hour walls in the column details they call.

The issued-for-construction floor plans of a laboratory fit-out were checked against the partition type, shaftwall and rated joint details they rely on, and the fire ratings, listed assemblies and sheet references disagree from plan to detail.

  • Laboratory building
  • Interior fit-out
  • Fire-rated partitions
  • Shaftwall
  • Rated joint systems
  • Masonry walls
  • Life safety
30 pagesFit-out plans and partition details
Code check enabledCoordination and code-reference checks
26 findingsPotential issues surfaced for verification
12 examplesConcise review details below

Lab fit-out partition fire ratings

Interior fit-out floor plans for two levels of a laboratory building, with the partition type sheets, shaftwall, head, joint and column enclosure details and selected structural details, read against one another with a fire and life safety focus and the code sections the review cited.

What the review compared

The review read the interior fit-out floor plans for two levels of a laboratory building with the partition type sheets and the shaftwall, head, joint and column enclosure details they reference, plus a few structural details. Its instructions focused on fire and life safety: construction classification, egress, fire-resistance ratings, opening protection and consistency across disciplines. Code checking was enabled.

Where plan tags and rated details part ways

The plans and the details describe different walls. Closet walls at columns and beside a slab opening are one-hour on the plans and two-hour in the details they call, two enclosure walls carry rated tags on types with no rated design, and the masonry type lists ratings its own legend contradicts. The shaftwall types point to stud partition heads, one horizontal shaftwall has two board thicknesses, and two joint system numbers are a digit short. Most of the type and detail sheets the construction-issue plans depend on are still stamped not for construction.

What to verify next

The architect should confirm the rating of every closet and shaft wall, make the plan tags, the type sheets and the details agree, and reissue the type and detail sheets for construction. Examples that cite a listing or requirement follow the documents and code sections the review cited; every example is a question for the architect and the building department.

12 selected examples from the review

Twelve distinct findings, summarized for professional verification.

01High priority

IT closet rated two ways

An IT closet’s walls are one-hour on the plan and two-hour in its column detail.

Why it matters: The walls could be built to the lower rating.

What to check: Set the rating and stud width; align tags and notes.

Architectural
02High priority

Shaft-side closet wall rated two ways

A plumbing closet wall beside a slab opening is one-hour on the plan, two-hour in detail.

Why it matters: A wall at a floor opening may be underrated.

What to check: Decide the rating and match plan and detail.

Architectural
03High priority

Rated tags on unrated types

Two column enclosure walls carry one-hour tags on types with no rated design.

Why it matters: No tested assembly backs the rating.

What to check: Retag with a rated type or add one.

Architectural
04Medium priority

Masonry rating list contradicts the legend

The block wall type lists one hour for tags its legend makes two- and three-hour.

Why it matters: Rated masonry walls carry conflicting ratings.

What to check: Correct the list to match the legend.

Architectural
05Medium priority

Shaftwall heads point to stud heads

Shaftwall types send their head joints to stud partition details, not the shaftwall heads.

Why it matters: Installers could use the wrong listed head joint.

What to check: Point each type to its own heads.

Architectural
06Medium priority

Type sheets not issued for construction

Most partition type and detail sheets are stamped not for construction beside construction-issue plans.

Why it matters: The rated wall information has no construction issue.

What to check: Reissue them or state which issue governs.

Architectural
07Medium priority

One shaftwall, two board thicknesses

Two details of the same two-hour horizontal shaftwall call different board thicknesses.

Why it matters: One may not match the cited listing.

What to check: Set one thickness per the listing.

Architectural
08Medium priority

Joint system numbers missing a digit

Two rated joint system numbers at masonry walls are a digit short.

Why it matters: The listed joints cannot be identified.

What to check: Print the complete numbers.

Architectural
09Medium priority

Cavity wall tags without a rating

Two masonry cavity wall tags omit the rating digit the legend requires.

Why it matters: Their fire rating cannot be read.

What to check: Add the digit and the width row.

Architectural
10Medium priority

Roof drains above their high points

Spot elevations put each lower roof drain above the sump high point around it.

Why it matters: Water would pond away from the drains.

What to check: Correct the spot elevations.

Architectural
11Low priority

Doors numbered for a room not shown

A storage room’s two doors carry a room number no plan tags.

Why it matters: Door schedule entries may miss the room.

What to check: Renumber the room or its doors.

Architectural
12Low priority

Detail titled for an unnamed level

A revised column enclosure detail is titled for “Level X” and called by no plan.

Why it matters: The floor it governs is unknown.

What to check: Title it with its level.

Architectural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Architectural and Structural

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Drawing coordination and code checking

Code checking was enabled alongside the review of plans, schedules, details, and notes.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check drawings and code references

    Read the detected code references alongside the drawing evidence.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination, completeness, and code-reference questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in November 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Which codes were checked?

Code checking was enabled for this review. Groundbook detects the codes a set references, reads the codes and amendments that governments publish online, and uses licensed codes only where a license allows it.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass