A footing steel table counts four footings where the plan shows six.

The work quantity schedule was traced line by line to the structural drawings, element specifications and explanatory note behind it.

  • Quantity takeoff
  • Bill of quantities
  • Steel specifications
  • Earthworks
85 pagesQuantity schedule and structural drawings
Coordination reviewCoordination and completeness within the set
75 findingsPotential issues surfaced for verification
7 examplesConcise review details below

Stormwater treatment quantity schedule

A work quantity schedule for a stormwater treatment facility, checked against the structural drawings for its chambers, tank slabs and steel-framed buildings.

What the review compared

The work quantity schedule was the checked document. The review traced its lines back to the structural drawings, element specifications, steel tables and explanatory note, recounting members and footings and recomputing volumes and masses where the drawings gave enough dimensions.

Where the quantities drift

Several totals come from tables that miscount what the drawings show, including wall struts, footings, platform posts and bar masses. Elsewhere the documents name different materials for the same work, such as the fill under the buildings and the bedding under a tank.

What to verify next

The designer should correct the source tables, and the estimator should then rebuild the affected quantity lines. Code checking was not enabled; the fire rating example compares the bracing’s stated role with the fire-safety rules the review cited and remains a question for the designer.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01High priority

Stability bracing has a lower fire rating

Bracing that the design note relies on for frame stability is rated below the main frame.

Why it matters: Losing the bracing in a fire weakens the frame.

What to check: Rate the bracing to its stated function.

Structural · Fire Protection
02Medium priority

Steel specification undercounts wall struts

The sections draw more wall strut length than the steel specification and quantity schedule carry.

Why it matters: Steel orders and the estimate run about 1.4 tonnes short.

What to check: Recount the struts and correct both totals.

Structural
03Medium priority

Footing steel is counted for four, not six

A footing steel table counts four footings of one type; the plan shows six.

Why it matters: Reinforcement ordered from the table would be short.

What to check: Correct the table to six footings.

Structural
04Medium priority

Bar mass overstates three tank slabs

One bar’s listed mass in three tank slab schedules does not match its diameter and length.

Why it matters: Those steel totals are overstated by about a fifth.

What to check: Correct the bar mass and update the totals.

Structural
05Medium priority

Anchor bolt sizes conflict

Foundation sheets give the column anchor bolts two different sizes.

Why it matters: Bolts and base plates cannot both be ordered.

What to check: Adopt one size across the sheets, note and schedule.

Structural
06Medium priority

Replacement fill is two materials

The explanatory note calls for medium sand; the drawings and quantity schedule carry sand-gravel mix.

Why it matters: The fill cannot be priced or ordered reliably.

What to check: Name one fill material in every document.

Structural
07Medium priority

Paving concrete exceeds its dimensions

The specification lists more paving and ramp concrete than the drawn dimensions produce.

Why it matters: The estimate carries roughly 18 percent too much.

What to check: Recalculate the volume and update the schedule.

Structural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Structural and Fire Protection

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.