The isolation instruction removes a fuse that does not feed the cabinet being isolated.

Four discipline drawings of the same loop were checked against each other and against the specification items that go out to bid.

  • Drawings and specification
  • Bid quantities
  • Signalling
  • Track and civil
45 pagesDiscipline drawings and specification
Coordination reviewCoordination and completeness within the set
40 findingsPotential issues surfaced for verification
7 examplesConcise review details below

Tram turning loop drawings and specification

Track, power supply, switches and signalling, and civil drawings for a tram turning loop, with the civil specification items for the bid.

What the review compared

The review checked the four discipline drawings against each other for every object shown on at least one of them, such as switches, cabinets, pits, cables and surfaces. It then checked each drawing against the specification items that will be priced. Building code requirements were out of scope.

Where drawings and items disagree

Quantities for the grass track, geotextile and seeding agree neither with the drawing nor with each other. Pits, transformer structures, ducts and cabinets carry different counts, types or numbers, and some items both reuse and replace the same equipment.

What to verify next

The track, power, signalling and civil designers should settle each object’s status and number, and the specification writer should then align the items before the work goes to bid. Code checking was not enabled; the examples are questions for the responsible designers.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01Medium priority

Grass track quantities exceed the drawing

Specification items price a larger grass track area than the civil drawing’s surfaces add up to.

Why it matters: Bids rest on unclear quantities.

What to check: Confirm the area and align the items.

Civil
02Medium priority

Two cable pits are new and existing

The specification prices six new cable pits; the drawing colors two of them as existing.

Why it matters: Supply and removal pricing is unclear.

What to check: Decide each pit’s status and align both.

Signalling
03Medium priority

One transformer structure or two

The signalling drawing shows two new transformer structures; the specification counts one.

Why it matters: Bids may omit one structure.

What to check: Correct the count or define the item.

Signalling
04Medium priority

Cable duct type conflicts

The drawing’s line type calls for one duct size; the specification item prescribes another.

Why it matters: The contractor cannot tell which duct to buy.

What to check: Align the drawing and the item.

Signalling
05Medium priority

One cabinet has two numbers

The power and signalling drawings give the cabinet at the same mast different numbers.

Why it matters: The wrong cabinet could be modified or registered.

What to check: Confirm the cabinet and use one number.

Electrical · Signalling
06Medium priority

Isolation names the wrong supply mast

The item for de-energizing a cabinet removes the fuse at a mast that feeds another cabinet.

Why it matters: Removing that fuse would leave the cabinet live.

What to check: Correct the mast reference.

Signalling
07Medium priority

Cabinet foundation is reused and renewed

One item reuses the cabinet foundation; the item it references asks for a new one.

Why it matters: Supply or reuse cannot be priced.

What to check: Decide and describe one foundation.

Signalling

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Signalling, Civil, Track, and Electrical

Check the findings with the responsible discipline designers.

02 · Priorities

Medium and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Check your discipline drawings against the specification items

Trusted by hundreds of professionals