Two columns the design schedules are missing from the shop drawings.

The fabricator’s erection plans and piece drawings were checked against the structural drawings and general notes they were prepared from.

  • Shop drawings
  • Submittal review
  • Structural steel
  • Delegated design
290 pagesShop drawings and structural drawings
Coordination reviewCoordination and completeness within the set
90 findingsPotential issues surfaced for verification
7 examplesConcise review details below

Structural steel shop drawings

A structural steel shop drawing submittal for one area of a multi-use event facility, reviewed against the issued structural drawings.

What the review compared

The review compared the steel fabricator’s erection plans, piece drawings and connection details for one area with the issued structural drawings, schedules and general notes. It checked members, sizes, elevations, base plates, welds, materials and the delegated connection design.

Where the submittal departs from the design

Columns and beams the design schedules are missing, some columns are split where the design runs them continuous, and several base plates are absent or do not fit their recessed footings. The delegated connection calculations were not included.

What to verify next

The engineer of record should return the submittal with the missing members, base plates and calculations listed, and check the resubmittal against each comment. This review did not enable code checking; the examples are questions for the engineer of record and the fabricator.

7 selected examples from the review

Seven distinct findings, summarized for professional verification.

01High priority

Scheduled columns are missing

Two columns the design schedules from foundation to second floor are absent from the shop drawings.

Why it matters: They would not be fabricated.

What to check: Add them to the erection plans.

Structural
02High priority

Columns split where the design runs them through

Five wall columns are split at a sloped beam; the design shows them continuous.

Why it matters: The detailed columns differ from the design.

What to check: Revise the columns to run continuous.

Structural
03Medium priority

Base plates missing at recessed footings

Seven columns set into recessed footings end with no base plate.

Why it matters: They cannot be anchored as designed.

What to check: Add the base plates the design detail shows.

Structural
04Medium priority

Base plates do not fit the recess

Seven other recessed column base plates are larger than the footing opening.

Why it matters: The plates cannot be set as detailed.

What to check: Resize them in the sealed connection design.

Structural
05Medium priority

Sealed connection calculations are missing

The design delegates connection design to the fabricator; the submittal has no sealed calculations.

Why it matters: The connections cannot be reviewed.

What to check: Submit sealed calculations for every connection.

Structural
06Medium priority

Field welds are below the general notes

Wall-support angle field welds are 3/16 inch; the general notes require 1/4 inch.

Why it matters: Welds fall below the stated minimum.

What to check: Revise the welds to 1/4 inch.

Structural
07Low priority

Steel grade differs from the general notes

Shop drawings call wide-flange pieces a different steel grade from the general notes.

Why it matters: Material could be ordered to the wrong standard.

What to check: Use the grade the notes specify.

Structural

Review scope and priorities

The review organized the questions by severity, discipline, and source context so the responsible designers could investigate them.

01 · Disciplines

Structural

Check the findings with the responsible discipline designers.

02 · Priorities

High, Medium, and Low priorities

Selected examples retain their assigned priority.

03 · Review scope

Coordination and completeness within the set

This review checked the documents against one another. No code check was enabled.

04 · Evidence

Findings connected to their source context

Groundbook links each finding to the sheets it came from so the responsible designer can confirm or dismiss it.

Potential impacts describe the issue type. They are not verified outcomes from this project.

Follow the information across the complete set

Groundbook reads the documents you upload and reports where they disagree, where a reference does not resolve, and where a required value is absent.

See how a full set is reviewed or how interfaces are coordinated.

  1. 1
    Map the complete set

    Identify sheets, disciplines, details, schedules, and notes.

  2. 2
    Connect repeated information

    Follow tags, references, and requirements wherever they reappear.

  3. 3
    Check coordination and completeness

    Compare the documents and identify missing or conflicting information.

  4. 4
    Return findings for verification

    Organize potential issues by severity, discipline, and supporting context.

Questions for professional verification

The output supports the responsible designers as they review the source documents and decide what needs to change.

What this result means

  • Groundbook surfaced potential issues for professional review.
  • Severity helps prioritize which questions to investigate.
  • The findings describe coordination and completeness questions in the uploaded set.
  • Each finding includes source context for verification.

What it does not mean

  • Every potential finding is a confirmed error or violation.
  • The project was unsafe, unbuildable, or ultimately noncompliant.
  • Groundbook replaced the responsible professionals or authority.
  • A correction was made, or any cost or delay was avoided.

About this review

Is this a real review?

Based on a Groundbook review completed in October 2026. Findings are summarized.

Are these findings confirmed defects?

No. Each one is a potential issue for the responsible designer to verify against the source documents. Groundbook reports what the documents say and where they disagree. It does not make design decisions, certify compliance, or replace the authority having jurisdiction.

How long did the review take?

Turnaround runs from 20 minutes to 24 hours depending on project size.

Was a code check included?

No code check was enabled for this review. It covered coordination and completeness within the set. Code checking is available: Groundbook reads the building codes that governments publish online and uses licensed codes only where a license allows it. You can upload a copy you’re licensed to use.

Can I see a full report?

Yes. The sample plan review report shows all 79 findings from one review of a drawing set and its specifications, with the cited excerpts.

Give the next drawing set a connected first pass

Upload the project, choose the checks that matter, and receive structured potential findings with source context.

Compare steel shop drawings with the structural design

Trusted by hundreds of professionals