Start with the Contract Documents definition and the installation paragraphs of the issued Section 31 21 13: they rely on approved design drawings for each building, so confirm that the drawings show every suction point, vent route, fan, discharge point, failure annunciator, power source, and enclosure, or that the section clearly makes the contractor responsible for that design and asks for it as a submittal. Then check that the building descriptions match the existing plans and roof, that the route and penetration restrictions agree with the drawings, and that the post-mitigation testing, redesign, and payment paragraphs can actually be administered.
Assemble the review package
Gather the floor plans for each building with room uses, the slab, foundation, and crawl space sections, the roof plan and exterior elevations, the reflected ceiling plans showing suspended ceilings, any pre-mitigation radon results and sub-slab diagnostic data, the mitigation drawings with suction points, vent risers, fans, discharge points, annunciators, and enclosures, the electrical drawings for the fan circuits, the historic preservation review if the building is listed, and the issued Section 31 21 13 with Sections 01 35 26, 01 20 00, 01 78 23, 07 84 00, and 09 29 00 and 09 90 00 where the project specifies renovation work separately. Follow one suction point from the slab penetration through the riser, fan, and roof discharge to its annunciator and circuit before assuming the others match.
WBDG publishes UFGS 31 21 13: Radon Mitigation as a public guide-specification reference (accessed November 17, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| Who designs the system and what the drawings show | Contract Documents definition (diagnostic testing, design, construction, and monitoring; this specification and the drawings listed in it) + Installation and Enclosures Installation (as indicated in the approved design drawings) + Short Term and Long Term testing (modifications reflected in the “Contractor’s design documents (drawings and design narrative)”) + Submittals (no item for design drawings, a narrative, or diagnostic results) + mitigation drawings | Do the drawings show the suction points, vent routes, fans, discharge points, annunciators, and enclosures for each building, or, if the contractor designs the systems, does the section add a submittal for the design drawings, narrative, and diagnostic results that the installation paragraphs call approved and the test paragraphs expect to be updated? |
| New construction or existing building | Opening note (new buildings, existing buildings, and enclosures) + new construction note (EPA radon zones; passive systems in the original design with provisions for later fans; a separate new-construction section “seems unnecessary” because materials sit in “Division 02 and Division 15”, retired division numbers) + Summary and Performance Requirements (target concentration bracket; unit of measure note) + Building Descriptions + slab and foundation sections | For new construction, are the sub-slab aggregate, soil-gas retarder, suction pipe, riser, and fan provision drawn and specified in the current earthwork, membrane, and plumbing or mechanical sections the note means, and for an existing building, does the section describe the actual buildings and use the unit of measure suited to the location? |
| Building descriptions and route restrictions | Building Descriptions note (construction of floors and walls in contact with soil, slab and aggregate thickness, number of floors, roof type and covering, suspended ceilings, occupancy during work, penetration restrictions, items embedded in the slab, routing restrictions) + sample paragraph + Furnishings brackets + historic property note + floor plans, roof plan, and elevations | Does each building description agree with the plans, sections, and roof plan, are the roof and elevation restrictions also drawn so riser routes respect them, are embedded conduits, grounding grids, or reinforcement in the slab identified before suction holes are cored, and is the historic preservation review complete where the building is listed? |
| Suction points, piping, and discharge | System Piping (route clear of operations; enclose in occupied spaces; listed unoccupied spaces and a blank; no enclosure above suspended ceilings) + Components (PVC DWV pipe; in-line fans; sealants; crawl space soil-gas retarder thickness in mils only; mock downspout bracket) + System Outlet Location (ANSI/AARST SGM-MFLB and EPA 402-R-93-078; rain cap bracket for freezing climates) + Back Drafting + Mechanical Work (ICC IMC, SMACNA 1378) + floor and roof plans | Do the plans show each riser’s route and its discharge point relative to roof openings, air intakes, and windows as the cited standards require, is the rain cap bracket kept or deleted for the climate, does every riser in an occupied space have an enclosure, has the specifier added a metric value to the crawl space membrane bracket, and are chimneys and fuel-burning appliances near each system identified for the back drafting requirement? |
| Fans, power, failure monitor, and labels | Electrical Work (NFPA 70; wire in EMT or surface metal raceway; power source distance that “should” be available and the length carried in the bid, both bracketed) + System Failure Warning Monitor (blockage, fan failure, and leakage; annunciator in an occupied space) + System Identification (labels on piping, enclosures, fans, conduit, and breakers; Public Works Office phone; NAVFAC note covering only “or as specified by the Contracting Officer”) + electrical plans and panel schedules | Do the electrical drawings show a circuit and a nearby power source for each fan, consistent with the length carried in the bid, does each system have an annunciator located in an occupied space, are the label wording and phone number filled in, and does the NAVFAC bracket around the label wording do what its note intends? |
| Enclosures and adjoining work | Radon Mitigation Systems Enclosures (first bracket with concrete, stud, gypsum board, sealant, paint, and hardware standards; second bracket pointing to the project’s own renovation sections) + gloss note + Enclosures Installation + Radon Mitigation System Inspection (verifies “the presence of fire stops”, which no paragraph specifies) + wall and ceiling details, finish schedule, and fire-rated assembly plans | Is one enclosure bracket kept to match whether the project has its own gypsum board and painting sections, do the details show enclosure framing, board, and finish matching adjacent surfaces, and where a riser passes a rated floor, wall, or roof, does the section or Section 07 84 00 specify the firestopping that the inspection checks for? |
| Worker protection and qualifications | Worker Health and Safety (29 CFR 1910.1096; OPNAV M-5090.1 and EM 385-1-1 brackets; protection plan contents; exposure records; medical certification; notification) + Respiratory Protection Program (fit testing; NIOSH-approved respirators; selection by the “Contractor’s Designated IH”, a role never defined) + Contractor Qualifications and Experience (NRPP, NRSB, or state credential; state listing bracket; experience brackets) + Testing Laboratory + On-Site Supervision + Preconstruction Conference (Section 01 35 26) | Has the specifier defined the Designated IH with a qualification and a submittal, chosen the OPNAV or EM 385-1-1 bracket for the agency, filled the state listing bracket where the state licenses mitigation contractors, and set experience brackets that suit the systems on the drawings? |
| Activation measurements, testing, and payment | Post Mitigation Functional Evaluation (suction and PFE measurements for ASD systems; airflow and pressure for other methods; no paragraph for the pre-mitigation diagnostic testing the definitions and Diagnostic Testing Equipment describe) + Radon Detector Location Log (EPA 402-R-92-014 Device Placement Log) + Short Term and Long Term testing (detector placement, timing, and laboratory reporting; redesign and retest; collection by the Contractor or the Contracting Officer bracket) + payment item citing a paragraph “POST MITIGATION TESTING - SCHEDULE OF PRICES DATA” that does not exist + unit price note | Does the bid schedule carry the unit price items the note asks for, has the specifier replaced the payment reference with the actual bid item, is pre-mitigation diagnostic testing specified if the contractor designs the systems, and do the floor plans used for the detector log show every enclosed space the testing paragraphs count? |
Worked example: sub-slab depressurization for an existing administration building
Illustrative example: an existing two-story administration building on a slab with a partial crawl space tested above the installation’s radon action level, and the project adds sub-slab depressurization. The issued Section 31 21 13 keeps both enclosure brackets, the rain cap prohibition, the crawl space membrane bracket, and the long-term payment item that cites a missing schedule of prices paragraph. The drawings show three suction points on the first floor plan but no riser routes, no fan or annunciator locations, and no roof discharge; the building description says roof penetrations are not permitted while a roof plan note calls for a vent through the roof; and no submittal asks the contractor for design drawings.
Ask the designer to decide whether the drawings or the contractor will lay out the systems, and to either draw the risers, fans, annunciators, and discharge points or add a design submittal with diagnostic testing. Ask the specifier to reconcile the roof penetration restriction with the vent route, to keep one enclosure bracket, to add a metric value to the crawl space membrane bracket, and to tie the long-term payment to a real bid item. Ask the facility’s safety office who serves as the Designated IH before the preconstruction conference.
Avoid a false conflict
Section 31 21 13 covers radon mitigation systems, their enclosures, worker protection, and post-mitigation testing. Firestopping follows Section 07 84 00, gypsum board and painting follow Sections 09 29 00 and 09 90 00 where the project has them, safety follows Section 01 35 26 and EM 385-1-1, bid items follow Section 01 20 00 or the activity’s instructions to bidders, and the adopted building and mechanical codes, any state radon licensing law, ANSI/AARST SGM-MFLB and MA-MFLB, and the EPA protocols govern the work, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the payment item cites a schedule of prices paragraph that is not in the section, the new construction note uses retired division numbers and doubts that a new-construction section is needed, the Designated IH is never defined, the definitions and test paragraphs point to diagnostic testing and contractor design documents that no paragraph or submittal covers, the crawl space membrane is in mils only, and the inspection checks fire stops that nothing specifies. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.