We’re at NCSEA in San Francisco, Oct 28–29 · Booth 110NCSEA · Booth 110 · Oct 28–29

Guide · Code reference

UFC 3-101-01 Architecture document review for DoD projects

UFC 3-101-01 is where DoD adds to the IBC’s architectural provisions and sets its own rules for air barriers, mockups, acoustics, and building area. Groundbook can compare the architectural drawings, wall sections, schedules, and specifications with the UFC 3-101-01 version you upload and flag where they disagree.

Confirm which version of UFC 3-101-01 the contract invokes, since WBDG now lists a reissued digital edition, then walk its IBC modifications chapter by chapter through the wall sections, slab and roof details, finish schedules, and specifications. Next check the design criteria in its Chapter 3: air barrier boundaries and testing, the envelope path for renovations and additions, mockups, and interior and site acoustics. AI can flag conflicts; the architect of record and the DoD reviewer decide compliance.

What does UFC 3-101-01 cover?

The digital UFC 3-101-01 states that it provides technical requirements, model code modifications, and requirements for architectural design services, for architects to use in plans, specifications, calculations, construction documents, and design-build requests for proposals. It describes itself as the minimum architectural requirements; project conditions and programs may call for more.

WBDG’s UFC 3-101-01 page lists the criteria as active digital UFC content, first published July 2, 2026, and tells teams to refer to UFC 1-200-01 for project applicability. The digital criteria viewer labels the latest version September 30, 2026. Checked October 16, 2026. WBDG’s change summary compares it with the 2020 edition with Change 4 and describes a consolidation that deleted the former programming, design services, and best practices content, promoting the air barrier modification and mockup guidance into criteria. Contracts awarded before the reissue may invoke a superseded PDF version; record the version and date the task order names.

Chapter 2 adds to or supplements IBC provisions on interior finishes and paint selection, ventilation openings and interior acoustics, exterior wall materials, vapor retarders, window selection by environmental severity, and EIFS, roof vapor retarders, below-grade dampproofing and foundation drains, slab vapor retarders and insulation, masonry flashing and weeps, wood clearances, and gypsum board and trim. Chapter 3 covers design quality and installation design guidance, historic buildings, space planning, gross building area, orientation, hazard prevention including radon, air barrier design and testing, mockups, fenestration, and outside-to-inside noise. See the UFC 1-200-01 guide for applicability and the IBC Chapter 14 guide for the exterior wall provisions it modifies.

Gather the envelope, interiors, and criteria documents

Collect the task order naming the UFC version, the code analysis, floor plans, elevations, wall sections and envelope details, wall and partition types, room finish and door schedules, the basis of design with the gross area calculation and block diagram, and the specifications, including the air barrier testing section if one is used. Add the project’s environmental severity classification from UFC 1-200-01, the installation design guide, the geotechnical report, and the noise contour map or acoustic study for the site.

For renovations and additions, add the existing conditions survey and any earlier air leakage test, because the UFC’s envelope modification paths depend on whether an air barrier already exists.

Trace architectural criteria through the set

UFC 3-101-01 document coordination checksSwipe or scroll sideways to read all columns.
Review questionSources to compareDecision to record
Air barrier boundary and test zonesWall sections, envelope details, building sections, specificationsConfirm the air barrier components, joints, and penetrations are detailed, the test zone boundaries and envelope area are on the drawings, and the testing section is in the project manual.
Envelope path for renovations and additionsScope narrative, existing conditions survey, envelope details, specificationsRecord whether the work is a major or minor envelope modification, with or without an existing air barrier, or an addition, and where the pressure testing or cost analysis that path calls for is scoped.
MockupsSpecifications, design criteria, AHJ correspondenceRecord whether the AHJ wants an on-site wall mockup and whether the specification lists its components and the air and water tests to run on it.
Moisture and vapor controlWall, roof, and slab sections, hygrothermal analysis, interior finish scheduleCheck each assembly for a single vapor retarder, the sheathing and interior finishes on exterior walls, and slab vapor retarder and moisture testing in the specifications.
Interior and facade acousticsPartition types, door schedule, room finish schedule, noise contour map, acoustic reportMatch partition and door sound ratings to the space types in the UFC table, and record whether nearby noise sources call for an acoustic study and facade isolation targets.
Fire-resistance rated wall typesWall type sheets, code analysis, life safety plansRecord the tested assembly each rated wall type cites, since WBDG’s change summary notes the UFC no longer names a specific assemblies directory and relies on the IBC and NFPA 101 test basis.

Air barriers continue in the air barrier specifications guide, masonry flashing and weeps in the masonry specifications guide, and rated walls in the IBC Chapter 7 guide.

Example: an addition with no test boundary

Hypothetical example. A two-story addition to an existing company operations facility shares a return air plenum with the original building. The envelope narrative says the addition will be pressure tested, but the wall sections show no temporary air barrier at the connection, no test zone boundary is drawn, and the project manual has no air barrier testing section.

The envelope narrative calls for pressure testing the addition, but the drawings show a shared return plenum with no temporary air barrier or test boundary, and the specifications omit the air barrier testing section. Confirm the test approach and coordinate the details and specifications.

The architect confirms the test approach with the DoD reviewer and adds the boundary and testing section. The finding is a gap between the narrative and the documents, not a leakage result.

Review architectural documents with Groundbook

Upload the current drawings and specifications to Groundbook, and state the edition, amendments, and review scope in your instructions. Add UFC 3-101-01 and the other UFCs the task order names from WBDG, which publishes them free, plus the model codes and standards the project uses from copies you are licensed to upload.

Compare the code analysis, floor plans, elevations, wall sections, envelope details, partition and door schedules, room finish schedule, basis of design, and specifications. Flag a conflicting UFC version, air barrier components or test boundaries the drawings do not show, renovation or addition scope with no testing path, assemblies with more than one vapor retarder, partition or door sound ratings that differ from the space type, and rated wall types with no tested assembly. Use the supplied UFC 3-101-01 and cite both sources.

Groundbook links each potential finding to the sheets and documents involved. It does not run hygrothermal, acoustic, or air leakage analysis, or calculate building area.

Document review does not certify compliance with DoD criteria or replace the architect of record, the acoustic consultant, or the DoD authority.

Questions, answered

FAQs

Did UFC 3-101-01 change in 2026?

Yes. WBDG lists a reissued digital UFC 3-101-01, first published July 2, 2026, and the digital criteria viewer labels the latest version September 30, 2026. WBDG’s change summary compares it with the 2020 edition with Change 4.

Does UFC 3-101-01 still require the UL Fire Rated Assemblies Directory?

WBDG’s change summary says the reissue removed that requirement because the IBC and NFPA 101 already require fire-resistance ratings based on recognized test standards. It notes the underlying requirement has not changed.

Can Groundbook check drawings against UFC 3-101-01?

It can compare supplied drawings and specifications with the UFC you upload and flag potential conflicts with links to the sources. It does not calculate or certify the design.

Bring your next set into focus

Set up a review or talk through your project with our team.

Check your architectural set against UFC 3-101-01

Trusted by hundreds of professionals