Guide · Specifications and drawings · 07 54 23

Check roofing membrane specifications against drawings

A roof plan shows where a membrane goes; the specification decides how it must be attached, flashed, and warranted. Compare both before treating one hatch pattern as the whole roof assembly.

Trace the roof plan’s membrane areas into the specified system, substrate, attachment, and flashing requirements, then confirm slope, insulation, and warranty scope match the same roof area before closing a roofing coordination question.

Assemble the review package

Gather the roof plan, roof details for edges, curbs, and penetrations, the insulation or taper layout, and the issued roofing specification. Include mechanical and electrical roof-penetration information and any existing-roof condition data for a re-roof. This guide focuses on TPO membrane roofing; identify the separate specification and details for other membrane types before comparing requirements.

WBDG publishes UFGS 07 54 23: Thermoplastic-Polyolefin Roofing as a public guide-specification reference (accessed September 18, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
System extentRoof plan area + specification scopeDo the documents identify which roof areas receive this membrane and distinguish them from adjacent roof types or existing roofing to remain?
Slope and drainageRoof plan slope and drain layout + drainage clausesCan the drainage path to each roof drain, scupper, or edge be followed, and does it match the specified minimum slope?
Substrate and insulationRoof section + substrate and insulation clausesDoes the specified substrate and insulation match what the roof section shows, including tapered insulation and cover board?
Attachment methodSpecification attachment clauses + roof detailIs the attachment method identifiable and consistent between the roof plan notes and the specification, especially at perimeter and corner wind zones?
Flashing and terminationsEdge, curb, and wall details + flashing clausesDoes each membrane termination shown in the details reference a compatible flashing accessory and method?
PenetrationsMEP roof-penetration plan + penetration and flashing clausesAre penetrations detailed for the specified system rather than left to a generic sealant note?
Walkways and protectionTraffic and maintenance-path notes + walkway-pad clausesAre equipment access paths and protection pads shown where the specification requires them?
Warranty scopeSpecified warranty term or type + roof area and system boundaryDoes the documented warranty scope match the actual roof area, system, and any excluded existing-to-remain sections?

Worked example: a curb outside the flashed area

Illustrative example: a mechanical roof-penetration plan shows a new rooftop-unit curb near a roof edge, but the roof detail sheet’s flashing details only cover curbs located away from the perimeter high-wind zone. The specification lists a perimeter attachment requirement that the curb detail does not reference.

Mark the curb location against the roof plan’s wind-zone layout, pair it with the specification’s perimeter clauses, and ask the roofing designer to confirm the correct attachment and flashing detail for that location. Recheck the walkway and warranty scope after the detail is revised, since a relocated curb can affect both.

Avoid a false conflict

A roof detail drawn for one location does not automatically apply to every similar condition; wind-zone requirements, existing-roof interfaces, and warranty exclusions can change the correct answer for what looks like the same curb or edge. Confirm the specific roof area before extending a detail elsewhere.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should a roofing membrane review compare?

Compare system extent, slope and drainage, substrate and insulation, attachment method, flashing at terminations and penetrations, walkway protection, and warranty scope for the same roof area.

Does this checklist confirm wind-uplift or code compliance?

No. It compares the design documents for consistency. Wind-uplift design, code compliance, and installation acceptance remain with the responsible engineer, roofing consultant, and authority having jurisdiction.

Why check warranty scope separately from the roofing specification?

A manufacturer warranty can exclude specific areas, attachment methods, or existing-roof interfaces that the drawings do not call out, and a mismatch there is a common source of disputes at closeout.

Keep exploring

Continue your review

Check resilient flooring specifications against drawings

Compare resilient flooring types, substrate moisture testing, transitions, and adhesive compatibility across finish plans and specifications.

Explore

Roofing and waterproofing review checklist

Trace slope, drainage, overflow, edges, penetrations, and transitions through a roof and below-grade package. 12 prompts and a free editable CSV.

Explore

Check lightning protection specifications against drawings

Compare system type, air terminals, down conductors, ground rods, test wells, fence bonding, and testing across roof plans and UFGS Section 26 41 00.

Explore

SDI steel deck review: deck type, thickness, finish, attachment, side laps, diaphragms, and composite slabs

Review roof and floor deck against ANSI/SDI SD-2022: deck type, gauge, finish, attachment, side laps, diaphragm schedule, and composite slabs. With AI limits.

Explore

Check roof insulation specifications against roof plans and details

Compare roof insulation R-value, tapered layout, thermal barrier, wind attachment zones, vapor retarder, and nailers with UFGS 07 22 00.

Explore

Check metal roof panel specifications against roof plans and details

Compare metal roof panel type, material and finish, wind uplift, underlayment, flashing and closures, gutters, glare, and leak testing with UFGS 07 41 13.

Explore

Drawings vs. specifications

Compare drawing requirements with specifications, schedules, and controls. Find potential equipment, material, and scope inconsistencies with Groundbook AI.