A shop drawing review asks one question in many forms: does this fabricator’s interpretation match the contract documents it was prepared from? The answer usually lives in two places at once.

Establish which contract issue the shop drawings were prepared from, then compare marks, sizes, elevations, connections, and embeds against it. Record differences with both references. Reviewing shop drawings for conformance with the design concept is the engineer of record’s responsibility; a document review prepares that work rather than replacing it.

Assemble a reviewable package

Gather the erection plans, member details, connection details, and the anchor or embed drawings, alongside the contract structural drawings, general notes, and the steel specification section. Include the connection design criteria and the transmittal that states which contract issue the set was prepared from.

Agree which areas and which design milestone are being reviewed, and record any document you expected and did not receive. A review can only compare what it is given, so a missing sheet is a finding in its own right. The drawing register template gives you somewhere to record the governing issue before you start.

Twelve document checks

Use one worksheet row per condition rather than per sheet. Where a condition repeats, note the locations you sampled and any exception you found. The CSV adds blank fields for the project location, source issue, reviewer, decision, revised sources, and closure evidence.

Structural steel shop drawing review checklistSwipe or scroll sideways to read all columns.
Review areaSources to compareQuestion to resolve
Contract basisStructural drawings, general notes, specification sectionWhich issue of the contract documents is the shop drawing set prepared from, and is it the current one?
Member identityErection plan marks, contract framing plan, member scheduleDoes each shop mark resolve to one contract member with the same size, grade, and location?
Connection design basisGeneral notes, connection details, delegated design scopeIs the connection designer identified, and are the reaction loads or criteria they were given stated on the drawings?
Camber and elevationErection plan, contract framing, top of steel notesAre top-of-steel elevations and any camber stated, and do they agree with the contract levels?
Bolting and weldingConnection details, welding symbols, specificationAre joint types, weld sizes, and bolt grades shown consistently between shop details and the specification?
Openings and penetrationsBeam penetration details, MEP coordination drawingsIs each web penetration located, detailed, and traceable to an engineer-reviewed condition?
Embeds and anchorsAnchor plans, foundation drawings, embed schedulesDoes every anchor and embed appear on both the steel and the concrete documents with the same location and projection?
Interface with other tradesCurtain wall, stair, canopy, and equipment support detailsAre delegated interfaces identified with the party supplying each side of the connection?
Coatings and fire protectionFinish schedule, fireproofing notes, specificationIs the required coating and fire-resistive treatment stated for each member group, including surfaces left unprotected?
Erection sequenceErection plan, temporary bracing notesIs the assumed sequence and temporary stability responsibility stated, and does it reference the party responsible?
Submittal statusTransmittal, review stamps, revision cloudsWhich sheets are for review, which are revised, and what changed since the previous submission?
Revision closureReviewer comments, revised shop drawings, contract documentsDoes each comment have a response, and do the revised sheets reflect the accepted resolution?

Record “needs clarification” when a reference is missing, and reserve “resolved” for a decision supported by documents you have read. If a row does not apply to this project, write why: a blank cell cannot tell a skipped check from a completed one.

Work one condition end to end

Take one transfer beam. Find its shop mark on the erection plan, follow it to its member detail, then find the same member on the contract framing plan. Compare size, grade, top-of-steel elevation, and camber. Then open both end connections and check that the reactions or criteria they were designed to are stated somewhere in the set. Finally, find its anchors or embeds on the concrete documents. A single member traced this way tests the whole interface.

Working one condition all the way through beats skimming every sheet, because it forces each document to answer the same question. When the answers differ, you have a finding with two references attached, which is what a designer needs in order to decide.

Close the loop

A response saying “coordinated” is the start of verification, not the end. Open the revised sheets, confirm the change, then follow it into the dependent documents: the schedule, the detail, the specification section, and the other discipline that relied on it. Record the sources you checked and the evidence that closed the question.

Where the answer is a decision rather than a correction, record the decision and who made it. The guide to prioritising findings covers how to sort what you have found once the list gets long.

Use AI for a source-linked first pass

Groundbook AI can run these comparisons across the whole set at once, returning each difference with both sheets highlighted and the supporting sources linked. It reads drawings, specifications, reports, checklists, and the building codes you upload, including scanned and hand-drawn sheets. Give the review a defined scope, then verify every cited location before turning a finding into a request.

The findings are questions for your team to settle. Design, engineering, and compliance decisions stay with the responsible professionals and the authority having jurisdiction.

Questions, answered

FAQs

Is reviewing shop drawings the same as approving them?

No. The engineer of record reviews submittals for conformance with the design concept, within the responsibilities set by the contract. A document review finds the places where the shop drawings and the contract documents disagree, so the reviewer spends their time deciding rather than hunting.

What causes the most shop drawing rework?

Connections designed to criteria that are not stated on the drawings, embeds that appear on one discipline’s documents but not the other, and shop drawings prepared from a superseded contract issue.

Does Groundbook review shop drawings?

It reviews them as documents: comparing the shop set against the contract set, the specification, and each other, and returning differences with both sheets linked. Fabrication, engineering, and approval decisions remain with the responsible parties.

Bring your next set into focus

Set up a review or talk through your project with our team.