Guide · Specifications and drawings · 08 71 63

Check detention hardware specifications against hardware sets, door schedules, keying, and electrical drawings

UFGS Section 08 71 63 Detention Hardware, a NAVFAC-prepared guide specification issued in August 2024 after a complete review and update, covers hardware for doors in brigs and detention facilities. It requires a hardware item list and hardware schedule, an installer approved by the hardware manufacturer, listings for electrically operated locks and for hardware on labeled fire doors, and a coordination conference, then specifies restricted Mogul keys and cylinders, builders cylinders, a detention keying system, security-pin and electric hinges, seven lock types from solenoid jamb locks to lever tumbler deadlocks and access door spring locks, surface and concealed closers, strikes with monitoring switches, ligature-resistant pulls, stops and holders, head and foot bolts, mortised and magnetic door position switches, wall bumpers, thresholds, drip strips, weatherstrip, tamper-resistant fasteners, BHMA finishes, installation, fire and exit door requirements, field testing, and training.

Start with the hardware sets on the drawings or in the project manual: confirm that every detention opening on the door schedule has a set, that each set names lock, closer, stop, and switch types the issued Section 08 71 63 keeps, and that the keying groups (exterior, corridor, utility and food pass, and each cell group) appear on a keying schedule. Then check that electric locks and position switches are powered and monitored on the electrical and security drawings, that fire-rated and egress doors get listed hardware, that cell-side trim is ligature resistant, and that the section’s cylinder, keying, listing, weatherstrip, and fastener wording is resolved.

Assemble the review package

Gather the floor plans with door numbers, the security perimeter, and the housing groups, the door schedule with fire ratings and hardware set numbers, the detention hardware sets, the keying schedule or keying intent, the life safety plan with egress doors and any locking arrangements the code analysis relies on, the electrical and electronic security drawings with lock power, control panels, and door position monitoring, the fire alarm drawings if doors release on alarm, the door and frame elevations and frame head details, and the issued Section 08 71 63 with Sections 08 34 63, 08 71 00, 08 11 13, 28 10 05, 01 78 23, and the security criteria. Follow one cell group from its doors through the hardware set, keying group, lock power, and control panel before assuming the others match.

WBDG publishes UFGS 08 71 63: Detention Hardware as a public guide-specification reference (accessed November 16, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
Hardware sets against the door scheduleDetention Hardware Schedule (item list: type, item number, quantity, size, reference type number, catalog number, key control symbols, UL mark if fire rated, BHMA finish; schedule: set number, openings, opening description, fire rating, sound rating, items) + Strikes (dust box and monitoring switch “where indicated in set numbers”) + Section 08 34 63 drawing note (hardware set number in the door schedule) + door schedule and hardware setsSince this section has no designer note on what the drawings must show, do the drawings or the project manual contain the hardware sets the strikes and switches refer to, does every detention door on the schedule have one, and does each set give the lock, cylinder, hinge, closer, stop, switch, and trim types by the type names this section uses?
Lock types and where each is usedDetention Locks (ligature-resistant interior trim where trim is specified) + Type 1 (solenoid jamb lock, line-voltage AC, signal switches, push button in the frame at cell doors) + Type 2 (paracentric lever tumbler deadlock) + Type 3 (low-voltage DC deadlocking latchlock “to conform to UL 10B”) + Type 4 (Mogul mortise lock, knob-operated deadbolt) + Type 5 and Type 6 (Mogul lever tumbler latch lock and deadlock) + Type 7 (Mogul spring lock for chase and access doors) + Regulatory Requirements (electrically operated locks to UL 1034) + hardware setsDoes each set name the lock type that suits the door’s role (cell, corridor, sallyport, exterior, utility, access panel), has the Type 3 lock been tied to the electric lock listing the Regulatory Requirements article names instead of a door assembly fire test, and has the specifier deleted the unused lock types and corrected the garbled bolt sizes in Types 4, 6, and 7?
Cylinders, keys, and keying groupsKeys and Cylinders (BHMA A156.5) + Mogul Keys (described for pin tumbler locks) + Mogul Cylinder (restricted keys, UL 437) + Builders Cylinder (used by Type 1 and Type 3 locks) + Detention Keying System (dissimilar combinations, brackets for each building and for wickets, food passes, and dormitory groups; two systems, Mogul and paracentric) + Keys (sent directly to the Contracting Officer) + Section 08 34 63 access panel locks (entered into this keying system) + keying scheduleDoes a keying schedule show the exterior, corridor, utility, and cell groups the keying paragraph describes, which system do the builders cylinders in Type 1 and Type 3 locks belong to, since the section sets up only a Mogul and a paracentric system, where are the paracentric key and cylinder specified, and are the Mogul-keyed lever tumbler locks compatible with keys the section describes for pin tumbler locks?
Hinges, closers, stops, and frame headsDetention Hinges (BHMA A156.1 and A156.7 types with security pins; garbled sentence on continuous conduction wiring; twist-off or spanner screws; zinc coated with prime coat on exterior doors; junction box and mortar shield; electric hinges to UL 634) + Type 1 Door Closers (surface, higher BHMA grade) + Type 2 Door Closers (concealed overhead, lower BHMA grade, installed in a deep head section) + Door Stops and Holders (PH1, PH2, OH3, FS1 to FS3) + Wall Bumpers + Section 08 34 63 frames (no head depth stated)Where a set uses electric hinges, is the conductor count stated and the hinge wired on the electrical drawings, where a set uses the concealed closer, does the frame elevation show the head depth it needs and has the lower closer grade been accepted for that door, and do the stops and holders chosen avoid creating ligature points on the cell side?
Ligature resistance and trimDetention Locks (ligature-resistant trim on the interior of all locks where trim is specified) + Door Trim (ligature-resistant pulls on the interior of all doors) + Loop Type Pulls (surface loop pulls) + Flush Type Pulls + Type 4 Lock (knob-operated deadbolt) + Deadbolts (surface head and foot bolts) + hardware sets and room dataDo the sets put flush or other ligature-resistant trim on the cell side and limit loop pulls and knob-operated deadbolts to the secure side, and has the specifier defined “interior” for each door type, since a cell door, a corridor door, and an exterior door have different secure and inmate sides?
Electrified hardware, monitoring, and powerShop Drawings (bracket for power components and wiring coordination) + Regulatory Requirements (NFPA 70 for electrically controlled hardware) + Type 1 and Type 3 locks (different supply types; signal switches; plug connectors) + Type 1 Door Position Switch (mortised arm; broken face plate sentence) + Type 2 Door Position Switch (magnetic, UL 634; power rating stated in volts) + Coordination Conference and Training (a locking control system this section does not specify) + electrical and security drawingsDo the electrical drawings provide the right supply type to each electric lock, does the security system monitor every lock signal switch and door position switch the sets call for, which section specifies the locking control system and control panels that the conference and training refer to, and has the switch power rating been restated in the right unit?
Fire doors, egress, and listingsRegulatory Requirements (hardware on labeled fire doors listed to UL 10B; egress doors to NFPA 101; electric locks to UL 1034) + Hardware Item List (UL mark if fire rated) + Fire Doors and Exit Doors (NFPA 72 door alarms, NFPA 80 fire doors, NFPA 101 exit doors, NFPA 252; bracket for tin-clad fire doors to UL 14C) + life safety plan and code analysisDoes the life safety plan show which detention doors are rated and which are on the means of egress, does each of those sets name listed hardware, are the locking arrangements the code analysis relies on for the detention occupancy reflected in the sets and the release sequence, and has the tin-clad fire door bracket been deleted, since this section and Section 08 34 63 cover steel detention doors?
Thresholds, weatherstrip, fasteners, and installationThresholds (aluminum, panic stop, insert) + Threshold Installation (sealant bed; cadmium-plated screws; underside coated with fluid-applied waterproofing from no named section) + Drip Strip (welded to shower doors) + Weatherstrip (adhesive silicone seal) + Weatherstripping Installation (stop-applied screwed, interlocking nailed, spring tension nailed; “bronze nails with bronze”) + bracketed lightproofing and soundproofing installation (no product) + Screws and Fasteners and note (choose a tamper-resistant fastener type; spanner heads on exposed hardware) + Installation (wood screws, sheet metal screws, and toggle bolts)Has the specifier kept one weatherstrip product and the installation that suits a steel detention door, deleted the nailed types and the wood and toggle fasteners or limited them to non-detention surfaces, chosen the tamper-resistant fastener type the note asks for, and either specified a sound seal or deleted the soundproofing bracket where the schedule shows no sound rating?

Worked example: a housing unit with electric cell locks, two keying systems, and an unrated corridor door

Illustrative example: a detention facility addition has two cell groups, a dayroom, a sallyport, and a control room. The hardware sets give the cell doors Type 1 solenoid locks with builders cylinders, the corridor doors Type 4 Mogul mortise locks with loop pulls on both sides, the sallyport a Type 3 lock, and the chases Type 7 locks. The issued Section 08 71 63 keeps all seven lock types, both closer types, all three weatherstripping installations, the soundproofing bracket, and the tin-clad bracket. The electrical plans power the Type 3 lock with the same supply as the Type 1 locks, the life safety plan shows the corridor door on the means of egress with a fire rating that the door schedule omits, and no keying schedule exists.

Ask the hardware consultant to add a keying schedule that places the builders cylinders, the Mogul cylinders, and any paracentric cylinders in named systems and groups, to replace the loop pull on the corridor door’s inmate side with a ligature-resistant pull, and to list rated hardware for the corridor door once the architect adds its rating to the schedule. Ask the electrical and security designers to correct the Type 3 lock supply and to show monitoring for every signal and position switch. Ask the specifier to tie the Type 3 lock to the electric lock listing, to delete unused lock types, the nailed weatherstripping, the wood and toggle fasteners, the soundproofing bracket, and the tin-clad bracket, to fix the garbled bolt and switch ratings, and to name the section that specifies the locking control system.

Avoid a false conflict

Section 08 71 63 covers detention locks, cylinders and keying, hinges, closers, trim, stops, bolts, door position switches, accessories, and fasteners. Detention doors, frames, reinforcements, and access panels follow Section 08 34 63 and the detention door and frame guide, commercial hardware follows Section 08 71 00 and the door hardware guide, commercial doors and frames follow Section 08 11 13, the locking control system, control panels, and monitoring follow the electronic security and electrical sections, and the adopted building code, NFPA 101, NFPA 80, and the facility’s security criteria govern egress, fire doors, and locking arrangements, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the hardware schedule is to be submitted with samples that are never requested, builders cylinders sit outside both keying systems and the paracentric cylinder has no paragraph, Mogul keys are described for pin tumbler locks used on lever tumbler locks, the Type 3 lock cites a door assembly fire test, loop pulls and a knob deadbolt sit beside a ligature-resistance requirement, several bolt sizes, the hinge conduction sentence, and a switch rating are garbled, the weatherstrip product does not match its installation types, the installation fasteners contradict the tamper-resistant fastener requirement, the soundproofing and tin-clad brackets have no product, and the conference and training name a locking control system the section does not specify. Ask the specifier which wording the project intends before treating a difference as a design conflict.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should a detention hardware specification review compare?

Compare hardware sets against the door schedule, lock types and where each is used, cylinders, keys, and keying groups, hinges, closers, stops, and frame heads, ligature resistance and trim, electrified hardware, monitoring, and power, fire doors, egress, and listings, and thresholds, weatherstrip, fasteners, and installation.

What lock types does UFGS 08 71 63 include?

The current UFGS 08 71 63 Detention Hardware on WBDG specifies seven lock types: an electro-mechanical solenoid jamb lock, a paracentric lever tumbler deadlock, an electro-mechanical deadlocking latchlock, a Mogul mortise lock, a Mogul deadlocking latch lock, a Mogul deadlock, and a Mogul spring lock for chase and access doors. The hardware sets choose among them for each opening. UFGS numbers are DoD guide specification numbers, not universal MasterFormat titles, and your project’s issued specification governs.

How is this different from the door hardware and detention door pages?

UFGS 08 71 00 covers commercial door hardware, and the door hardware page checks hardware sets, operation, and access control for ordinary openings. UFGS 08 71 63 covers detention hardware: restricted Mogul and paracentric keying, security-pin hinges, detention lock types, ligature-resistant trim, door position monitoring, and tamper-resistant fasteners. The detention door and frame page covers the doors, frames, lock pockets, and reinforcements this hardware mounts into under UFGS 08 34 63.

Can Groundbook check detention hardware sets against Section 08 71 63?

Groundbook compares the drawing set with the specification sections and reference documents you upload, such as your issued Section 08 71 63, the hardware sets and keying schedule, Section 08 34 63, the electrical and security sections, the life safety plan, and licensed standards you hold, and returns potential conflicts with links to the source pages. It has no built-in code library and does not design hardware or keying systems, calculate electrical loads, certify listings, security ratings, or code compliance, or approve submittals. Each finding is a question for the architect, the hardware consultant, the security or electrical designer, or the contracting officer.

Keep exploring

Continue your review

Check door hardware specifications against door schedules

Match door numbers and hardware sets with operation, frame preparation, access control, and specification requirements. Includes an editable checklist.

Explore

Check steel door and frame specifications against schedules

Compare door and frame type, gauge, fire rating, and anchor type across door schedules and specifications. Editable CSV included.

Explore

Door schedule review checklist

Check door schedules against plans, frames, hardware, specifications, and access control. Includes 12 review prompts, a worked example, and a free CSV.

Explore

Check electronic security system specifications against drawings

Compare intrusion detection, access control, and video surveillance subsystem assignment and door-hardware interface across specifications and drawings.

Explore

Low-voltage, security, and AV review checklist

Review technology systems, pathways, head-end rooms, access control, life-safety interlocks, and AV against the electrical and hardware documents. Free CSV.

Explore

Check sound control door specifications against door schedules

Compare STC-rated door assemblies, fire labels, frame infill, seals, door bottoms, thresholds, and STC hardware with UFGS 08 34 73 and the door schedule.

Explore

NFPA 80 fire door and opening review

Review NFPA 80 fire door documents across opening schedules, rated walls, hardware, and details. Connect each question to a specific opening and source.

Explore

NFPA 101 life safety plan review

Review NFPA 101 life safety documents across occupancy, exits, doors, stairs, barriers, and system references. Connect the design basis to current plans.

Explore

NFPA 72 fire alarm plan review

Review fire alarm layouts, risers, device schedules, and system interfaces using the applicable NFPA 72 reference. Connect every question to its documents.

Explore

NFPA 70 National Electrical Code plan review

Review electrical drawings against NFPA 70 (NEC) across one-lines, panel schedules, equipment, rooms, and other trades. See checks and AI review limits.

Explore

IBC Chapter 10 means of egress: plan review

What 2024 IBC Chapter 10 governs and how to check egress plans: occupant load, exits, travel distance, doors, stairs, corridors, and exit discharge.

Explore

Check detention hollow metal door and frame specifications against door schedules, wall types, and opening details

Compare detention door and frame construction, frame anchorage, lock pockets, glazing stops, port openings, and access panels with UFGS 08 34 63.

Explore

Drawings vs. specifications

Compare drawing requirements with specifications, schedules, and controls. Find potential equipment, material, and scope inconsistencies with Groundbook AI.