Start with the hardware sets on the drawings or in the project manual: confirm that every detention opening on the door schedule has a set, that each set names lock, closer, stop, and switch types the issued Section 08 71 63 keeps, and that the keying groups (exterior, corridor, utility and food pass, and each cell group) appear on a keying schedule. Then check that electric locks and position switches are powered and monitored on the electrical and security drawings, that fire-rated and egress doors get listed hardware, that cell-side trim is ligature resistant, and that the section’s cylinder, keying, listing, weatherstrip, and fastener wording is resolved.
Assemble the review package
Gather the floor plans with door numbers, the security perimeter, and the housing groups, the door schedule with fire ratings and hardware set numbers, the detention hardware sets, the keying schedule or keying intent, the life safety plan with egress doors and any locking arrangements the code analysis relies on, the electrical and electronic security drawings with lock power, control panels, and door position monitoring, the fire alarm drawings if doors release on alarm, the door and frame elevations and frame head details, and the issued Section 08 71 63 with Sections 08 34 63, 08 71 00, 08 11 13, 28 10 05, 01 78 23, and the security criteria. Follow one cell group from its doors through the hardware set, keying group, lock power, and control panel before assuming the others match.
WBDG publishes UFGS 08 71 63: Detention Hardware as a public guide-specification reference (accessed November 16, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| Hardware sets against the door schedule | Detention Hardware Schedule (item list: type, item number, quantity, size, reference type number, catalog number, key control symbols, UL mark if fire rated, BHMA finish; schedule: set number, openings, opening description, fire rating, sound rating, items) + Strikes (dust box and monitoring switch “where indicated in set numbers”) + Section 08 34 63 drawing note (hardware set number in the door schedule) + door schedule and hardware sets | Since this section has no designer note on what the drawings must show, do the drawings or the project manual contain the hardware sets the strikes and switches refer to, does every detention door on the schedule have one, and does each set give the lock, cylinder, hinge, closer, stop, switch, and trim types by the type names this section uses? |
| Lock types and where each is used | Detention Locks (ligature-resistant interior trim where trim is specified) + Type 1 (solenoid jamb lock, line-voltage AC, signal switches, push button in the frame at cell doors) + Type 2 (paracentric lever tumbler deadlock) + Type 3 (low-voltage DC deadlocking latchlock “to conform to UL 10B”) + Type 4 (Mogul mortise lock, knob-operated deadbolt) + Type 5 and Type 6 (Mogul lever tumbler latch lock and deadlock) + Type 7 (Mogul spring lock for chase and access doors) + Regulatory Requirements (electrically operated locks to UL 1034) + hardware sets | Does each set name the lock type that suits the door’s role (cell, corridor, sallyport, exterior, utility, access panel), has the Type 3 lock been tied to the electric lock listing the Regulatory Requirements article names instead of a door assembly fire test, and has the specifier deleted the unused lock types and corrected the garbled bolt sizes in Types 4, 6, and 7? |
| Cylinders, keys, and keying groups | Keys and Cylinders (BHMA A156.5) + Mogul Keys (described for pin tumbler locks) + Mogul Cylinder (restricted keys, UL 437) + Builders Cylinder (used by Type 1 and Type 3 locks) + Detention Keying System (dissimilar combinations, brackets for each building and for wickets, food passes, and dormitory groups; two systems, Mogul and paracentric) + Keys (sent directly to the Contracting Officer) + Section 08 34 63 access panel locks (entered into this keying system) + keying schedule | Does a keying schedule show the exterior, corridor, utility, and cell groups the keying paragraph describes, which system do the builders cylinders in Type 1 and Type 3 locks belong to, since the section sets up only a Mogul and a paracentric system, where are the paracentric key and cylinder specified, and are the Mogul-keyed lever tumbler locks compatible with keys the section describes for pin tumbler locks? |
| Hinges, closers, stops, and frame heads | Detention Hinges (BHMA A156.1 and A156.7 types with security pins; garbled sentence on continuous conduction wiring; twist-off or spanner screws; zinc coated with prime coat on exterior doors; junction box and mortar shield; electric hinges to UL 634) + Type 1 Door Closers (surface, higher BHMA grade) + Type 2 Door Closers (concealed overhead, lower BHMA grade, installed in a deep head section) + Door Stops and Holders (PH1, PH2, OH3, FS1 to FS3) + Wall Bumpers + Section 08 34 63 frames (no head depth stated) | Where a set uses electric hinges, is the conductor count stated and the hinge wired on the electrical drawings, where a set uses the concealed closer, does the frame elevation show the head depth it needs and has the lower closer grade been accepted for that door, and do the stops and holders chosen avoid creating ligature points on the cell side? |
| Ligature resistance and trim | Detention Locks (ligature-resistant trim on the interior of all locks where trim is specified) + Door Trim (ligature-resistant pulls on the interior of all doors) + Loop Type Pulls (surface loop pulls) + Flush Type Pulls + Type 4 Lock (knob-operated deadbolt) + Deadbolts (surface head and foot bolts) + hardware sets and room data | Do the sets put flush or other ligature-resistant trim on the cell side and limit loop pulls and knob-operated deadbolts to the secure side, and has the specifier defined “interior” for each door type, since a cell door, a corridor door, and an exterior door have different secure and inmate sides? |
| Electrified hardware, monitoring, and power | Shop Drawings (bracket for power components and wiring coordination) + Regulatory Requirements (NFPA 70 for electrically controlled hardware) + Type 1 and Type 3 locks (different supply types; signal switches; plug connectors) + Type 1 Door Position Switch (mortised arm; broken face plate sentence) + Type 2 Door Position Switch (magnetic, UL 634; power rating stated in volts) + Coordination Conference and Training (a locking control system this section does not specify) + electrical and security drawings | Do the electrical drawings provide the right supply type to each electric lock, does the security system monitor every lock signal switch and door position switch the sets call for, which section specifies the locking control system and control panels that the conference and training refer to, and has the switch power rating been restated in the right unit? |
| Fire doors, egress, and listings | Regulatory Requirements (hardware on labeled fire doors listed to UL 10B; egress doors to NFPA 101; electric locks to UL 1034) + Hardware Item List (UL mark if fire rated) + Fire Doors and Exit Doors (NFPA 72 door alarms, NFPA 80 fire doors, NFPA 101 exit doors, NFPA 252; bracket for tin-clad fire doors to UL 14C) + life safety plan and code analysis | Does the life safety plan show which detention doors are rated and which are on the means of egress, does each of those sets name listed hardware, are the locking arrangements the code analysis relies on for the detention occupancy reflected in the sets and the release sequence, and has the tin-clad fire door bracket been deleted, since this section and Section 08 34 63 cover steel detention doors? |
| Thresholds, weatherstrip, fasteners, and installation | Thresholds (aluminum, panic stop, insert) + Threshold Installation (sealant bed; cadmium-plated screws; underside coated with fluid-applied waterproofing from no named section) + Drip Strip (welded to shower doors) + Weatherstrip (adhesive silicone seal) + Weatherstripping Installation (stop-applied screwed, interlocking nailed, spring tension nailed; “bronze nails with bronze”) + bracketed lightproofing and soundproofing installation (no product) + Screws and Fasteners and note (choose a tamper-resistant fastener type; spanner heads on exposed hardware) + Installation (wood screws, sheet metal screws, and toggle bolts) | Has the specifier kept one weatherstrip product and the installation that suits a steel detention door, deleted the nailed types and the wood and toggle fasteners or limited them to non-detention surfaces, chosen the tamper-resistant fastener type the note asks for, and either specified a sound seal or deleted the soundproofing bracket where the schedule shows no sound rating? |
Worked example: a housing unit with electric cell locks, two keying systems, and an unrated corridor door
Illustrative example: a detention facility addition has two cell groups, a dayroom, a sallyport, and a control room. The hardware sets give the cell doors Type 1 solenoid locks with builders cylinders, the corridor doors Type 4 Mogul mortise locks with loop pulls on both sides, the sallyport a Type 3 lock, and the chases Type 7 locks. The issued Section 08 71 63 keeps all seven lock types, both closer types, all three weatherstripping installations, the soundproofing bracket, and the tin-clad bracket. The electrical plans power the Type 3 lock with the same supply as the Type 1 locks, the life safety plan shows the corridor door on the means of egress with a fire rating that the door schedule omits, and no keying schedule exists.
Ask the hardware consultant to add a keying schedule that places the builders cylinders, the Mogul cylinders, and any paracentric cylinders in named systems and groups, to replace the loop pull on the corridor door’s inmate side with a ligature-resistant pull, and to list rated hardware for the corridor door once the architect adds its rating to the schedule. Ask the electrical and security designers to correct the Type 3 lock supply and to show monitoring for every signal and position switch. Ask the specifier to tie the Type 3 lock to the electric lock listing, to delete unused lock types, the nailed weatherstripping, the wood and toggle fasteners, the soundproofing bracket, and the tin-clad bracket, to fix the garbled bolt and switch ratings, and to name the section that specifies the locking control system.
Avoid a false conflict
Section 08 71 63 covers detention locks, cylinders and keying, hinges, closers, trim, stops, bolts, door position switches, accessories, and fasteners. Detention doors, frames, reinforcements, and access panels follow Section 08 34 63 and the detention door and frame guide, commercial hardware follows Section 08 71 00 and the door hardware guide, commercial doors and frames follow Section 08 11 13, the locking control system, control panels, and monitoring follow the electronic security and electrical sections, and the adopted building code, NFPA 101, NFPA 80, and the facility’s security criteria govern egress, fire doors, and locking arrangements, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the hardware schedule is to be submitted with samples that are never requested, builders cylinders sit outside both keying systems and the paracentric cylinder has no paragraph, Mogul keys are described for pin tumbler locks used on lever tumbler locks, the Type 3 lock cites a door assembly fire test, loop pulls and a knob deadbolt sit beside a ligature-resistance requirement, several bolt sizes, the hinge conduction sentence, and a switch rating are garbled, the weatherstrip product does not match its installation types, the installation fasteners contradict the tamper-resistant fastener requirement, the soundproofing and tin-clad brackets have no product, and the conference and training name a locking control system the section does not specify. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.
Where Groundbook fits
Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.