Guide · Structural documents

Hanger and connector schedule checklist

Metal connectors, such as joist and girder hangers, rafter ties, hold-downs and straps, are where a wood structure’s load path is most often left undefined. Supplier drawings leave them “by others”, framing plans offer a list of options, and the framer ends up choosing.

Check a connector schedule by listing every condition that needs a connector, from each hung truss, joist and beam end to each uplift bearing, shear wall end and floor-to-floor strap, and confirming that one model or required capacity is named for each across every sheet. Then check the anchors cast in the foundation, the fasteners, the coating for treated or exposed wood, the specification, substitutions and inspection.

Connections left to others

Truss and joist suppliers design their members and print the reactions, but they usually leave hangers, ties and bracing to the building designer. If no sheet specifies them, they are left to the framer. In the house floor truss submittal load path review, the truss drawings required hangers “by others” at several trusses and a two-ply girder hung from another girder, plus an uplift tie at one girder bearing. Neither the truss layout nor the engineer’s sheets specified them.

The two-story house roof load and shear wall review of the same house found the opposite problem: the rafter-to-plate tie named as three different models across three sheets, with no uplift value that would settle which governs.

Twelve questions for hangers and connectors

Work through the framing plans level by level, then the foundation plan. The CSV has columns for the location, the source references, the reviewer, the status, the decision and the closure evidence. It contains no capacities; those come from the engineer of record, the supplier’s reactions and the manufacturer’s published data.

Hanger and connector schedule checklistSwipe or scroll sideways to read all columns.
Review areaOpen these sources togetherQuestion to resolve
Connections left to othersTruss and joist design drawings, layouts, structural notesWhere the supplier drawings leave hangers, ties or bracing “by others”, does any drawing or schedule specify them?
One connector per conditionFraming plans, typical details, connector schedule, general notesIs one model, or one required capacity, named for each condition across every sheet, without unexplained option lists?
Hangers at girder and beam endsHanger schedule, framing plans, girder reactionsDoes each hung truss, joist, girder or beam end have a hanger named for its member size, plies and reaction?
Uplift ties at every bearingTruss reactions, roof framing plan, connector schedule, wind dataDoes each rafter or truss bearing have one named tie for the uplift the truss drawings or calculations give?
Hold-downs at both wall endsShear wall plans, hold-down schedule, foundation planDoes each shear wall, or each sheathed segment, have hold-downs at both ends where the design requires them?
Anchors cast before the pourHold-down details, foundation plan, anchor bolt notesIs each hold-down anchor given a rod size, embedment, edge distance and location on the foundation plan?
Straps between floorsFloor-to-floor strap details, shear wall plans, sectionsAre floor-to-floor straps and their nailing shown where upper wall forces continue to the floor below?
Fasteners namedConnector schedule, general notes, manufacturer requirements citedDoes the schedule give the fastener type and quantity each connector needs, or point to where the manufacturer’s requirements are listed?
Coating and treated woodConnector schedule, specifications, preservative-treated lumber notes, exposureDo the notes state the connector coating or material for preservative-treated lumber and exposed or coastal locations?
Connectors in the specificationSpecification sections for rough carpentry, trusses and connectors, drawingsDoes the specification’s list of framing anchors and connectors agree with the models and coatings on the drawings?
SubstitutionsGeneral notes, specifications, submittal requirementsDo the notes say whether equivalent connectors may be substituted and who approves them?
Inspection of connectionsInspection notes, special inspection statement, specificationsDo the documents say which connections are inspected, and before which work they must be visible?

Mark a row not applicable only after recording why. A building with no hung members still has uplift ties and anchors to check.

Hold-downs start in the foundation

Hold-downs are the connectors with the earliest deadline, because their anchors are cast before the pour. Check that each shear wall end the design requires has a hold-down, and that its anchor rod size, embedment and location are on the foundation plan. The same review found interior shear walls with a hold-down at only the end that met an exterior wall, and a hold-down detail with no anchor rod or embedment. The wood shear wall drawing checklist follows those walls in full.

Match the drawings to the specification

Connector models, coatings and substitution rules often appear in the rough carpentry or truss specification as well as on the drawings. Read them together, and check that connectors in preservative-treated or exposed wood have a coating or material the documents state. The rough carpentry specifications versus drawings guide covers the framing anchors paragraph, and the engineered wood beam checklist covers the beams the hangers support.

Where Groundbook fits

Groundbook compares the framing plans, connector schedules, truss and joist design drawings, foundation plans, specifications and calculations you upload, and returns potential conflicts with links to each source, such as a hanger the truss drawings leave to others that no sheet specifies. It does not select connectors, check capacities or approve substitutions. Each finding is a question for the engineer of record. See cross-discipline coordination review for the workflow, and the structural load path checklist for the members the connectors join.

Questions, answered

FAQs

Who specifies joist hangers when the truss drawings say “by others”?

Usually the engineer of record or the building designer. The drawings should name each hanger, or state a required capacity and who selects the product.

What should a connector schedule include?

Each condition, the connector model or required capacity, the fasteners, the coating or material, and where it occurs on the plans.

Can the framer substitute a different hanger?

Only as the documents allow. Check the notes and specification for the substitution rule and who must approve an equivalent product.

Why do hold-down anchors need to be on the foundation plan?

Because they are cast into the concrete before the walls are framed. An anchor missing from the foundation plan is often missed at the pour.

Keep exploring

Continue your review

Structural drawing review checklist

Review structural notes, framing plans, schedules, details, and support interfaces with a practical checklist, worked example, and free editable CSV.

Explore

Structural load path drawing checklist

Follow every load from the roof to the footings across the drawings: girder reactions, posts, transfer walls, hold-downs and supplier members. Free CSV.

Explore

Engineered wood beam drawing checklist

Check LVL, PSL and glulam beams across the framing plans, supplier layouts and details: sizes, plies, bearing, posts, hangers and exposure. Free CSV.

Explore

Wood truss drawing review checklist

Check wood truss layouts and truss design drawings against the architectural and structural sheets: loads, bearings, headers, uplift and bracing. Free CSV.

Explore

Wood shear wall drawing checklist

Check wood shear wall drawings from plan to anchor: walls on the architectural plans, openings, foundations, hold-downs, nailing and connectors. Free CSV.

Explore

Check rough carpentry specifications against framing plans, shear wall schedules, and roof nailer details

Compare lumber grades, glulam, sheathing and shear wall panels, treatment, anchors and nailing, bracing, and roof nailers with UFGS 06 10 00.

Explore

House floor truss submittal load path

A review of a two-story house’s floor truss package against its structural design finds girder loads, beams and hangers that no engineer’s sheet carries.

Explore

Cross-discipline coordination

Find potential conflicts across architectural, structural, and MEP drawings. Review levels, openings, equipment, and references with linked document evidence.

Explore

Bring your next set into focus

Set up a review or talk through your project with our team.

Find every hanger, tie and hold-down left to others

Trusted by hundreds of professionals