We’re at NCSEA in San Francisco, Oct 28–29 · Booth 110NCSEA · Booth 110 · Oct 28–29

Guide · Specifications and drawings · 26 20 00

Check interior electrical distribution specifications against drawings

Section 26 20 00 is the catch-all for building wiring: panelboards, conductors, raceways, motor controllers, and grounding. Because so much of it says “as indicated,” most of its review questions are really about whether the panel schedules, one-line, and riser say the same thing.

Trace each panelboard from the riser and one-line to its schedule, then compare the source named on each, the breaker positions the schedule shows, the conductor material and raceway types drawn, and the grounding shown in each electrical room. The section requires breakers to be placed as the panelboard schedule shows, so the schedules are part of what the contractor builds, not just a load summary.

Assemble the review package

Gather the electrical one-line and riser diagram, every panelboard schedule, the power and lighting plans, the grounding plan or riser, the electrical room plans, the fire pump and controller drawings, the emergency and standby panel schedules, the mechanical equipment schedules that list motors, and the issued Section 26 20 00 with its edits. Review one panel from its source breaker to its last branch circuit before assuming other panels are drawn the same way.

WBDG publishes UFGS 26 20 00: Interior Distribution System as a public guide-specification reference (accessed October 18, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
Panel names and sourcesRiser diagram + one-line + Panelboards articleDoes every panel on the riser appear on the one-line and on a schedule with the same name and the same upstream source, so the directory the section requires can name where it is fed from?
Breaker placement and spacesPanelboards article + panelboard schedulesDo the schedules show each breaker’s position, its poles, and any “space only” positions, since the section asks for breakers to be placed as scheduled?
Feeder and branch conductorsWires and Cables and Aluminum Conductors articles + feeder scheduleIs conductor material and size stated for each feeder, and if the issued section keeps the aluminum option, do conduit and pull box sizes leave room for the substitution it allows?
Raceways and wiring methodsWiring Methods and Conduit Installation articles + plans and detailsWhere the drawings call for cable, cable tray, or a particular raceway, is it a method the section permits in that location, including the restrictions on EMT and nonmetallic conduit in equipment and fire pump rooms?
Grounding and bondingGrounding and Bonding and Ground Bus articles + grounding planIs the ground bus in each electrical room drawn where the section says “as indicated,” and where lightning protection exists, is the interconnection of grounding systems shown?
Fire pump circuitsMotors and Motor Controllers articles + fire pump drawingsWhere the section defers the fire pump motor and controller to Section 21 30 00, do the electrical drawings show the fire pump feeder and controller consistently with that section?
Emergency source for control circuitsControl Circuits article + one-line + emergency panel schedulesWhere the section retains backup control power from the emergency source for designated systems, are those systems identified and is the emergency circuit on a schedule?
Protection, surge, and studiesCoordinated Power System Protection and Surge Protective Devices articles + one-lineDoes the one-line show where surge protective devices go, and if the coordinated protection article is retained, is Section 26 05 73 in the project manual?

Worked example: a panel fed from two different places

Illustrative example: the riser diagram shows lighting panel LP-2 fed from distribution panel DP-1, while the LP-2 schedule header says “Fed from MDP” and the MDP schedule lists a breaker labeled LP-2. The issued Section 26 20 00 requires each panel directory to name its source and requires breakers to be placed as the schedules show.

Ask the electrical engineer which source is intended, then correct the riser, the LP-2 header, and the schedule of the panel that should not carry the breaker. Recheck the feeder size and the load totals on both upstream panels, since one of them is now carrying a load it should not.

Avoid a false conflict

A complete-looking panel schedule does not prove the panel is fed the way the riser shows. Schedule headers are often copied between panels, so check the source on every schedule against the one-line, not only the circuits.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should an interior distribution specification review compare?

Compare panel names and sources, breaker placement and spaces, feeder and branch conductors, raceways and wiring methods, grounding and bonding, fire pump circuits, emergency control power, and surge protection and study requirements.

Does UFGS 26 20 00 require breakers to match the panelboard schedule?

The current UFGS 26 20 00 on WBDG requires specific breaker placement to match the panelboard schedule on the design drawings, with Government approval needed before a different placement is installed. Your project’s issued specification governs, so confirm what it says after editing.

Does this checklist confirm the distribution design meets NFPA 70?

No. It checks that the drawings and the specification describe the same installation. Load calculations, conductor and overcurrent sizing, code compliance, and approval stay with the electrical engineer of record and the authority having jurisdiction.

Bring your next set into focus

Set up a review or talk through your project with our team.

Check your distribution drawings against Section 26 20 00

Trusted by hundreds of professionals