Start with the drawing note of the issued Section 07 19 00: confirm that the exterior elevations show where each type of water repellent goes and designate it by a code that matches a kept product paragraph. Then check that the substrates on the wall types are the above-grade concrete, concrete masonry, or plaster the section covers, that the Surfaces to Be Coated paragraph has been edited so it does not override the drawn locations, that the test panel is specified once in the right section, and that the sealant schedule and the repellent agree on which goes first.
Assemble the review package
Gather the exterior elevations with water repellent codes, the wall types and wall sections showing the substrate, cavity, and interior finish, the parapet, coping, sill, and window and door jamb details, the sealant schedule and joint details, the landscape plan near treated walls, the concrete, masonry, and plaster sections with their cure and cleaning requirements, any durability or chloride criteria for a marine or deicing exposure, and the issued Section 07 19 00 with Sections 07 92 00, 04 20 00, 01 33 00, and 01 57 19. Follow one wall from its elevation code to the wall type, the sealant joints in it, and the test panel before assuming the others match.
WBDG publishes UFGS 07 19 00: Water Repellents as a public guide-specification reference (accessed November 16, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| What the drawings must show | Drawing note (show the location of each type of water repellent; designate by code) + delete note (delete types not required) + Surfaces to Be Coated (all exterior surfaces of the bracketed substrates, including parapet backs, wall tops, and returns at frames) + Covered Surfaces (the same list plus window sills) + exterior elevations and wall types | Does every code on the elevations match one kept product paragraph, have the specifier deleted the unused types, and has the blanket coat-all-exterior-surfaces language in both Surfaces to Be Coated and Covered Surfaces been edited to point at the drawn locations, so the two lists and the elevations agree, including at sills, wall tops, and the backs of parapets? |
| Substrates the section covers | Opening note (above-grade concrete, concrete masonry, and plaster) + bracketed substrates in Qualifications, the test panel, Surfaces to Be Coated, Examination, and Spray Application (concrete, concrete masonry or masonry, plaster) + acrylic note (concrete, exposed aggregate, stucco, masonry, or stone) + Examination (mortar joints tight and sound) + wall types and finish legend | Are all treated walls above grade, with below-grade walls sent to the dampproofing or waterproofing section, do the brackets say concrete masonry or masonry consistently, and if the elevations call for treating clay brick, stone, or stucco, has the specifier confirmed a product and test basis for that substrate, since the acrylic note names substrates the scope note does not? |
| Product type, appearance, and exposure | Materials (clear, non-yellowing, deep-penetrating, non-staining, interlocking bond) + opening note (penetrant-type repellents; no graffiti resistance or gloss) + Silane, 20, 40, and 85 Percent Solids + Siloxanes + Low-Solids and High-Solids Acrylic (breathing coatings; note accepts wet sheen or darkening) + VOC-Complying Water Repellents (a certification listed as a type) + Environmental Protection (local air district or CARB bracket) + exposure criteria | Does the elevation code point to a penetrating silane or siloxane or to an acrylic coating, and if an acrylic is kept, has the Materials paragraph been edited so it does not forbid the sheen and darkening the acrylic note accepts, does any wall need graffiti resistance that these products do not give, and does the VOC limit for the project’s air district allow the chosen solids level? |
| Test standards and performance criteria | Performance Requirements (absorption by ASTM C140/C140M; vapor transmission by ASTM E96/E96M; ASTM E514/E514M; AASHTO T 259 and T 260; ASTM G154) + Silane criteria (absorption by ASTM C642 and E514/E514M; vapor transmission by ASTM D1653; absorption values reported under E514/E514M) + Siloxane criteria (ASTM E96/E96M) + no criteria for the acrylic types + chloride tests without an acceptance value + SD-06 Test Reports | Has the specifier chosen one absorption method and one vapor transmission method per substrate and aligned Performance Requirements with the criteria paragraphs, has a criterion been written for any kept acrylic type, and where chloride resistance matters for a marine or deicing exposure, does the section state what result the test reports must show? |
| Units and printed values | Silane, 20 Percent Solids (inch-pound density range garbled and not matching the metric range) + all three silane paragraphs (specific gravity temperature in metric and inch-pound that does not convert) + Siloxanes (density and flash point) + product data submittals | Has the specifier corrected the 20 percent silane density so the metric and inch-pound ranges agree, and fixed the specific gravity reference temperature, so a reviewer comparing the product data can tell which value governs? |
| Test panel and field hose test | Sample Test Panel (standard of quality; Contracting Officer approval) and note (specify panels in Division 03, 04, or 09) + Preparation of Sample Test Panel (bracketed substrate; blank for the section; full-height expansion joint sealed with project materials) + Testing (treat the left side, then the right side; hose test “similar to AAMA 501.2”, titled for storefronts, curtain walls, and sloped glazing) + Field Testing (“Navy Hose Stream Field Test” not defined; recoat the entire building if moisture shows inside) + wall types | Is the panel specified in one section only, with the blank filled, does the panel procedure keep an untreated area to compare against, and for a wall with a drained cavity or an interior finish, has the specifier defined what “inside of the wall” means for the field test, and is recoating the whole building the intended remedy when a leak may come from a crack, joint, or flashing that a repellent cannot fix? |
| Cure, moisture, weather, and sequencing | Weather and Substrate Conditions (no application on substrates cured less than a stated period; temperature, rain, and drying limits) + Moisture Condition (per the manufacturer) + Examination (a fixed wall moisture content limit; cracks repaired; form release and curing compounds removed) + Masonry, Plaster, and Concrete Surfaces (cure periods by substrate; masonry differs from the general condition) + Inspections (manufacturer’s representative approval) + concrete, masonry, and plaster sections | Has the specifier reconciled the cure period in the weather paragraph with the longer masonry period, chosen whether the manufacturer’s moisture limit or the Examination value governs, and checked that the concrete section’s curing compound will not block penetration on walls scheduled for repellent? |
| Sealants, glazing, landscaping, and warranty | Sealants (repellent after sealants are installed and cured, unless adhesion and compatibility are tested) + Compatibility (confirm with each joint sealer; bracketed sealant-first or masking options) + Protection (glass, glazed and prefinished products, landscape materials) + Cleaning + Warranty (joint manufacturer and applicator; moisture penetration through structurally sound surfaces) + sealant schedule and Section 07 92 00 | Do the sealant schedule and Section 07 92 00 state the same order of work as the kept paragraphs, has a compatibility test been required if the repellent goes first, do the elevations and landscape plan show the glass, prefinished metal, and plantings that need protection, and does the warranty term suit the owner’s expectations for the wall type? |
Worked example: a split-face masonry barracks with plaster accents and an acrylic code
Illustrative example: a barracks has split-face concrete masonry walls, plaster accent bands, and a clay brick base course. The elevations tag the masonry WR-1 and the plaster WR-2 and leave the brick untagged. The issued Section 07 19 00 keeps the 40 percent silane and the high-solids acrylic, keeps Surfaces to Be Coated unedited with every bracket, leaves the test panel blank, and keeps both sealant brackets. The sealant schedule puts sealant after the coatings, the masonry section uses a shorter cure than the repellent masonry paragraph, and the wall type shows a drained cavity behind the block.
Ask the architect to decide whether the brick base is treated and to tag it, and to confirm the drawn locations govern. Ask the specifier to edit Surfaces to Be Coated and Covered Surfaces to match the elevations, to fill the test panel blank or move the panel to the masonry section, to keep one sealant bracket that matches the sealant schedule, to edit Materials for the acrylic, to reconcile the cure periods, and to define the field test result for a cavity wall.
Avoid a false conflict
Section 07 19 00 covers clear repellent treatments on above-grade concrete, concrete masonry, and plaster. Masonry construction follows Section 04 20 00 and the masonry guide, stucco follows Section 09 24 23 and the stucco guide, sealants follow Section 07 92 00 and the joint sealant guide, below-grade protection follows the dampproofing and waterproofing sections and guides, and paints and elastomeric coatings follow the painting section, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the Materials paragraph rules out the sheen the acrylic types produce, the acrylic types have no criteria, the test methods in Performance Requirements differ from those in the criteria paragraphs, one density range and the specific gravity temperatures do not convert, the masonry cure periods disagree, the coat-all-surfaces paragraphs override the drawing note, the panel is placed both here and in other divisions, and the field test is not defined. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.