Start with the Summary and Environmental Requirements notes of the issued Section 09 64 29: wood flooring moves with humidity, so confirm that the mechanical drawings show how the gymnasium or court will be kept within the humidity the floor needs, and that the slab drawings show a depression deep enough for the chosen sleeper or channel system. Then check that one species, grade, and thickness are kept, that the vapor barrier, sleepers or channels, expansion space, wall base, and court wall construction are drawn, and that the finish and game lines are specified somewhere.
Assemble the review package
Gather the floor finish plans and finish schedule, the gymnasium and court floor plans with game lines, the structural slab plans and sections with slab depressions and joints, the floor system and wall base details, the handball and squash court wall sections, the mechanical drawings and sequences for heating, cooling, ventilation, humidification, and dehumidification in those rooms, any termite treatment notes for the site, and the issued Section 09 64 29 with Sections 06 10 00, 09 90 00, 09 06 00, 03 30 00, and 01 33 00, and Section 09 64 66 if the project also uses it. Follow one floor from the slab depression up through the vapor barrier, sleepers or channels, pads, and flooring to the finish before assuming the others match.
WBDG publishes UFGS 09 64 29: Wood Strip and Plank Flooring as a public guide-specification reference (accessed November 17, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| Which section, and what the drawings must show | Opening note (gymnasiums, handball and squash courts, other special purpose applications) + Summary (allows competitive, manufacturer-standard integrated systems) + title “Strip and Plank” while Part 2 is headed Strip Flooring with one strip face width and only bamboo as plank + SD-02 Strip Flooring with a “G” and no paragraph defining that drawing + UFGS 09 64 66 Wood Athletic Flooring (also Active) + finish plans and floor details | Has the project chosen this section or Section 09 64 66 for the gymnasium, does the finish plan key each wood floor to one system, does the section say what the flooring shop drawing must show, such as layout, direction, expansion space, and system section, and if plank flooring is intended, has the specifier added plank widths the section does not give? |
| Species, grade, thickness, and options | Strip Flooring note (gymnasiums limited to hard maple; thicker flooring for hard service and frequent sanding) + General Requirements (thickness bracket; kiln dried, tongue and groove; beech and birch and oak by NOFMA Grading Rules and hard maple by MFMA GS, both dated 1999; grading agency mark; no added urea-formaldehyde) + certified wood, recycled content, termite, and indoor air quality brackets and notes + Bamboo bracket + SD-04 samples | Has the specifier deleted the beech, birch, and oak grades for a gymnasium, chosen one thickness that suits the sanding life the owner expects, kept the termite bracket where the site is termite-prone and confirmed its effect on the finish, deleted Bamboo unless the plans show it, and checked the grading rule editions against what suppliers grade to today? |
| Humidity, ventilation, and the HVAC drawings | Summary note (ventilated at all times for the life of the floor; humidify in long dry heating periods and dry the space when humidity rises; localized HVAC or continuous monitoring at problem sites; floating or sleeper systems as alternatives) + Environmental Requirements and note (permanent HVAC working before installation; temperature range; humidity bracket or manufacturer’s value, held through the contract; local values may be substituted) + Delivery, Storage, and Handling (moisture content; storage matching the rooms) + Scheduling + mechanical drawings | Do the mechanical drawings and sequences show how the gymnasium or court is ventilated, humidified, and dehumidified to the humidity the section and the flooring manufacturer need, has the humidity bracket been filled with a value the HVAC can hold, and does the construction schedule have permanent HVAC running before the flooring is delivered and laid? |
| Slab depression, flatness, and vapor control | Surface Conditions (level, steel troweled slab within a flatness tolerance; clean, dry, and approved; “depressed as required by the floor specified”) + Moisture Barrier (polyethylene; no Part 3 paragraph places it under any floor) + Wood Sleepers (slab vapor-sealed with a two-ply membrane and hot-poured steep-slope asphalt, with no product paragraph or standard) + Asphalt Primer (ASTM D41/D41M) and Asphalt Mastic (never used in Part 3) + structural slab sections and Section 03 30 00 | Do the structural drawings show a slab depression whose depth matches the total height of the chosen system, is the slab finish and flatness in Section 03 30 00 consistent with this section, and has the specifier said which vapor control each floor system gets, where the polyethylene barrier goes, and what membrane and asphalt the sleeper floor uses, or deleted the primer and mastic paragraphs that nothing uses? |
| Sleepers or steel channels | Gymnasium Floors: Wood Sleepers (anchored, treated sleepers at one spacing with a subfloor or a closer spacing without one and thicker flooring; spaces left vacant; expansion joint maximum) + Steel Channels (galvanized channel on grooved foam or resilient board; expansion by the manufacturer) + Clips, Anchor Channels and Insulation and note (channel system as an option to wood nailers) + Resilient Pads + Installation (wood nailers in Section 06 10 00) + floor system details | Has the specifier chosen sleepers, channels, or a manufacturer system and deleted the others, does the floor section detail match that choice in spacing, subfloor, pads, and insulation, does the subfloor option agree with the flooring thickness kept, and do Section 06 10 00 and this section together give a preservative treatment for the sleepers, which this section calls treated without naming a standard? |
| Laying direction, expansion space, and wall base | Installation (manufacturer’s approved instructions; laid parallel to the length of the area unless approved; close or intermediate expansion bracket; end joint staggering; expansion space at walls and fixed projections by a rule tied to room width with a minimum at each wall) + Wood Sleepers (expansion joint maximum) + Wall Base (wood molding or vented cove; premolded outside and mitered inside corners) + floor plans, base details, and thresholds | Do the floor plan and details show the laying direction, the perimeter expansion space, and how it is covered at walls, doors, bleachers, and floor inserts, has the specifier said which governs on a gymnasium-size floor where the perimeter rule in Installation gives more space than the maximum in Wood Sleepers, and does the base schedule show the vented base the section specifies? |
| Handball and squash courts | Handball Court Floor and Walls (boards laid for a light, even appearance) + Squash and Handball Court Walls (maximum wall expansion space; larger joints and steel channel joints detailed and submitted for approval; SD-02 “G”) + Wood Supports (anchored supports holding treated sleepers off the wall for ventilation; exterior plywood backed with aluminum enamel per Section 06 10 00) + Steel Supports (channel spacing; hot-poured asphalt fill behind the wall, or a polyethylene vapor seal and insulation when thicker flooring is used) + court wall sections | Do the court wall sections show wood or steel supports matching the kept paragraph, the ventilation space, plywood backing, or asphalt fill, does any paragraph cover the squash court floor, which only the walls heading names, and has the specifier confirmed that the court construction suits the playing standard the owner wants, since the section states no ball rebound or play criteria? |
| Sanding, finish, game lines, and protection | Sanding (multiple cuts with finer paper; drum and disc sanders; a diagonal pass; first seal coat within a set time per Section 09 90 00, cited as “Paints and Coatings”) + no paragraph for the finish system, game lines, or court markings + Protection (from installation to acceptance) + indoor air quality certifications + gymnasium game line plan and finish schedule | Does Section 09 90 00, cited by its current title Architectural Paints and Coatings, include a wood floor seal, finish, and game line paint suited to a gymnasium, do the game line plans give the courts, colors, and line widths that section will paint, and does the schedule allow the first seal coat to follow sanding within the time the section sets? |
Worked example: a fitness center with a maple gymnasium and two handball courts
Illustrative example: a fitness center has a maple gymnasium on a sleeper system and two handball courts with wood floors and walls. The issued Section 09 64 29 keeps all species and grades, both thickness options, the Bamboo paragraph, the moisture barrier, asphalt primer, and asphalt mastic, and both the wood sleeper and steel channel paragraphs. The structural slab plan shows a slab depression that is shallower than the sleeper system detail, the mechanical drawings serve the gymnasium with heating and ventilation only, the court wall sections show steel channels while the floors use sleepers, and the game line plan exists with no finish or paint paragraph covering it.
Ask the structural engineer and architect to reconcile the slab depression with the sleeper system height. Ask the mechanical engineer how the gymnasium humidity will be held within the range the section and the flooring manufacturer require. Ask the specifier to keep hard maple only, one thickness, and the sleeper paragraph for the floors, to delete Bamboo and the unused primer and mastic or place them in Part 3, to state which vapor control goes under the sleepers, and to confirm that Section 09 90 00 covers the gym finish and game lines.
Avoid a false conflict
Section 09 64 29 covers wood strip and plank floors and court walls. Wood athletic flooring may instead follow Section 09 64 66, nailers and sleepers draw on Section 06 10 00 and the rough carpentry guide, the floor finish and game lines follow Section 09 90 00 and the painting guide, the slab follows Section 03 30 00 and the concrete guide, resilient athletic floors follow Section 09 65 66, and the mechanical design governs humidity control, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the title promises plank flooring that Part 2 does not size, the moisture barrier, asphalt primer, and asphalt mastic are specified but never installed, the sleeper vapor seal names a membrane and asphalt with no product paragraph, the flooring shop drawing is required but undefined, and the painting section is cited by an old title. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.