Guide · Specifications and drawings · 09 67 23.14

Check chemical resistant resinous flooring specifications against finish plans, room chemical lists, drain details, and slab drawings

UFGS Section 09 67 23.14 Chemical Resistant Resinous Flooring, a USACE-prepared guide specification issued in August 2016 and last changed in August 2018, covers trowelled or spray-applied industrial, conductive, and decorative resinous floor surfacings, excluding resinous terrazzo, for biological laboratories, areas with hard wear or chemical spills that must stay clean, and explosive and ammunition facilities. It offers three binders, a latex or resin emulsion, an epoxy, and a polyester, each with its own property paragraphs and chemical resistance list, plus primer, aggregate, fillers, top coat, conductive sparkproof flooring, sealer, and an antimicrobial option. Part 3 covers surface preparation for new and contaminated concrete, plywood, and ceramic tile, crack and joint filling, application, resistance and spark tests for conductive floors, and protection.

Start with the opening notes of the issued Section 09 67 23.14: the binder must be chosen for the chemicals and temperatures each room will see, and the drawings must key each floor type to its location and detail cove bases, joints, stairs, floor drains, and grounding, so confirm that a room-by-room chemical list exists and that the kept binder suits it. Then check that the section actually specifies the coves, drains, and slopes the drawings show, that the substrate, moisture test, and joints are settled, and that conductive floors have grounding details and a current test reference.

Assemble the review package

Gather the floor finish plans and finish schedule with resinous floor types, colors, and base types, the room data sheets or the list of chemicals, cleaning agents, and temperatures for each room, the structural slab plans and general notes with the concrete type, finish, curing method, vapor retarder, and slab joints, the plumbing plans with floor drains, trench drains, and floor slopes, the wall base, curb, stair, and threshold details, the electrical drawings for rooms with conductive floors, the explosives safety site plan or hazard analysis for those rooms, and the issued Section 09 67 23.14 with Sections 03 30 00, 09 06 00, 07 92 00, 01 33 00, and 01 78 23. Follow one room from its chemical exposure to its binder, substrate, thickness, base, drain, and test before assuming the others match.

WBDG publishes UFGS 09 67 23.14: Chemical Resistant Resinous Flooring as a public guide-specification reference (accessed November 17, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
What the drawings must showPart 1 drawing note (location of resinous flooring, keyed by type where more than one is used; details of coved bases, expansion joints, control joints, stairs, and floor drains; details for grounding of conductive floors) + Shop Drawings (type and layout of the flooring system; SD-02 with a “G”) + Color (as indicated or by Section 09 06 00) + no Part 2 or Part 3 paragraph for cove bases, stair treatment, or drain terminations + finish plans and base scheduleDoes the finish plan key every resinous floor area to one type, do the base, stair, and drain details show how the surfacing turns up, terminates, and laps into each drain or trench, and has the specifier added cove base, nosing, and drain termination requirements, since the section asks for those details but never specifies them?
Binder choice against each room’s chemicalsPart 1 selection note (choose by required exposure; polyester not where strong alkalis spill; epoxy not where oxidizing acids or high temperatures occur) + Binder note (latex or emulsion not for solvents, strong acids or alkalis, high stain resistance, or decorative quartz; epoxy not for steam, boiling liquids, light-colored quartz, or substrates that cannot be dried; polyester not for strong alkalis, maximum slip resistance, or occupied buildings) + Binder bracket + matrix notes (add the project’s chemicals and concentrations to the lists; lettered item references that no longer match) + room chemical listsHas the specifier kept one binder or keyed each binder to rooms, does any room handle the alkalis, oxidizing acids, solvents, steam, or hot spills the notes warn about, and have the laboratory, plating, or process chemicals and concentrations for those rooms been added to the chemical resistance list, which as written covers only household reagents and cleaners?
Property paragraphs and test methodsMaterials (single manufacturer; an epoxy finish to the NTMA Info Guide, a terrazzo reference, or ASTM C722 Type A or Type B surfacings; thickness brackets) + Latex, Epoxy, and Polyester Matrix property paragraphs (ASTM C579, C307, C580, C531, C413, E162, D4060, D1308) + polyester porosity, impact, fungistatic, ultraviolet, thermal shock, stain, and adhesion paragraphs all citing ASTM D4060 + smoke paragraphs in milligrams and grams + thermal coefficient, polyester tensile, and thinnest thickness brackets whose metric and inch-pound values do not correspond + unnumbered latex Chemical Resistance headingHas the specifier deleted the property paragraphs of the binders not chosen, replaced the D4060 citations on the polyester properties with methods that actually measure porosity, impact, ultraviolet, thermal shock, stain, and adhesion, made the smoke, thermal coefficient, tensile, and thickness values agree in both unit systems, and decided whether the NTMA bracket belongs in a section that excludes terrazzo?
Substrate type and the concrete it needsPart 1 notes (normal-weight concrete only, not lightweight; check other sections for no vermiculite or perlite aggregate, no curing compounds or sealers, a single trowelled finish with no burnishing, a vapor barrier under slabs on grade, exterior plywood with ring or spiral nails, hardware cloth over existing lumber) + Surface Preparation note (not over existing resilient flooring; a new topping where concrete is badly cracked or contaminated) + Plywood and Ceramic Tile paragraphs + structural general notes, slab sections, and Section 03 30 00Is every resinous floor on a normal-weight slab, do the structural notes and Section 03 30 00 omit curing compounds and burnished finishes and show a vapor retarder under each slab on grade in those rooms, are plywood or tile substrates kept only where the drawings show them despite the note’s concrete-only scope, and is a new topping shown where the existing slab survey found damaged concrete?
Surface preparation and moisture testingConcrete Surfaces note and table (preparation by surface condition: new concrete, acid, oil and fat, alkali, paint, adhesive and asphalt, dust, form oil and curing compound) + bracketed Mechanical Cleaning, Steam Cleaning, Paint Stripping, Acid Etching, and Air Drying paragraphs + Environmental Requirements (concrete cure and dry periods; ASTM D4263) + Air Drying (its own mat or sheet test and duration) + existing conditions surveyDoes the kept preparation match the condition of each existing slab in the survey or demolition drawings, is one moisture test named, with Environmental Requirements and Air Drying agreeing on the method, does a test survive if the Air Drying bracket is deleted, and does the schedule allow the cure and dry periods before surfacing on new slabs?
Joints, drains, slopes, and thicknessSubstrate Cracks, Spalls, Joints, and Depressions (fill all joints with latex underlayment) + Floor Surfacing note (thickness by traffic for each binder; continuous placement only if structural control joints are outside the floor area) + Floor Surfacing (thickness blank; continuous or with divider strips at control joints; all surfaces level within a tolerance) + Part 1 drawing note (expansion and control joints, floor drains) + slab joint plan, plumbing floor drain and slope plans, Section 07 92 00Do the slab joint plan and the kept placement bracket agree, so that control and expansion joints are carried through the surfacing with strips or sealant rather than filled with underlayment, has the thickness blank been filled to suit the traffic and the binder, and where the plumbing plans slope floors to drains or trenches, does the section allow that slope rather than requiring every surface to be level?
Conductive sparkproof floors and groundingConductive Sparkproof Flooring note (operations with electrostatically sensitive explosives, loose ammunition with electric primers, exposed electro-explosive devices, electrically initiated items, static-ignitable materials) + Conductive Sparkproof Flooring (thickness and ASTM C722 type brackets; ground and conform to NFPA 99) + Top Coating note (conductive clear top coat only) + Testing note + Electrical Resistance (a test window; limits by service voltage; NFPA 99 cited by a hyphenated paragraph number in an older style while References list the 2024 edition) + Spark Resistance + SD-06 + electrical drawingsAre conductive floors kept only in the rooms the explosives hazard analysis identifies and marked on the finish plan, do the electrical drawings detail the floor grounding and show each room’s service voltage, has the specifier confirmed the resistance test reference against the NFPA 99 edition listed and the project’s explosives safety criteria, and is the top coat in those rooms conductive?
Primer, top coat, installer, samples, and protectionPrimer (manufacturer’s; CDPH Section 01350 or SCAQMD Rule 1113) + Aggregate note and bracket (industrial or colored quartz decorative) + Top Coating note and bracket (clear for decorative; colors for industrial) + Sealer and Resin (nonslip, stain resistant) + Antimicrobial note + Qualifications of Installer (approved by the manufacturer; SD-07 “G”) + Flooring Systems samples and Data Package 1 (Section 01 78 23) + Mixing and Application (OSHA 29 CFR 1910 Subpart Z) + Protection (set time before traffic; cover until acceptance)Does the aggregate and top coat choice match the industrial or decorative finish on the schedule, is the antimicrobial bracket kept only for rooms that need it, do the slip resistance criteria for wet rooms agree with the sealer, and does the project schedule allow the set and protection period before other trades and equipment move in?

Worked example: a laboratory with a wash-down room, a trench drain, and an explosives bay

Illustrative example: a research building schedules epoxy resinous flooring in a biological laboratory, a wash-down room with a trench drain, and a small explosives handling bay. The issued Section 09 67 23.14 keeps all three binders, the full chemical resistance lists as printed, the continuous-placement bracket, and the Testing paragraphs. The room data sheet for the wash-down room lists a hot caustic cleaner, the structural slab plan shows sawcut control joints through the laboratory, the plumbing plan slopes the wash-down floor to the trench, the base schedule shows an integral cove in all three rooms with no detail, and the finish plan does not say which floor is conductive.

Ask the architect to key the conductive floor to the explosives bay, to detail the integral cove and the surfacing lap into the trench drain, and to confirm whether an epoxy suits the wash-down room’s hot caustic cleaning, as the binder note warns. Ask the specifier to delete the binders not used, to add the room’s cleaners and process chemicals to the resistance list, to choose the divider strip bracket so the laboratory control joints are carried through, to allow the sloped wash-down floor, and to correct the polyester test methods if polyester stays. Ask the electrical engineer to detail the bay grounding and confirm the test reference.

Avoid a false conflict

Section 09 67 23.14 covers resinous floor surfacings that are not terrazzo. Resinous terrazzo follows Section 09 66 23 and its guide, standard resinous flooring and fuel-resistive systems follow Sections 09 67 23.13 and 09 67 23.15, coatings on tanks and equipment follow Section 09 96 00 and the heat- and chemical-resistant coating guide, the slab follows Section 03 30 00 and the concrete guide, sealants follow Section 07 92 00, drains follow the plumbing section, and DoD explosives safety criteria, NFPA 99, and the electrical design govern conductive floors and grounding, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: no paragraph specifies the coves, stairs, or drains the drawing note asks for, the polyester properties cite an abrasion method for unrelated tests, the smoke units and several unit conversions disagree, the notes point to lettered items that no longer exist, the moisture test is cited two ways, joints are both filled and carried through, and every surface must be level even where floors slope to drains. Ask the specifier which wording the project intends before treating a difference as a design conflict.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should a chemical resistant resinous flooring specification review compare?

Compare what the drawings must show, the binder choice against each room’s chemicals, the property paragraphs and test methods, the substrate type and the concrete it needs, surface preparation and moisture testing, joints, drains, slopes, and thickness, conductive sparkproof floors and grounding, and the primer, top coat, installer, samples, and protection requirements.

How does UFGS 09 67 23.14 say to choose between epoxy, polyester, and latex?

The notes of the current UFGS 09 67 23.14 Chemical Resistant Resinous Flooring on WBDG say to choose by the exposure each location must withstand: polyester suits detergents but not strong alkalis, epoxy does not suit oxidizing acids, high temperatures, steam, or substrates that cannot be dried, and latex or resin emulsion matrices do not suit solvents or strong acids and alkalis. The designer adds the project’s chemicals to the resistance lists. UFGS numbers are DoD guide specification numbers, not universal MasterFormat titles, and your project’s issued specification governs.

How is this different from the resinous terrazzo page?

UFGS 09 66 23 covers thin-set epoxy and polyester terrazzo with marble chips, divider strips, chip size tied to topping thickness, and cast-in-place cove bases. UFGS 09 67 23.14 covers plain or quartz-filled resinous surfacings for laboratories, wash-down areas, and explosives facilities, with three binders and their property paragraphs, substrate preparation for concrete, plywood, and tile, and spark testing for conductive floors. A building can use both, so check that each area on the finish plan points to the right section.

Can Groundbook check resinous floor areas against Section 09 67 23.14?

Groundbook compares the drawing set with the specification sections and reference documents you upload, such as your issued Section 09 67 23.14, the finish schedule, room data sheets with chemical lists, the plumbing and electrical drawings, and licensed standards you hold, and returns potential conflicts with links to the source pages. It has no built-in code library and does not select flooring systems, rate chemical resistance, classify hazardous operations, design grounding, run or interpret tests, certify compliance, or approve submittals. Each finding is a question for the architect, the specifier, the electrical engineer, or the contracting officer.