Start with the summary note and the two performance paragraphs of the issued Section 09 96 00: confirm that the drawings show the type and extent of the coating work on each surface, quantify any existing coating removal by method and substrate, and that the operating temperatures and chemical concentrations left blank for each “[unit]” have been filled from the equipment and process data on the drawings. Then check that the kept test methods match each surface’s exposure (interior or exterior, atmospheric or immersion, insulated or bare), that the substrate paragraphs match the materials drawn, and that the tank, floating pan, and door sheet brackets are kept only where a chemical tank is actually in the work.
Assemble the review package
Gather the coating schedule or the plans and elevations that show which surfaces receive heat- or chemical-resistant coating, the mechanical and process equipment schedules with operating temperatures, the chemical storage and feed schedules with concentrations, the tank drawings with bottom, shell, roof, manways, internal piping, and any floating pan, the mechanical insulation drawings and schedules, the hazardous materials survey for existing coatings, the demolition and phasing plans, the site plan showing containment, staging, and berms, and the issued Section 09 96 00 with Sections 09 90 00, 09 97 13, 33 52 80, 02 83 00, 01 45 00, 01 35 26, and the tank construction section. Follow one hot or wetted surface from its equipment tag to its coating system, preparation, and test method before assuming the others match.
WBDG publishes UFGS 09 96 00: Heat- and Chemical-Resistant Coatings as a public guide-specification reference (accessed November 16, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| What the drawings must show | Summary note (indicate the type and extent of work on the drawings; quantify the area of existing coatings to be removed by method for each substrate; no quantities in the specification) + Summary bracket (substrates; high temperature or chemical exposure) + Surfaces to Be Coated brackets (tank, structure, roof, shell, legs, stair, railing; bottom, shell, roof; remove interior piping; do not coat an aluminum floating pan) + Project Identification note (mark the stencil location on the drawings) + coating schedule and plans | Do the drawings tag every surface that gets a heat- or chemical-resistant system, separate it from surfaces painted under Section 09 90 00, give the existing coating removal areas by method and substrate rather than leaving them for the specification, and show where the stencil goes, and does the kept bracket in Summary match the substrates and exposures actually drawn? |
| Scope boundary with fuel and architectural coatings | Opening note (high heat in immersion or atmosphere, including HVAC units and heat exchangers; immersion in destructive chemicals, such as chemical storage tanks and piping; fuel immersion in Section 09 97 13; interior fuel pipe coating in Section 33 52 80) + Galvanized Metal note (see Section 09 90 00) + Definitions (bottom, shell, and roof of a vertical tank) + Coatings Work Plan note (floating pans) + Work Sequence brackets (after tank tightness testing; before floating pan) + tank and equipment drawings | Is every tank, pipe, and piece of equipment assigned to this section actually in high-heat or chemical service, are fuel tanks and fuel piping sent to Sections 09 97 13 and 33 52 80, and has the specifier deleted the vertical tank definitions, floating pan, and tightness-test brackets where no chemical tank is in the work, since the section keeps them even though floating pans are typical of fuel storage it excludes? |
| Operating temperatures and chemical exposure | Heat-Resistant Performance Requirements (the “[unit]” maximum operating, minimum operating, and minimum off temperatures, blank; highest testing temperature as a stated percentage of the maximum) and note (mean or median operating temperature; ASTM D2485 range) + Chemical-Resistant Performance Requirements (maximum temperature, maximum humidity, and chemical concentrations, blank) + combined heat and chemical service bracket (printed twice) + equipment and process schedules | Has the specifier filled the temperature, humidity, and chemical blanks for each unit, and do they match the operating data on the mechanical and process schedules, so the laboratory tests the coating at conditions the equipment will see, and where one unit has both heat and chemical exposure, is the combined-service bracket kept once and tied to that unit’s design temperature? |
| Test methods, test panels, and insulated service | Heat-Resistant Coating Performance Testing (ASTM D2485 Method A interior or Method B exterior; ASTM D6944 Method A immersion or Method B atmospheric; failure criteria) + CUI notes and bracket (ISO 19277 class by temperature; steel only; no sacrificial zinc under insulation) + Chemical-Resistant Performance Testing (pass two or more of ASTM D1308 immersion, ASTM D6943, ISO 2812; matched chemicals) + Performance Requirements (panels of the same material and grade as the substrate) and bracket (test concrete and masonry systems on steel panels) + mechanical insulation drawings | Does each kept method match the exposure shown (indoors or exposed to sun and salt, immersed or atmospheric), is the CUI bracket kept wherever the insulation drawings cover hot steel, and has the specifier reconciled the unbracketed same-substrate panel requirement with the steel-panel bracket for concrete and masonry, since both cannot apply to a concrete containment or masonry stack? |
| Substrates and coating systems | Coating Systems for Steel (carbon and low-alloy steel; stainless steel with no metal-rich primers) + Historical MPI Coating Systems by Substrate table (a vinyl wash primer listed as a polyurethane and as the only chlorinated rubber entry for aluminum; an alkyd primer as the chlorinated rubber entry for galvanized metal; interior latex and a water-based galvanized primer under polyurethane) and chlorinated rubber content sentence + one manufacturer and contrasting coat colors + Color Chips + equipment, structural, and architectural material callouts | Do the drawings name the substrate of each coated surface (galvanized steel, stainless steel, aluminum, concrete, masonry, or carbon steel), has the specifier deleted the substrate paragraphs and table rows not in the work, and has the historical table been corrected or removed, since several of its entries are primers or latex products in columns for other resin types and none of its chlorinated rubber entries is a chlorinated rubber product? |
| Surface preparation and existing coatings | Removal of Coatings Containing Hazardous Materials bracket (Section 02 83 00) and note + Carbon Steel and Low-Alloy Steel (SSPC-SP 10; profile from the Coating System Instructions; a rejection sentence that mixes a fixed value with “the specified range”) + Galvanized Metal (ASTM D6386 or SSPC-SP 16; ASTM D7803 for powder) + Aluminum and Stainless Steel (SSPC-SP 17; non-metallic media) + Concrete (curing time before coating, longer for slab on grade; SSPC-SP 13) + Surface Standard (unfinished ICRI CSP bracket) + hazardous materials survey and demolition plans | Does the hazardous materials survey identify lead, chromium, cadmium, or PCB coatings on the surfaces shown for removal, and is Section 02 83 00 in the project manual if so, has the specifier rewritten the steel profile rejection sentence and finished or deleted the concrete profile bracket, and does the schedule give new concrete curbs, pads, or slabs enough age before coating? |
| Shop or field work, sequence, containment, and access | Work Sequence brackets (all in the field; shop blast with a hold primer removed in the field; all in an SSPC QP 3 shop with field repair; coat after tank tightness testing; coat before the floating pan) and notes + Containment System (SSPC Guide 6 class bracket; containment in place from blasting through initial cure) + Use of Door Sheet Access Way (API Std 650 and 653; a registered engineer approves calculations) and note (may require a hydrotest) + overspray limit from the tank perimeter or berm + Curing for Immersion Service + phasing and site plans | Has the specifier kept one sequence bracket that matches how the equipment or tank is fabricated and delivered, do the phasing and site plans leave room for the containment class chosen and show the berm or perimeter the overspray limit refers to, and if a door sheet access way is allowed, does the tank section or the drawings address the hydrotest and the return-to-service schedule? |
| Coatings QA and QC chain and the section’s own wording | Contract Errors, Omissions, and Other Discrepancies (submit after award) + PCS qualifications (independent third party) and PCS paragraph (a QC Specialist reporting to the QC Manager; liaison to a “QA Manager”) + Coatings Inspection Company note (the Government may provide QP 5 QA) + Section 01 45 00 experience matrix note + Mixing (temperature and humidity “specified in” Delivery and Storage, which gives none) + Environmental Conditions Monitoring (an Automated Monitoring Requirements paragraph that does not exist) + oil and grease cleaning to SSPC-SP 1 (not in References) + stripe coat definition (spray) versus application (brush-out) + Grade A samples (MPI APL or MIL QPL listing) | Who provides the QA coatings inspector, the contractor or the Government, and is the PCS listed as a QC Specialist in the issued Section 01 45 00, has the specifier fixed the paragraphs that point to requirements the section does not contain, and has the sample grading been adjusted for products qualified by testing rather than by a product list? |
Worked example: a boiler plant stack and a chemical feed tank with the operating blanks left open
Illustrative example: a central heating plant renovation recoats the exterior of the boiler breeching and a steel exhaust stack, coats a new carbon steel tank for water treatment chemicals, and coats a new concrete containment curb around it. The issued Section 09 96 00 leaves every “[unit]” temperature and chemical blank, keeps both D2485 methods and both D6944 methods, deletes the CUI bracket, keeps the floating pan and door sheet brackets, and keeps the historical MPI table whole. The mechanical schedule lists the breeching and stack temperatures, the insulation drawings wrap the breeching, the hazardous materials survey reports lead in the existing stack coating, and the concrete schedule pours the containment curb shortly before the coating starts.
Ask the mechanical engineer to give the operating temperatures for the breeching and stack and the chemical concentrations and service temperature for the tank, and ask the specifier to enter them per unit, keep one D2485 and one D6944 method per exposure, restore the CUI bracket for the insulated breeching, delete the floating pan and door sheet brackets, correct the historical table, and add Section 02 83 00 for the lead coating. Ask the architect or civil engineer to show the containment and staging areas and to sequence the curb pour so the concrete is old enough before it is coated.
Avoid a false conflict
Section 09 96 00 covers coatings for high-heat and chemical service. Architectural paints follow Section 09 90 00 and the painting guide, fuel tank and fuel piping coatings follow Sections 09 97 13 and 33 52 80, hazardous coating removal follows Section 02 83 00, quality control and safety follow Sections 01 45 00 and 01 35 26, tank construction and insulation follow their own sections, and the coating manufacturer’s instructions govern profile, thickness, and recoat windows, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the combined-service bracket prints twice, the test panel paragraph and the steel-panel bracket disagree for concrete and masonry, the historical MPI table puts primers and latex products in other resin columns, the steel profile rejection sentence and the concrete profile bracket are unfinished, Mixing and Environmental Conditions Monitoring point to requirements the section does not contain, SSPC-SP 1 and ICRI are not in References, the PCS is both independent and a contractor QC Specialist, the stripe coat definition and application disagree, and the fuel-tank brackets remain in a section that excludes fuel. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.
Where Groundbook fits
Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.