Guide · Specifications and drawings · 09 66 23

Check epoxy and resinous terrazzo specifications against finish plans, room uses, conductive floor areas, and bases

UFGS Section 09 66 23 Resinous Matrix Terrazzo Flooring, a USACE-prepared guide specification issued in August 2016 and last changed in August 2018, covers thin-set terrazzo with an epoxy or polyester binder and a conductive version of either. It specifies the system by NTMA Info Guide paragraphs, primer, resin, fillers, domestic marble chips with an optional recycled content bracket, divider and control joint strips, grout, and sealer with indoor air quality options, installer qualifications, then substrate preparation, installation to a bracketed topping thickness, cast-in-place cove bases, a resistance test for conductive floors, cleaning, sealing, and protection. Its notes say where the thin-set system may replace portland cement terrazzo, where it may not be used, and how to choose a binder for the room’s chemical exposure.

Start with the opening and Summary notes of the issued Section 09 66 23: confirm that each terrazzo area on the finish plan has a binder suited to the chemicals and temperatures in that room, that none sits on lightweight concrete or replaces quarry tile in a kitchen, and that conductive terrazzo is kept wherever the room’s operations need it and deleted, with its test, everywhere else. Then check that the topping thickness, chip size, and color plate agree, that cove bases, strip layouts, and joints are shown, and that conductive rooms have the strip material, grounding, and testing the section and the project’s safety criteria call for.

Assemble the review package

Gather the floor finish plans and the finish schedule with terrazzo colors and base types, the room data sheets or the list of operations and chemicals for each room, the structural slab plans with the concrete type and slab joints, the wall base and threshold details, the electrical drawings for rooms with conductive floors, the explosives safety or hazard analysis for those rooms, and the issued Section 09 66 23 with Sections 09 06 00, 03 30 00, 07 92 00, 09 30 10, and 01 33 00. Follow one terrazzo area from its room use to its binder, thickness, base, strips, and test before assuming the others match.

WBDG publishes UFGS 09 66 23: Resinous Matrix Terrazzo Flooring as a public guide-specification reference (accessed November 16, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
What the drawings must showOpening note (areas to receive terrazzo shown on the drawings; color by an NTMA plate from a “Terrazzo Information Guide” or “NTMA terrazzo catalog”, while References list the Terrazzo Reference Guide) + Summary (colors indicated; areas shown on the detail drawings) + Divider Strips note (strip locations shown, at logical stops and expansion joints) + Strips (contractor drawings of strip type, size, and layout; SD-02 Strips and Control Joint Strips with a “G”) + SD-02 Detail Drawings with a “G” and no paragraph defining them + finish plansDoes every resinous terrazzo area on the finish plan carry a color plate from the publication References list, a strip layout, and its base type, and has the specifier said what the separately listed Detail Drawings submittal must show beyond the strip layout?
Epoxy, polyester, or conductive for each roomSummary (epoxy or polyester to NTMA Info Guide paragraphs 2.01; conductive epoxy to 2.01 with an added paragraph; conductive polyester to paragraphs numbered 2.10) + opening note (choose by exposure: polyester where detergents are used but not where strong alkalis spill; epoxy not where oxidizing acids or high temperatures occur; latex mastic and resin emulsions not for strong acids or alkalis) + room data sheets or chemical listsHas the specifier kept one binder, or a choice the project can live with in every room, does any room on the room data sheets handle the alkalis, oxidizing acids, or hot spills the note warns about, and is the conductive polyester reference a mistyped 2.01?
Where a thin-set resinous floor may goOpening note (may replace portland cement terrazzo where light weight helps; not over lightweight concrete; not in place of quarry tile in kitchens; hard-wear, clean, decorative areas when economically justified) + Preparation of Concrete Subfloor (a substrate cure period before topping; preparation by the resin manufacturer; no moisture test named) + structural slab concrete type + kitchen finish schedule + Section 09 30 10Is any resinous terrazzo area on a lightweight concrete slab or a kitchen floor the note gives to quarry tile, does the schedule allow the substrate cure period before topping, and has the specifier asked for the slab moisture testing the resin manufacturer will require?
Conductive floors and resistance testingSummary note (conductive floors where electrostatically sensitive explosives, loose ammunition with electric primers, exposed electro-explosive devices, electrically initiated items, or static-ignitable materials are present) + Divider Strips note (plastic strips with conductive terrazzo; both strip paragraphs still offer brass and zinc) + Testing (unbracketed; a test window after installation; resistance limits by the room’s service voltage; NFPA 99 cited by a hyphenated paragraph number in an older numbering style while References list the 2024 edition; certificates and certified test reports) + SD-06 Certified Test Reports “G” + SD-07 (installer qualifications only) + electrical drawings + explosives safety criteriaWhich rooms need conductive terrazzo under the project’s explosives safety criteria, does the finish plan mark them, are their strips plastic, do the electrical drawings give the service voltage the resistance limits depend on, does the test method cited still exist in the NFPA 99 edition listed or should the project’s explosives safety criteria govern, is the certificate submittal listed, and is Testing deleted if no floor is conductive?
Topping thickness, chip size, and cove basesMarble Chips (domestic; size ranges tied to each topping thickness; color plate on the drawings or in Section 09 06 00) + Mixing, Proportioning, and Installation note (topping thickness set by the chip size in the selected plate, named “NTMA-01”; delete the base sentence if no resinous bases) + Mixing, Proportioning, and Installation (bracketed topping thickness; cast-in-place cove base with bracketed heights) + finish schedule base types + wall base and threshold detailsDoes the bracketed topping thickness match the chip sizes in the color plate the finish schedule names, do the base details show the cove radius and the height the specifier kept, are cove bases deleted where the schedule gives another base, and do thresholds account for a thin-set floor beside thicker finishes?
Divider and control joint stripsDivider Strips (as deep as required; gauge blank; brass, zinc, or plastic in a color from Section 09 06 00) + Control Joint Strips (as deep as required; gauge blank; brass, zinc, or plastic; neoprene filler thickness blank with a mixed unit) + Mixing, Proportioning, and Installation (install strips in locations indicated) + slab joint plan + Section 07 92 00Has the specifier filled the gauges and the filler thickness, does a control joint strip sit over every slab joint on the structural plans, and do the strip colors and materials on the finish schedule agree with the section and with the conductive floor note?
Primer, resin, grout, sealer, and indoor air qualityPrimer (resin manufacturer’s, monolithic bond) + Resin (NTMA Info Guide; mixing and installation instructions) + Fillers + Grout (resin manufacturer’s; CDPH Section 01350 or SCAQMD Rule 1168) + Sealer (penetrating, non-yellowing, slip resistant; flash point by ASTM D56; CDPH Section 01350 or SCAQMD Rule 1113) + Marble Chips recycled content bracket + SD-03 “S” itemsAre primer, resin, and grout from one manufacturer’s system, does the slip resistance the sealer must give agree with any floor slip criteria on the finish schedule, and if the recycled content bracket is kept, is the recycled chip supply domestic as the Marble Chips paragraph requires?
Installer, samples, cleaning, and protectionQuality Assurance (resin manufacturer’s approval and an experience record, unbracketed; SD-07 “G”) + Summary (samples of each terrazzo color and each strip type; SD-04 lists only the terrazzo samples, without a “G”) + Delivery, Storage, and Handling and Environmental Requirements (temperature ranges before and after installation) + Cleaning and Sealing (removes “cement smears” from a resin floor; maintenance literature under SD-03) + ProtectionDoes the installer requirement suit the size of the project, are the strip samples listed and the terrazzo samples given an approval path, does the schedule hold the conditioned temperatures the section requires around installation, and has the cleaning wording been edited for a resin floor?

Worked example: an ammunition maintenance shop with conductive epoxy terrazzo and a break room

Illustrative example: an ammunition maintenance facility schedules conductive epoxy terrazzo in two work bays and standard epoxy terrazzo in the corridor and a break room with a kitchenette. The issued Section 09 66 23 keeps both the epoxy and polyester brackets, keeps brass divider strips, leaves the Testing paragraph as written, and keeps the cove base sentence. The finish plan does not mark which bays are conductive, the electrical drawings show two service voltages in the bays without saying which floor areas they serve, the structural notes call for lightweight concrete on the second-floor break room, and the base schedule shows rubber base in the corridor.

Ask the architect to mark the conductive floor areas and to move the break room off resinous terrazzo or onto a normal-weight slab, as the note directs. Ask the specifier to keep one binder for the work bays, to change the strips to plastic in the conductive bays, to confirm the test method against the project’s explosives safety criteria and the NFPA 99 edition listed, to list the conformance certificates, and to delete the cove base sentence where the schedule gives rubber base. Ask the electrical engineer to show the service voltage for each conductive bay.

Avoid a false conflict

Section 09 66 23 covers thin-set epoxy and polyester terrazzo, conductive or not. Portland cement terrazzo follows Section 09 66 13 and the portland cement terrazzo guide, terrazzo tile follows Section 09 66 16, chemical-resistant resinous flooring without a terrazzo finish follows Section 09 67 23.14, quarry tile follows Section 09 30 10 and the ceramic tile guide, the slab follows Section 03 30 00 and the concrete guide, sealants follow Section 07 92 00, and DoD explosives safety criteria and the electrical design govern conductive floors and grounding, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the conductive polyester option cites a different NTMA paragraph number from every other option, the notes name color publications References do not list, the conductive note asks for plastic strips the strip paragraphs do not require, Testing cites NFPA 99 by an older paragraph number and is not bracketed for the conductive option, the certificates Testing asks for are not listed, the Detail Drawings submittal is undefined, strip samples are asked for but not listed, and cleaning removes cement smears from a resin floor. Ask the specifier which wording the project intends before treating a difference as a design conflict.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should a resinous terrazzo specification review compare?

Compare what the drawings must show, the epoxy, polyester, or conductive choice for each room, where a thin-set resinous floor may go, conductive floors and resistance testing, topping thickness, chip size, and cove bases, divider and control joint strips, primer, resin, grout, sealer, and indoor air quality, and installer, samples, cleaning, and protection.

Where does UFGS 09 66 23 say not to use resinous terrazzo?

The opening notes of the current UFGS 09 66 23 Resinous Matrix Terrazzo Flooring on WBDG say the systems will not be used over lightweight concrete or in place of quarry tile in kitchens, and they warn against polyester where strong alkalis spill, epoxy where oxidizing acids or high temperatures occur, and latex mastic or resin emulsions where strong acids or alkalis are present. UFGS numbers are DoD guide specification numbers, not universal MasterFormat titles, and your project’s issued specification governs.

How is this different from the portland cement terrazzo page?

UFGS 09 66 13 covers cementitious terrazzo bonded through a sand and cement underbed, with a slab recess, grinding and grouting, and curing. UFGS 09 66 23 covers thin-set epoxy and polyester terrazzo, adds the binder choice by chemical exposure, the lightweight concrete and kitchen exclusions, conductive floors with a resistance test, chip size tied to topping thickness, cast-in-place cove bases, and installer qualifications. A project can use both, so check that each area on the finish plan points to the right section.

Can Groundbook check conductive floor areas against Section 09 66 23?

Groundbook compares the drawing set with the specification sections and reference documents you upload, such as your issued Section 09 66 23, the finish schedule, the room data sheets, the electrical drawings, the project’s explosives safety criteria, and licensed standards you hold, and returns potential conflicts with links to the source pages. It has no built-in code library and does not select flooring systems, classify hazardous operations, design grounding, run or interpret resistance tests, certify compliance, or approve submittals. Each finding is a question for the architect, the electrical engineer, the safety office, the specifier, or the contracting officer.

Keep exploring

Continue your review

Check ceramic, quarry, and glass tile specifications against drawings

Compare tile type, substrate preparation, setting method, and waterproofing across finish plans and specifications. Editable CSV included.

Explore

Check resilient flooring specifications against drawings

Compare resilient flooring types, substrate moisture testing, transitions, and adhesive compatibility across finish plans and specifications.

Explore

Finish schedule review checklist

Check a room finish schedule against floor finish plans, ceiling plans, elevations, details and specifications. 12 review prompts and a free CSV.

Explore

Check concrete specifications against drawings

Compare concrete mix references, slab finishes, joints, embeds, and curing requirements across specifications and drawings. Includes an editable checklist.

Explore

Check joint sealant specifications against drawings

Compare joint sealant type, joint design, substrate compatibility, and movement capability across wall details and specifications. Editable CSV included.

Explore

Commercial kitchen drawing review checklist

Reconcile food-service equipment, utility rough-ins, hoods, grease waste, and floor construction across disciplines. 12 prompts and a free editable CSV.

Explore

NFPA 99 health care facilities plan review

Review NFPA 99 health care facility documents across risk categories, medical gas, electrical systems, rooms, and equipment. See checks and limits.

Explore

UFC 3-120-10 Interior Design review of DoD SID and FF&E packages

Review DoD interior design packages against the reissued UFC 3-120-10: comprehensive interior design, SID finishes, FF&E plans, wayfinding, and room numbers.

Explore

UFC 3-101-01 Architecture document review for DoD projects

Review DoD architectural sets against the reissued UFC 3-101-01: IBC modifications, air barriers, envelope renovation, mockups, and acoustics.

Explore

Floor level and elevation coordination checklist

Check finished floor, slab, roof, grade and drainage invert levels across architectural, structural, MEP and civil drawings. 12 review prompts and a free CSV.

Explore

Use the section number to find the actual requirement

What CSI MasterFormat numbers identify, how to read a project specification reference, and how to connect sections with drawings and submittals.

Explore

Check portland cement terrazzo specifications against floor finish plans, slab recesses, and strip layouts

Compare bonded cement terrazzo depth, divider and control joint strips, colors, recycled aggregate, and grinding with UFGS 09 66 13.

Explore

Check chemical resistant resinous flooring specifications against finish plans, room chemical lists, drain details, and slab drawings

Compare matrix choice by chemical exposure, substrate prep, moisture testing, joints, drains, cove bases, and conductive floors with UFGS 09 67 23.14.

Explore

Drawings vs. specifications

Compare drawing requirements with specifications, schedules, and controls. Find potential equipment, material, and scope inconsistencies with Groundbook AI.

Explore

Bring your next set into focus

Set up a review or talk through your project with our team.

Check your resinous terrazzo spec against the finish plans

Trusted by hundreds of professionals