We’re at NCSEA in San Francisco, Oct 28–29 · Booth 110NCSEA · Booth 110 · Oct 28–29

Guide · Specifications and drawings · 26 05 73

Check power system study specifications against drawings

Section 26 05 73 asks the contractor’s System Analyzer to model the system and run load flow, fault current, coordination, and arc flash studies. The studies can only be as accurate as the drawings they start from, so the review is about whether the one-line and schedules give the studies the right equipment, sources, and names.

Confirm that the scope and operating modes the section lists cover every source on the one-line, including generators, transfer switches, and ties, and that the equipment, protective devices, and names the studies must model are shown on the one-line and schedules. Then check that the sections that invoke the studies, and the arc flash label details, point to the same Section 26 05 73.

Assemble the review package

Gather the electrical one-line, the switchgear, switchboard, and panelboard schedules, the generator and transfer switch drawings, the utility or existing system information, the existing one-line and demolition drawings for renovation work, the arc flash and fault current label details, and the issued Section 26 05 73 with the sections that reference it (26 20 00, 26 23 00, and 26 24 13). Review one path from the source bus to the farthest panel in scope before assuming the rest is covered.

WBDG publishes UFGS 26 05 73: Power System Studies as a public guide-specification reference (accessed October 18, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.

Eight checks to run against the issued set

Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.

Eight specification-to-drawing checksSwipe or scroll sideways to read all columns.
CheckSources to compareQuestion to resolve
Scope of studiesScope of Studies article + one-lineIs the starting bus and extent of the studies filled in, and does the one-line show all the equipment within that scope?
Modes of operationScope of Studies article + one-line + generator and transfer switch drawingsDo the modes of operation listed include every combination of utility, generator, and tie the one-line makes possible?
Available fault currentDetermination of Facts article + one-line or utility dataIf the specification says to use the indicated available fault current, is a value actually shown on the drawings for the source bus?
Protective devices shownPower System Studies article + one-line + panel schedulesAre the fuses, breakers, and relays the designer is responsible for showing on the drawings, so the studies model the devices that will be bought?
Equipment namesSingle Line Diagram and Arc Flash Labels articles + one-line + schedulesDoes each bus and device have one unique name used the same way on the one-line, schedules, and room plans, so the model and labels can match it?
Existing equipmentModeling and Field Examination articles + existing one-lineFor renovation work, is the existing equipment affected by the work identified so the field examination and model can include it?
Sections that invoke the studiesCoordinated Power System Protection articles in Sections 26 20 00, 26 23 00, and 26 24 13Where those sections point to Section 26 05 73, is it in the project manual, and where it is included, are those articles retained consistently?
Arc flash labels and timingArc Flash Labels and Study report(s) articles + label detailsIs the arc flash label format shown, and does the submittal schedule put the studies with the protective device submittals the section names?

Worked example: a generator the study scope leaves out

Illustrative example: the one-line shows a standby generator feeding the main switchboard through a transfer switch, and a tie between two distribution sections. The issued Section 26 05 73 lists a single primary mode of operation, utility source with the tie open, and the generator schedule gives no data the System Analyzer could use for its contribution.

Ask the electrical engineer to list the operating modes the one-line allows, including generator operation and the closed tie, and to add the generator data or state where it will come from. Recheck the equipment names on the one-line against the schedules so the model and arc flash labels can use them.

Avoid a false conflict

A study that matches its own model can still miss equipment that is on the drawings but outside its scope. Check the scope and modes against the one-line, not against the study report.

When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.

Close the issue across the affected documents

Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.

For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.

Where Groundbook fits

Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.

Questions, answered

FAQs

What should a power system study specification review compare?

Compare the scope of studies, modes of operation, available fault current, the protective devices shown, equipment names, existing equipment, the sections that invoke the studies, and arc flash label formats and submittal timing.

When does UFGS 26 05 73 require the studies to be submitted?

The current UFGS 26 05 73 on WBDG asks for the study reports to be submitted along with the protective device equipment submittals, with arc flash labels applied after the studies are approved and the studies updated after equipment changes. Your project’s issued specification governs, so confirm what it says after editing.

Does Groundbook perform the power system studies?

No. Groundbook compares the documents the studies depend on. The studies, protective device settings, and arc flash results come from the System Analyzer the specification requires, and design and approval stay with the electrical engineer of record and the authority having jurisdiction.

Bring your next set into focus

Set up a review or talk through your project with our team.

Check that your studies match the equipment drawn

Trusted by hundreds of professionals