Start with the opening note of the issued Section 03 41 33: confirm that the drawings give the assumed loads including topping weight, the framing layout, a cross-section of every member, the reinforcement and tendon data with the final stressing force, the connections with end bearing and embedded items, the topping, openings, hangers, raceway cells, and the fire-rated areas. Then check who designs the members, that camber and strand data on the member schedules match the tolerances and detensioning paragraphs, that bearing pads, welds, and openings are located, and that the section’s blank water-cementitious ratio, misassigned test standards, strand wording, and joint tape standards are resolved.
Assemble the review package
Gather the structural general notes with design loads, deflection limits, and concrete data, the precast framing plans with piece marks, column grid, floor elevations, and openings, the member schedules and sections with strand patterns, stressing force, and camber, the bearing, connection, and weld details, the topping plans, the architectural reflected ceiling plans and elevations showing exposed precast, the roof plan and roofing details over precast roof slabs, the life safety plans with fire ratings, the electrical plans that use hollow-core cells as raceways, the MEP penetration and hanger plans, the project’s Environmental Severity Classification from UFC 1-200-01, and the issued Section 03 41 33 with Sections 03 30 53, 03 45 00, 05 05 23.16, 07 92 00, 09 90 00, and 26 20 00. Follow one bay from its framing plan through a beam bearing, a hollow-core opening, and a roof joint before assuming the others match.
WBDG publishes UFGS 03 41 33: Precast Structural Pretensioned Concrete as a public guide-specification reference (accessed November 15, 2026). Use your project’s issued specification and amendments for the actual comparison; the guide specification does not automatically govern your project. The checklist below is an original suggested review workflow, not a reproduction of the UFGS requirements.
Eight checks to run against the issued set
Use one record per location or system. The CSV contains the same eight prompts plus fields for source revisions, observed evidence, the review owner, the decision, and closure references.
| Check | Sources to compare | Question to resolve |
|---|---|---|
| What the drawings must show | Opening drawing note (assumed loads including topping weight and suspended equipment; framing layout with column centers, offsets, floor elevations, and openings; cross-sections of every member; architectural finish locations; reinforcement schedules, welded-wire fabric, and tendons with the final stressing force; connections with end bearing minimums and embedded items; topping; openings with steel framing; filler blocks; hangers; raceway cells; fire-rated locations) + Forms, Reinforcement, Built-In Anchorage Devices, and Blockouts notes (indicate them) + framing plans and member schedules | Do the framing plans and member schedules carry each item the note lists, especially the topping weight in the assumed loads, the final stressing force and strand pattern for every prestressed member type, the end bearing at each support, and the embedded plates and inserts, or are some items left for the precaster to guess? |
| Who designs the members and connections | Opening note (“a complete design” on the drawings) + Design Methods (ACI/MCP-3, ACI 318 and 318M, PCI MNL-120) + Allowable Design Loads and Deflections (“as indicated”) and note (recommended loads in ASCE 7-10, an edition the References article does not list) + System Description (fabrication and installation drawings signed and sealed by a licensed professional engineer) + SD-02 drawings with “G” + structural general notes | Do the general notes say whether the engineer of record has designed the members and connections or delegated them to the precaster’s engineer, are deflection limits indicated as the paragraph requires, are the design loads taken from the ASCE 7 edition the adopted building code uses rather than the edition the note names, and does the submittal review path suit sealed drawings? |
| Strand, wire, and bar tendons | Strand Tendons (uncoated or galvanized bracket; “7-strand, stress-relieved, steel wire” to ASTM A416/A416M, titled low-relaxation seven-wire strand) and note (galvanized tendons in severe Environmental Severity Classifications) + Wire Tendons (ASTM A421/A421M types to suit the anchorage) + Steel-Bar Tendons (ASTM A322, titled standard-grade alloy bars; two bracketed tensile property columns) + Tendon Anchorages for Pretensioning and for Post Tensioning + member schedules | Has the specifier rewritten the strand paragraph to name the strand the member schedules and the precaster’s design actually use, is the galvanized bracket kept where the classification calls for it, and are the wire tendon, bar tendon, and post-tensioning anchorage paragraphs deleted unless the drawings show field post-tensioned connections, with a prestressing bar standard named if bars are kept? |
| Pretensioning, detensioning, camber, and tolerances | Pretensioning (single- or multiple-strand; force by elongation checked against gauge or dynamometer; broken tendon limit) + Detensioning (strength by member type, including members where camber must be minimized; symmetric, gradual release) + SD-07 Pretensioning and Detensioning + Fabrication Tolerances (deviation from the camber indicated on the drawings; tendon and deflection point position; metric and inch-pound ends-out-of-square limits for wider members that do not agree) + Installation Tolerances (difference between adjacent members) + member schedules and topping sections | Do the member schedules indicate a camber for each prestressed member, since the tolerance is measured from it, do they identify the beams where camber must be minimized, does the topping section allow for the camber and the difference between adjacent members, and has the specifier made the two ends-out-of-square tolerance lists agree? |
| Concrete, plant testing, and acceptance | Normal-Weight and Lightweight Concrete Properties tables (a maximum water-cementitious ratio row with no value or bracket in both unit systems) + Concrete Design Mixes (trial mixes; “the maximum water/cement ratio specified”) + Tests for Concrete Materials (printed twice; fineness modulus to ASTM C126, titled ceramic glazed structural clay facing tile; heat of hydration to ASTM C185, titled air content of mortar) + Quality Control Testing During Fabrication + Evaluation of Compressive Strength Tests (two bracketed criteria) + Strength at Installation (two paragraphs, one to delete) + Supplemental Testing (cores; static load test at a proof-test load not stated) | Has the specifier filled in the water-cementitious ratio, kept only the normal-weight or lightweight tables the members use, deleted the duplicate test table, pointed the fineness modulus and heat of hydration rows at the right test methods, chosen one acceptance criterion and one strength-at-installation paragraph, and stated the test load for a static load test? |
| Bearing pads, connections, and welding | Flexible Bearing Pads (hardboard or elastomeric, one to delete; location and size indicated; an elastomeric property row with a value but no property or test method) + Installation of Flexible Bearing Pads + Placing Slab Structural Sections (a minimum end bearing stated in the text) + Steel Plates, Shapes, and Bars (no welded or bolted connectors exposed to weather unless stainless, galvanized, or epoxy coated) + Welded Connections (AWS D1.4 and D1.1) + Inspection of Welding (bracketed clause numbers) + Weld Acceptance (AWS D1.4 only; random NDT percentage blank “as indicated on the drawings”) and note (welds requiring inspection indicated) + connection details | Do the bearing details show a pad type and size at every support, does the end bearing on the details meet the minimum the text fixes, are exposed connections specified in a corrosion-resistant finish, do the drawings mark which welds are inspected and by which method, and has the specifier filled the NDT percentage and checked the AWS clause numbers against the listed editions? |
| Openings, hollow-core raceways, and hangers | Blockouts (as indicated; openings that would cut primary reinforcement cast in at the plant) + Field Cut Openings (no cutting of bars or strands; size limited by the voids) and the hollow-core header paragraph, whose note says to use it when hollow-core slabs are not required + Electrical Raceway UL Listing and Label + placing and sealing raceway slabs + Section 26 20 00 + MEP penetration plans and hanger details | Is every opening on the plumbing, mechanical, and electrical plans that exceeds what a field cut allows drawn on the precast framing plan as a blockout with its header, has the specifier corrected the note on the header paragraph so it is kept when hollow-core slabs are used, are raceway cells and their alignment shown where the electrical plans rely on them, and are hangers for ceilings, ducts, and piping detailed rather than drilled into strands? |
| Grout, roof joints, fire rating, finishes, and other trades | Grouting Materials (packaged nonshrink grout or epoxy grout) + Grouting Connections and Joints (cement or nonshrink grout; fire agency note) + Bituminous Joint Sealing Materials (asphalt-treated, glass-fiber tape cited to ASTM D2103 and D4397, titled polyethylene film and sheeting, or a building paper standard) + Sealing Joints in Roof Slabs + UL Fire-Resistance Listing (locations and classifications indicated) + Finishing Formed Surfaces (grout finish on exposed surfaces; architectural finishes to Section 03 45 00) + Sections 07 92 00, 09 90 00, and the roofing section | Do the roof plan and roofing details account for the joint sealing tape over double-tee joints, and has the specifier named a tape standard that matches the tape described, do the life safety plans give each rated area a listed precast assembly with the grout and joint treatment that listing requires, and do the reflected ceiling plans and elevations mark which surfaces get a grout finish, an architectural finish, joint sealant, or paint? |
Worked example: hollow-core floors with an unshown shaft, double-tee roof joints, and no camber on the schedule
Illustrative example: a two-story battalion headquarters uses hollow-core floor planks on precast inverted-tee beams and a double-tee roof. The issued Section 03 41 33 keeps both the normal-weight and lightweight tables, leaves the water-cementitious ratio blank, keeps the strand paragraph as printed, keeps both bearing pad types and both strength-at-installation paragraphs, and leaves the NDT percentage blank. The member schedule gives strand patterns but no camber, the plumbing plans show a riser shaft through the second floor that the precast framing plan does not show, the bearing details at the inverted tees show a pad with no type or size, and the roofing details show the double-tee joints without the joint sealing tape the section requires.
Ask the structural engineer to state whether the members are delegated, to add camber to the member schedule, to size the bearing pads, and to add the shaft opening and its header to the framing plan so it is cast in at the plant. Ask the specifier to delete the lightweight tables, fill in the water-cementitious ratio, choose one bearing pad type, one strength-at-installation paragraph, and one acceptance criterion, fill in the NDT percentage, rewrite the strand paragraph, correct the test standards and the joint tape standard, and fix the field-cut openings note. Ask the architect to coordinate the roof joint tape with the roofing section.
Avoid a false conflict
Section 03 41 33 is the USACE guide section for plant-made pretensioned and conventionally reinforced structural members; UFGS also carries 03 45 33, prepared by NAVFAC, for precast structural concrete, so check which section the project manual uses before applying either guide. Cast-in-place topping follows Section 03 30 53, precast wall panels and exposed aggregate finishes follow Section 03 45 00, short-span roof slabs follow Section 03 41 16.08, post-tensioned cast-in-place work follows Section 03 23 00 and the tendon guide, welding follows Section 05 05 23.16, joint sealants follow Section 07 92 00, and raceway work follows Section 26 20 00, so check those before calling a requirement missing. Some of the section’s own wording needs resolving: the strand paragraph describes stress-relieved strand under a low-relaxation standard, two test rows cite unrelated standards and the test table is printed twice, the water-cementitious ratio row is blank, the ends-out-of-square tolerances disagree between unit systems, the field-cut openings note is inverted, the joint tape cites polyethylene sheeting standards, one bearing pad property has no name or test, and a design load note cites an older ASCE 7 edition. Ask the specifier which wording the project intends before treating a difference as a design conflict.
When requirements disagree, follow the project’s document-control and clarification process. Do not assume that drawings always override specifications, or the reverse. Identify the exact sources and request an authorized decision.
Close the issue across the affected documents
Record the location or tag, drawing and specification references, issue dates, observed difference, and the decision needed. Assign an owner and keep the item open until the response identifies the governing requirement. Check the revised drawings and specification references together; a response email alone may leave the issued package inconsistent.
For the overall process, use the guide to drawing and specification conflicts. Mark an inapplicable checklist row with a reason, and distinguish a verified correction from a question that still needs design information.
Where Groundbook fits
Groundbook’s drawing and specification review helps investigate potential disagreements in the documents you supply. Include the relevant specification sections and drawing references, then verify the cited evidence with the responsible reviewers before acting on a finding.