Plan check correction · Fire and life safety

Plan check correction: fire separation distance and exterior wall openings

Buildings close to a property line draw this comment. The distance sets both the rating of the exterior wall and how much of it can be windows and doors.

The comment asks you to dimension the fire separation distance from each exterior wall to the lot line, or to the centerline of a street or an imaginary line between buildings, and show that the wall rating and opening area meet the limits for that distance. Clear it with dimensioned site and floor plans and an opening-area calculation on the elevations.

Read the comment

What the plans examiner is asking for

Fire separation distance

Dimensions measured perpendicular from each face of the building to the lot line, street centerline, or an imaginary line between buildings on the same lot.

Exterior wall rating

The rating each wall needs for its distance, occupancy, and construction type under IBC Section 705.5 and Table 705.5.

Opening area

Allowable unprotected and protected opening area for the distance under IBC Section 705.9 and Table 705.9, with the actual area calculated per story.

Projections

Eaves, balconies, and other projections checked for their distance to the line.

Published correction lists

How city lists word this correction

Published lists ask for fire separation distance dimensions, exterior wall ratings, or the percentage of openings. Paraphrased from each department’s own published list; the lists do not rank items by how often they are issued.

Fire separation distance: published correction list items by citySwipe or scroll sideways to read all columns.
CityWhat the published list asks forCode citedWhere it appears
Los AngelesShow fire separation distance to interior lot lines, to the centerline of streets, alleys or public ways, and to imaginary lines between buildings, measured perpendicular to the wall.CBC 202Commercial Plan Check Correction Sheets (2026 LABC), Part II, E. Fire-Resistance Rated Construction, item 2
San FranciscoPlot plan must locate the building, adjoining buildings and public ways with real and assumed property lines to support exterior wall and opening protection review.SFBC 106A.3.4.2.1, item 3cSFBC 106A.3.4.2.1 Contents of site permit application, item 3c
San DiegoThe site plan must dimension fire separation distance between adjoining buildings and from property lines to every building or structure.Project Submittal Manual Section 2, checklist item 4.1.10 (Fire Separation Distances)

Sources reviewed September 12, 2026. Code sections are as cited on each list and follow that city’s adopted code. Confirm the current list and edition with the department.

Revise the set

What changes on the drawings, and what else to re-check

Opening limits change elevations, and rating changes reach the wall assembly and its details.

Fire separation distance: sheets to revise and dependent sheetsSwipe or scroll sideways to read all columns.
ChangeSheets to reviseAlso re-check
Distances dimensionedSite plan; floor plansSurvey basis, setbacks on zoning sheets, imaginary lines between buildings
Exterior wall ratedWall types; wall sectionsListed assembly for exterior walls, eave and soffit construction, vents in the wall
Openings reduced or protectedElevations with opening area table; window scheduleDaylight and energy calculations, rated glazing, sprinkler protection of openings
Projection cut backRoof plan; wall sectionsDrainage, structural framing, architectural elevations

Close the comment

A response the reviewer can verify

An illustrative example written for this guide, not a real project or a city’s wording. Name the sheet, the detail, and the change, so the recheck does not start with a search.

Comment

Show fire separation distance to property lines. Provide exterior wall ratings and allowable opening percentages for the north and east walls.

Response

Revised as requested. Fire separation distances are dimensioned on A1.01 (north wall 6 feet 2 inches, east wall 12 feet). Both walls revised to one-hour construction (wall type EW2 on A0.20). Opening area tables on elevations A4.01 and A4.02 show 14 percent unprotected openings on the east wall and 9 percent on the north wall, within the allowable for those distances.

How to write the whole response letter

Before you submit

Catch it before the plans examiner does

  1. Dimension from the right line

    Measure to the lot line, street centerline, or imaginary line, and say which one on the plan.

  2. Tabulate per story

    Calculate opening area on each story of each wall that is within the limited distance.

  3. Check the eaves

    Look at roof overhangs and balconies, which sit closer to the line than the wall.

Groundbook compares the drawings, schedules, and specifications with the code and local references you upload, and links each potential issue to the sheets and sections behind it. Your team verifies each finding; the jurisdiction makes every approval decision. See the pre-permit review and drawing-to-code review.

Questions, answered

Fire separation distance: questions

How is fire separation distance measured?

Perpendicular from the face of the building to the closest interior lot line, the centerline of a street or public way, or an imaginary line between two buildings on the same lot.

Is fire separation distance the same as a zoning setback?

No. A zoning setback is a planning rule for where a building can sit. Fire separation distance is a building code measurement that sets exterior wall ratings and opening limits.

Do sprinklers change the allowable openings?

Yes. In IBC Table 705.9 the allowable percentage rises when the building is sprinklered throughout or when the openings are protected; either condition is enough. State the basis on the elevations.