Plan check guide · Los Angeles

Los Angeles plan check guide

LADBS reviews building plans against the Los Angeles codes and returns circled correction sheets. This guide collects what the department publishes: which plan check path fits, how to format plans for ePlanLA, which departments sign off, and what the 2026 correction sheets ask designers to show.

In Los Angeles, the Department of Building and Safety (LADBS) reviews permit plans through Counter, Expanded Counter, or Regular Plan Check, applying the 2025 California Building Standards Code with Los Angeles amendments. Corrections come back as circled items on standard correction sheets: answer each with a written response and a sheet or detail reference, then verify the corrections with the plan check engineer by appointment.

Los Angeles at a glance

The facts to confirm before you submit

Los Angeles plan check at a glanceSwipe or scroll sideways to read all columns.
QuestionWhat the official source saysSource
Who reviews building plans?The Department of Building and Safety (LADBS). City Planning, the Fire Department, Public Works, Transportation, and other agencies issue clearances that must be signed off before the permit is issued.City of Los Angeles Development Services Committee - Building Permit Clearance Handbook
Which code applies?LADBS applies the 2025 California Building Standards Code with Los Angeles amendments. Correction sheets effective January 1, 2026 cite the 2026 Los Angeles Building and Residential Codes alongside CBC sections.LADBS Information Bulletin P/BC 2026-120 - Policy for Plan Check Time Extension
How are plans submitted?Through ePlanLA, as single-file vector PDFs in landscape layout, bookmarked by sheet number, up to 50 MB per file, with the top-right corner of every sheet left clear for the LADBS stamp.LADBS - ePlanLA FAQ (FAQ search results, ePlanLA category)
How long does plan check take?Counter Plan Check is reviewed the same day. Regular Plan Check is assigned within a few days and returned within weeks, and LADBS says timing varies with the backlog at submittal.LADBS - Regular Plan Check
How do I respond to corrections?Answer every circled correction with a written response or detail reference that shows where the revision is, then verify corrections with the plan check engineer by appointment.LADBS - Commercial Plan Check Correction Sheets (2026 LABC), PC/STR/Corr.Lst.015
How long is a plan check valid?Eighteen months, with up to four six-month extensions, for about three and a half years from the original submittal.LADBS Information Bulletin P/BC 2026-120 - Policy for Plan Check Time Extension

Sources reviewed September 12, 2026. Requirements change; confirm the current version with City of Los Angeles Department of Building and Safety.

Who reviews

Who comments on a Los Angeles permit set

LADBS plan check covers the building code. Other departments issue clearances that are tracked on the Clearance Summary Worksheet and must be signed off before the permit is issued, and LADBS warns that some take months, so apply for them early.

Department of City Planning (DCP), including its Zoning Division

Clears projects against existing planning cases and conditions, new entitlement actions, and specific plan, HPOZ, CDO, CPIO and POD areas; public hearings or discretionary approvals can affect final design.

Source

Department of Public Works, Bureau of Engineering (BOE)

Address approval, construction permits for driveways, curbs, gutters and sidewalks, storm drain connections, and encroachments into the public way.

Source

Department of Public Works, Bureau of Sanitation, Watershed Protection Division

Low Impact Development (LID) sign-off for new construction, additions, parking lot regrading, or pads adding more than 2,500 sq ft of impervious area.

Source

Los Angeles Fire Department (LAFD)

Hydrant and access approval for new buildings and additions valued at $50,000 or more (hydrant spacing, fire lanes, fire hazard severity zones), plus high-piled storage, underground fuel tanks and asbestos removal clearances.

Source

Department of Transportation (LADOT)

Driveway approval for projects on Boulevard and Avenue roadways or with drive-through uses, and Transportation Demand Ordinance clearance.

Source

Los Angeles County Department of Public Health

Plan check for food facilities, public pools, tattoo shops, wells and x-ray rooms; clearance is given as a Public Health approval stamp on the plans.

Source

LADBS Disabled Access review

New construction or alterations to apartment and commercial buildings receive a separate disabled access and accessibility review.

Source

LADBS Green Building Division and Grading Division

Green Building Division clearance; Grading Section approval of soils, foundation and geology reports; grading pre-inspection reports for Hillside Grading Area work.

Source

Review paths

Choose the right plan check path

Express Permit

For simple projects that need no plan check; can be obtained online.

Source

Counter Plan Check

Same-day, over-the-counter review of simple projects, such as single-story home additions, alterations, tenant improvements, storefront changes, non-bearing partitions and disabled access improvements.

Source

Expanded Counter Plan Check (ECPC)

For modest projects such as medium-size home additions and multi-floor tenant improvements with no change in use.

Source

Regular Plan Check (RPC)

For large, complex projects. Processed at the Metro, Van Nuys and West LA offices, though plans may be submitted at any Development Services Center; plans are assigned to an engineer after submittal.

Source

Expedited Regular Plan Check

Paying an additional 50% of the plan check fee expedites regular plan check review.

Source

Preliminary Plan Check

Paid pre-submittal meeting ($208 plus surcharges) with a plan check engineer to answer code questions before formal submittal.

Source

Parallel Design-Permitting Process

For major developments: design and permitting run concurrently, with LADBS giving guidance from conceptual design and plan check and correction verification through later design phases.

Source

Counter Plan Check plans are reviewed the same day as submittal; projects suited to the counter can be reviewed in roughly 45 to 60 minutes. (source) Regular Plan Check: plans are assigned within a few days of submittal and returned within weeks, depending on workload. (source) LADBS's FAQ says plan check time varies from week to week based on the backlog at the time of submittal. (source)

What LADBS asks for

What Los Angeles’s published correction sheets ask for

LADBS publishes standard correction sheets by project type, and plan check engineers circle the items that apply to your plans. These items come from the 2026 Commercial, Counter, and Adaptive Reuse correction sheets. Paraphrased from the department’s published documents, grouped by topic. The documents do not rank items by how often they are issued.

Los Angeles published plan check itemsSwipe or scroll sideways to read all columns.
TopicWhat the published document asks forCode citedSheets that usually changeWhere it appears
Code analysisShow project data on the title sheet: height, stories, basements, floor area, fire district, uses, lot size, construction type, occupancy groups, scope, sprinkler and alarm status, allowable-area analysis.CBC 903.2, T506.2; CBC 907; CBC 506cover/title sheet project data and code analysisCommercial Plan Check Correction Sheets (2026 LABC), Part I General Requirements, C. Administration, item 6
Occupant load and egress widthLabel each space with the occupant load factor matching its actual function, and provide width calculations for all egress components.CBC T1004.5; CBC 1005.2, 1005.3occupant load/egress plans; code analysisCommercial Plan Check Correction Sheets (2026 LABC), Part II, H. Means of Egress, items 3 and 10
Travel distance and common pathDimension the common path of egress travel from each space, and add a legend showing exit locations and travel distance from the most remote point on each story.CBC 1006.2.1; CBC T1017.2egress/life safety plansCommercial Plan Check Correction Sheets (2026 LABC), Part II, H. Means of Egress, items 13 and 40
Number and separation of exitsProvide two exits from any space or story whose occupant load exceeds the table limit, for example more than 49 occupants in Groups A, B, E, F, M or U.CBC T1006.2.1floor plans; egress planCommercial Plan Check Correction Sheets (2026 LABC), Part II, H. Means of Egress, item 12
Stairs, handrails, and guardsDetail every stairway: 7 in. maximum riser, 11 in. minimum tread, 6 ft 8 in. headroom, required width, landings, handrail height, grip size and extensions, and 42 in. guards.CBC 1011.2, 1011.3, 1011.5, 1011.6, 1014.2, 1014.4, 1014.7, 1015.3stair plans, sections and detailsCommercial Plan Check Correction Sheets (2026 LABC), Part II, H. Means of Egress, item 25
Fire-rated assembliesIdentify fire areas, fire walls, fire barriers and fire partitions on the plans, with a complete legend and construction details for each.CBC 702, 706, 707, 708fire/life safety plans; wall type legend; rated assembly detailsCommercial Plan Check Correction Sheets (2026 LABC), Part II, E. Fire-Resistance Rated Construction, item 8
Rated openings and penetrationsAnalyze protected and unprotected exterior wall openings; no openings are allowed under 3 ft fire separation distance, and required door and window protection ratings must be shown.CBC 705.9; CBC T716.1(2); CBC T716.1(3)exterior elevations; opening area table; door and window schedulesCommercial Plan Check Correction Sheets (2026 LABC), Part II, E. Fire-Resistance Rated Construction, item 6
Fire separation distanceShow fire separation distance to interior lot lines, to the centerline of streets, alleys or public ways, and to imaginary lines between buildings, measured perpendicular to the wall.CBC 202site plan; code analysis; exterior wall rating diagramCommercial Plan Check Correction Sheets (2026 LABC), Part II, E. Fire-Resistance Rated Construction, item 2
Path of travel in alterationsAltered elements must fully comply, and alterations or additions need an accessible path of travel to the work area, covering the primary entrance, restrooms, drinking fountains, phones and signs.11B-202.3; 11B-202.4site plan path of travel; floor plans; restroom enlarged plans; accessibility detailsCounter Plan Check Correction Sheet (2026 Code Ref.), Part III, H. Accessibility, items 1-2
Path of travel in alterationsWhen adjusted construction cost is at or below the valuation threshold, path-of-travel cost may be limited to 20 percent, with an unreasonable hardship request. The sheet lists $203,611; the state updates the threshold each January.11B-202.4, Exceptioncover sheet valuation and accessibility notes; path-of-travel planCounter Plan Check Correction Sheet (2026 Code Ref.), Part III, H. Accessibility, items 3-4
Special inspectionState required continuous or periodic special inspection, and require structural observation for items such as shear walls over 300 plf, hold-down anchors or diaphragms.Sec 1704; Sec 1709structural general notes; special inspection and observation scheduleCounter Plan Check Correction Sheet (2026 Code Ref.), Part III, L. Structural item 13 and M. Add Structural Notes item 2
Special inspectionRequire structural observation by a licensed architect or civil/structural engineer for wall anchorage, anchor connectors and continuity ties, and put the completed observation form on the plans.LABC Section 1704structural general notes; structural observation form sheet; anchorage detailsAdaptive Reuse Plan Check Correction Sheets (2026 LABC), Part II, page 3 of 6, item 8 (structural observation)
Sheet coordinationDelete any plans, details or notes that do not apply to this project.general notes; standard detail sheets; any sheet with unused contentCommercial Plan Check Correction Sheets (2026 LABC), Part I, C. Administration, item 11
Allowable height and areaProvide an allowable area analysis using the CBC formulas; a frontage increase needs 20 ft unobstructed yards along at least 25% of the building perimeter.CBC 506.2.1; CBC 506.2.2; CBC 506.3.2code analysis on cover sheet; area plans; site plan (frontage)Commercial Plan Check Correction Sheets (2026 LABC), Part II Building Code Requirements, C. Building Limitation, item 4
Allowable height and areaCalculate the grade plane and show it on elevations, sections and site plan; show maximum building height in feet and stories on every elevation.CBC 202exterior elevations; building sections; site planCommercial Plan Check Correction Sheets (2026 LABC), Part II, C. Building Limitation, items 10-11
Structural calculations and signaturesEvery architectural and structural sheet must carry the signature and registration number of a California-registered architect or engineer.title blocks of all architectural and structural sheetsCommercial Plan Check Correction Sheets (2026 LABC), Part I, C. Administration, item 4
Geotechnical reportSoils, foundation or geology reports must be approved by the LADBS Grading Section; submit the approved report and approval letter and show compliance with their conditions.foundation plan; structural general notes; grading planCommercial Plan Check Correction Sheets (2026 LABC), Part I, B. Clearances, item 9
Energy complianceMake the signed energy certificate of compliance, mandatory measures and calculations part of the plans, and specify insulation R-values for exterior walls, raised floors and roofs.Title 24 energy compliance sheets; wall, floor and roof sectionsCounter Plan Check Correction Sheet (2026 Code Ref.), Part III, J. Building Envelope, item 9
Energy complianceIn adaptive reuse work, building envelope changes and new HVAC or lighting must meet Title 24; provide the calculations and include compliance certificates in the plan notes.Title 24 energy sheets; mechanical and lighting plans; general notesAdaptive Reuse Plan Check Correction Sheets (2026 LABC), Part II, A. General Plan/Calculation Requirements, item 15
Green buildingObtain a clearance from the LADBS Green Building Division before the permit can be issued.green building code notes and checklist sheetsCommercial Plan Check Correction Sheets (2026 LABC), Part I, B. Clearances, item 15
Plumbing fixture countProvide a plumbing fixture analysis based on calculated occupant load, with separate facilities by sex where required and maximum travel distance to toilet facilities.CPC Table 422.1, P/BC 2026-095; CPC 422.2; CPC 422.4fixture count table on code analysis sheet; floor plans; restroom enlarged plansCommercial Plan Check Correction Sheets (2026 LABC), Part II, I. Interior Environment, item 4
Fire sprinklers and alarmsWhere sprinklers are required, add a plan note that the building will have an NFPA 13 system approved by the Plumbing Division before installation.CBC 903.2; CBC 903.3.1.1general notes; code analysis on cover sheetCommercial Plan Check Correction Sheets (2026 LABC), Part II, G. Fire Protection, item 1
Site plan informationProvide a scaled, fully dimensioned plot plan showing legal description, property lines, setbacks, easements, street centerline, dedications, parking, each building's use and type, new work, and fire walls.LABC 106.3.2.1; LABC 506.3; CBC 706site/plot planCommercial Plan Check Correction Sheets (2026 LABC), Part I, C. Administration, item 8
Site plan informationShow natural and finished grade elevations around the building perimeter plus floor and roof elevations, and include a survey map signed by a licensed surveyor or civil engineer.LABC 106.4.3.3site plan; exterior elevations; topographic surveyCommercial Plan Check Correction Sheets (2026 LABC), Part I, C. Administration, item 9
Site plan informationNew buildings valued over $50,000, or with any part 150 ft from an improved street or fire lane, need fire lane access clearance from LAFD's Hydrants and Access Unit.LAMC 57.503.1site plan (fire lane, hydrants, building distances to street)Commercial Plan Check Correction Sheets (2026 LABC), Part I, B. Clearances, item 16

Respond and resubmit

Responding to LADBS corrections

  • Review the circled corrections on the correction sheet, plans and calculations; answer each with a written response or detail reference that identifies where the revision is on the plans. Source

  • Verification of corrections is by appointment only; contact the plan check engineer after corrections are addressed. For paper plans, bring the originally checked set, the correction sheet and revised plans. Source

  • Projects reviewed through ePlan upload plan revisions and correction responses through the ePlanLA portal. Source

  • The permit is issued only after compliance with the corrections is verified and all clearances on the Clearance Summary Worksheet are signed off, including each agency's conditions. Source

  • Plan checks extended past three and a half years require resubmitting plans for recheck against current codes, with the plan check fee charged hourly or as the Department sets. Source

How to write a response letter the reviewer can verify

Official documents

LADBS lists and checklists to work from

Before you submit

Check the set before LADBS does

Upload the drawings with the California Building Code and Los Angeles amendment PDFs that apply to the project. Groundbook compares the sheets with each other and with those references, and links each potential issue to its sources for your team to verify.

Questions, answered

Los Angeles plan check FAQs

How do I respond to LADBS plan check corrections?

Answer each circled correction with a written response or a reference to a detail, and state where each revision appears on the plans. Verification is by appointment with the plan check engineer; ePlan projects upload revised plans and responses through ePlanLA.

What PDF format does ePlanLA require for drawings?

Single-file vector PDFs in landscape layout, bookmarked by sheet number, 50 MB maximum per file, with a title sheet containing a sheet index. Leave the upper-right corner of every sheet clear for the LADBS approval stamp. Supporting documents go in as portrait PDFs up to 8.5x11 in.

How long is an LADBS plan check valid, and can it be extended?

The plan check period is 18 months; LADBS's extension bulletin says it starts when the plan check fee is paid. Administrative six-month extensions, up to four, can stretch it to about three and a half years from original submittal.

Can architects and engineers sign and seal LA plans electronically?

Yes. Information Bulletin P/BC 2026-073 allows electronic signatures and electronically generated seals. Each sheet prepared by a licensed professional needs signature, seal and signing date; multi-page calculations or reports need it at least on the title, cover or signature sheet.

Does Groundbook approve permits or replace LADBS plan check?

No. Groundbook surfaces potential conflicts and omissions in the drawings you upload, with links to the sources, for your team to verify before submitting. LADBS reviews the application and makes every approval decision.

Official source directory

Keep the reference trail

California plan review guide · All plan check corrections · California AB 253 private plan review · San Francisco plan check · San Diego plan check · San Jose plan check · Seattle plan check · New York City plan check

Find the corrections before the plans examiner does

Upload the drawing set with the code and local references that govern it. Groundbook links each potential issue to its sources for your team to verify.