Plan check guide · San Jose

San Jose plan check guide

San José’s Building Division reviews plans electronically in SJePlans and publishes review times in working days for each discipline. This guide collects what the City publishes about its permit services, plan formats, timelines, resubmittals, and the information plan reviewers expect on the drawings.

In San Jose, the Building Division of the Planning, Building and Code Enforcement Department reviews plans through Standard Plan Review, with faster services such as STAR for eligible office tenant improvements and over-the-counter review for small residential work. Plans submitted on or after January 1, 2026 are reviewed under the 2025 California codes; applicants answer plan review comments and resubmit through SJePlans.

San Jose at a glance

The facts to confirm before you submit

San Jose plan check at a glanceSwipe or scroll sideways to read all columns.
QuestionWhat the official source saysSource
Who reviews building plans?The Building Division, with Planning, the Fire Department’s Bureau of Fire Prevention, Public Works, Environmental Services, and the County Health Department when the scope requires them.Form #348 Commercial & Industrial Projects Submittal Checklist (12/06/2023)
Which code applies?Plans submitted on or after January 1, 2026 are reviewed under the 2025 California codes, including Building, Residential, Energy, Fire, and CALGreen.City of San José – Adopted Building Codes
How are plans submitted?Apply at SJPermits.org, then upload to SJePlans as unsecured, flattened, bookmarked landscape PDFs split by plan type, with stamp space at the top right of every sheet.Standard Plan Review Service
How long does review take?The City publishes approximate working days by project type: a new commercial building gets about 25 for the first architectural and structural review and 13 for later rounds.Plan Review Time Frames
Are reviews running longer?The Building Division says reviews are taking longer than normal and asks applicants to add 2 to 3 weeks to the published time frames.Building Division (PBCE) landing page
How do I respond to comments?Answer comments and resubmit through the SJePlans Respond and Resubmit task. Only the designated ePlan Applicant can upload plans and respond.Standard Plan Review Service

Sources reviewed September 12, 2026. Requirements change; confirm the current version with San José Building Division (Planning, Building and Code Enforcement).

Who reviews

Who comments on a San Jose permit set

The Building Division routes plans to other departments when the work touches the site or exterior, fire and hazardous materials systems, public infrastructure, or health-regulated uses.

Planning Division (Planning, Building and Code Enforcement)

Reviews building permit plans that show changes to the site or to the building exterior.

Source

San José Fire Department – Bureau of Fire Prevention

Reviews architectural plans routed with building applications for fire and hazmat compliance, issues deficiency comments, and provides directives listing required fire/hazmat system permits (sprinklers, alarms, hazardous materials) and inspections.

Source

Public Works Department – Development Services

Reviews or clears flood zone, geologic hazard, grading, driveway/sidewalk and other Public Works items on commercial and industrial projects.

Source

Environmental Services Department (Regional Wastewater Facility)

Approval required for food and drinking establishments, public swimming pools, and manufacturing discharge.

Source

Santa Clara County Health Department

Approval required for food and drinking establishments and public swimming pools.

Source

Review paths

Choose the right plan check path

Standard Plan Review Service

Default online path for commercial, industrial and residential projects needing plan review that don't qualify for a faster service: apply at SJPermits.org, upload to SJePlans, pay fees, answer reviewer comments, then permit issuance.

Source

Streamlined Tenant Alteration Review (STAR) Service

Eligible Group B office interior tenant improvements or industrial tool installations reviewed in one 90-minute in-person City Hall meeting with Planning, Building, Public Works and Fire staff; 50% surcharge on plan review fees.

Source

Best Prepared Designer Program

Enrollment program for building professionals; the Building Division says enrolled designers can get building permits in as little as 3 to 5 days.

Source

Over-the-Counter Service

Walk-in, no appointment, for qualifying single-family/duplex work such as one-story additions under 500 sq ft or remodels up to 750 sq ft using prescriptive framing without engineering; permit issued during the visit if plans are accurate.

Source

Residential Express Service

Permit issued in an online meeting for qualifying one-story single-family additions/remodels and accessory buildings under 500 sq ft; appointment required; fee is 1.5 times the single-family addition/alteration plan review fee.

Source

Resubmittal/Revision Service

For applicants not using SJePlans who must resubmit corrected plans, and for revisions to plans after a permit has been issued.

Source

Standard Plan Review, commercial (approx. working days, first/subsequent round): new building 25/13 and high-rise 40/15 for building, fire-architectural and structural review; mechanical/electrical/plumbing 10/5; fire protection and hazmat systems 15/7 (new building), 20/10 (high-rise). (source) Single-family/duplex (first/subsequent): new house 20/10, addition to one-story home 10/5, addition to two-story home 15/7, alterations without structural calcs 10/5, tract 25/13. MEP is checked in the field by the inspector; fire review 10/5. (source) Time frames count working days (no weekends, City holidays or closures) and apply only to Standard Plan Review; fire systems times apply regardless of service. Page last updated 02/13/2026. (source)

What San Jose asks for

What San Jose’s published checklists and Building Division Notes ask for

San Jose does not publish a correction list. These items come from the Building Division Notes on what plan reviewers expect on drawings, submittal checklists, and bulletins. Several notes date from February 2023 and cite the 2022 codes, and the tenant improvement checklist dates from 2000. Paraphrased from the department’s published documents, grouped by topic. The documents do not rank items by how often they are issued.

San Jose published plan check itemsSwipe or scroll sideways to read all columns.
TopicWhat the published document asks forCode citedSheets that usually changeWhere it appears
Code analysisDrawings must carry project data such as construction type, occupancy classification and square footage.Cover sheet / code analysis sheetBDN 01 Information Required on the Drawings, Required Information list
Occupant load and egress widthInclude an exit analysis that shows exit access, exits and exit discharge along with the occupant loads they serve.Code/life-safety plan, floor plansBDN 01 Information Required on the Drawings, Required Information list
Fire-rated assembliesIdentify every fire-rated element (corridors, enclosures, shafts, passageways) with its rating or through a legend, and give complete construction details for each rated assembly.Life-safety/code plan, floor plans, wall and assembly detailsBDN 01 Information Required on the Drawings, Required Information list
Rated openings and penetrationsDetail how penetrations and openings in fire-rated assemblies are protected, and include door and window schedules.Rated assembly details, door and window schedulesBDN 01 Information Required on the Drawings, Required Information list
Rated openings and penetrationsMechanical submittals should locate fire, smoke-fire and air dampers and include fire-resistive separation details and corridor construction showing openings and penetrations.Mechanical plans, rated assembly detailsForm #323, p. 4, Mechanical Plan Submittal Checklist
Path of travel in alterationsFor work in existing buildings, include the City's Accessibility Compliance Form, plus an Unreasonable Hardship request where one applies.Cover sheet or accessibility sheetBDN 01 Information Required on the Drawings, Required Information list
Path of travel in alterationsCommercial remodels must provide accessible parking near accessible entrances, directional signs at inaccessible entrances, a path of travel to the remodeled area, and accessible toilets, phones and drinking fountains.Site plan, path-of-travel plan, restroom plans and details, signage detailsBulletin #226 Disability Access Requirements (03/26/2023), p. 2, General Accessibility Requirements chart – Commercial Remodels
Path of travel in alterationsFor tenant improvements, a key plan should locate the work within the building and show the path of travel to exits and the accessible main entrance.Key plan / accessibility path-of-travel planTenant Improvements – Plan Checklist (Handout No. 2-10), Sec. II, A-3 Key Plan
Special inspectionThe statement of special inspections on the plans must list every material, system and work item requiring inspection, the type and extent of each, and continuous or periodic frequency.CBC 2022 §1704.3; §§1705.12–1705.14 (as cited)Structural general notes / special inspection scheduleBDN 11 Special Inspection Plan Checks (Feb. 1, 2023), Required Special Inspection Information on Plan – Typical Comments
Special inspectionBefore permit issuance, submit the Special Inspection and Testing Form signed by all parties, using an agency from the City-approved list, plus the contractor's statement of responsibility.CBC 2022 §1704.4 (as cited)Usually no sheet change; form and inspector matrix submitted with permit documentsBDN 11 Special Inspection Plan Checks, Special Inspection Form – Typical Comments
Special inspectionPlans must outline a schedule of structural observation stages; the Building Official may require observation for complex or unusual framing, separate from special and City inspections.CBC 2022 §1704.6.1, §1705, §110 (as cited)Structural general notesBDN 05 Structural Observation (Feb. 1, 2023), Findings
Deferred submittalsThe design professional of record lists deferred items on the drawing cover sheet and approves those documents before City submittal; installation waits for Building Division approval.Cover sheet (deferred submittal list)Form #319 Deferred Submittal Form (12/09/2020), p. 2, Requirements for Deferred Submittals
Deferred submittalsDeferred packages must be stamped by a registered design professional and marked reviewed by the professional of record; single-family dwellings and shear wall holdown systems are not accepted as deferred.Cover sheet deferred list; structural drawings for holdownsBDN 02 Deferred Submittals Review Procedure (Feb. 1, 2023)
Allowable height and areaTenant improvement cover sheets should show allowable floor area calculations, occupancy groups, construction type, and gross tenant area for each floor and tenant.Cover sheet / code analysisTenant Improvements – Plan Checklist (Handout No. 2-10, published 8/21/00), Sec. II, A-1 item 4
Accessible route and entrancesAt least one accessible route must run from site arrival points (streets, sidewalks, accessible parking, loading zones, transit stops) to the entrance, following the general public route where feasible.Site plan, accessibility site planBulletin #226 Disability Access Requirements, p. 1, accessible route to the entrance
Structural calculations and signaturesClearly define the lateral force-resisting system with load-path details, list seismic and wind design factors, and show minimum shear wall lengths and holdown locations.CBC 2022 §1603.1.4, §1603.1.5 (as cited)Structural general notes, foundation and framing/shear wall plans, detailsBDN 01 Information Required on the Drawings, Required Information list
Structural calculations and signaturesA registered architect or engineer must stamp and sign plans for new buildings, additions, structural alterations, occupancy changes, exiting changes, and remodels affecting rated corridors or occupancy separations.Cal. Bus. & Prof. Code §5537; 2022 CBC Ch. 23 (as cited)All sheets (title block stamp and signature)Bulletin #240 Plans That Require an Architect or Engineer (06/03/2025), p. 2
Geotechnical reportThe minimum submittal checklist lists a soil report and a seismic hazard zone report among support documents, when applicable to the project.Foundation plan, structural notes referencing the reportForm #323, p. 3, Minimum Plan & Document Submittal Checklist – Support Documents
Energy complianceTitle 24 energy calculations and forms are required for new construction, envelope alterations, HVAC changes beyond equipment replacement, or replacing at least half the lighting fixtures in the work area.Title 24 energy compliance sheets, lighting and mechanical plansForm #323 Plan Review Submittal Package (02/28/2023), p. 2, Calculation Requirements
Green buildingPlace the CALGreen Mandatory Measures Checklist on the drawings.CALGreen sheetBDN 01 Information Required on the Drawings, Required Information list
Plumbing fixture countIn qualifying Group B take-out or limited-seating spaces, employee restrooms need not serve customers, but restrooms installed for employees must still meet CBC accessibility requirements.CPC 2022 Table 422.1, §422.4; CBC Ch. 11B (as cited)Code analysis (plumbing fixture count), restroom plansBDN 29 Minimum Plumbing Facilities (Feb. 1, 2023), Findings
Fire sprinklers and alarmsProjects that affect or add fire sprinklers, fire alarms, or hazardous materials storage need review or clearance from the Fire Department's Fire Prevention Bureau.Fire protection and alarm plans (often deferred), code analysis sheetForm #348 Commercial & Industrial Projects Submittal Checklist (12/06/2023), p. 3, Section 5 Approvals or Clearances
Site plan informationProvide a dimensioned site plan locating the building, any existing structures, and their distances to property lines.Site planBDN 01 Information Required on the Drawings, Required Information list
OtherThe cover sheet needs a scope-of-work statement that clearly names every item intended to be reviewed under this permit.Cover sheetBDN 01 Information Required on the Drawings (Feb. 1, 2023), Required Information list
OtherDrawings must be to scale, fully dimensioned and legible in grayscale, with text at least 10 pt and symbols or hatching, not color, defined in a legend.All sheetsBulletin #227 Electronic Plan Review – File Format Requirements (08/02/2024), item 6

Respond and resubmit

Responding to San Jose plan review comments

  • On SJePlans projects, only the ePlan Applicant can upload plans and respond to plan review comments; corrections are resubmitted through the SJePlans Respond and Resubmit task. Source

  • Without SJePlans: separate corrected plan files by trade (single-family excepted), format them per Bulletin 227, and include a response-to-comments letter for each trade set that received comments, sent as the comment letter instructs. Source

  • Planning comments or site/exterior changes go to Planning's electronic plan review mailbox; Fire comments to the Fire resubmittal mailbox; Public Works comments to the assigned Public Works plan reviewer. Source

  • Fire resubmittals should include updated digital architectural plans, the requested documents, and a narrative describing the changes. Source

  • In non-SJePlans file names, a submission number marks each round: S1 for the first submittal, S2 for the next resubmittal or revision, then S3, S4 and so on. Source

  • The City warns that inaccurate plans lead to resubmittals and additional fees. Source

How to write a response letter the reviewer can verify

Official documents

San Jose lists and checklists to work from

Before you submit

Check the set before San Jose does

Upload the drawings with the California code and San Jose amendment PDFs that apply to the project. Groundbook compares the sheets with each other and with those references, and links each potential issue to its sources for your team to verify.

Questions, answered

San Jose plan check FAQs

Which code edition will San José use to check my plans?

Plans submitted on or after January 1, 2026 are reviewed under the 2025 California codes, including Building, Residential, Electrical, Mechanical, Plumbing, Fire, Energy and CALGreen, which replaced the 2022 codes.

How long does the first round of plan check take?

Standard Plan Review targets are published in working days. For example, a new commercial building gets about 25 days for first architectural/structural review and 13 for later rounds; a new single-family home gets 20 and 10. Fire systems review has separate targets.

How do I respond to plan review comments and resubmit?

SJePlans users resubmit through SJePlans. Otherwise, upload corrected plans split by trade (single-family excepted), formatted per Bulletin 227, with a response-to-comments letter for each trade that got comments. Planning, Fire and Public Works resubmittals go to their own contacts.

Can an office tenant improvement skip the standard plan review queue?

Possibly. STAR covers eligible Group B office tenant improvements up to 50,000 sq ft on one floor, with no change of use or exiting, additions, exterior site work or major structural work. Review happens in one 90-minute City Hall meeting with a 50% fee surcharge.

Does Groundbook approve permits or replace San Jose plan check?

No. Groundbook surfaces potential conflicts and omissions in the drawings you upload, with links to the sources, for your team to verify before submitting. San Jose reviews the application and makes every approval decision.

Official source directory

Keep the reference trail

California plan review guide · All plan check corrections · California AB 253 private plan review · Los Angeles plan check · San Francisco plan check · San Diego plan check · Seattle plan check · New York City plan check

Find the corrections before the plans examiner does

Upload the drawing set with the code and local references that govern it. Groundbook links each potential issue to its sources for your team to verify.