Plan check correction · General

Plan check correction: list deferred submittals on the cover sheet

When the set leaves a system to a later design, such as fire sprinklers or pre-engineered trusses, the reviewer needs to know that it was deferred on purpose and approved to be.

The comment asks you to list every part of the design that will be submitted later for separate review, on the cover sheet, so the building official can approve the deferral. Clear it with a deferred submittals list that names each system and notes that the design professional will review it before it goes to the department.

Read the comment

What the plans examiner is asking for

The list

Each deferred portion of the design listed on the construction documents under IBC Section 107.3.4.1.

Building official approval

Deferral approved by the building official, which the list lets the reviewer grant during plan check.

Design professional review

A note that the registered design professional will review deferred documents before submittal to the department.

Enough information now

Performance criteria and loads for the deferred system on the main set, such as truss loads or sprinkler design criteria.

Published correction lists

How city lists word this correction

Published lists ask for a deferred submittal list on the title sheet, or name the systems to be deferred. Paraphrased from each department’s own published list; the lists do not rank items by how often they are issued.

Deferred submittals: published correction list items by citySwipe or scroll sideways to read all columns.
CityWhat the published list asks forCode citedWhere it appears
San FranciscoInclude a list of deferred submittals, and the addenda schedule when one applies, on the cover sheet.—Residential Pre-Plan Check checklist - Plans: Cover Sheet
San DiegoThe architect or engineer of record must list deferred items on the construction documents; only components in the bulletin's Table 1 are deferrable without building official approval.—Information Bulletin 188, Deferred Submittals (Table 1 and listing requirement)
San DiegoIf prefabricated trusses are deferred, permit plans still need a truss layout, shear transfer details compatible with the trusses, and a summary of truss design loads.—Project Submittal Manual Section 2, checklist items 12.0-12.3 (Truss Plans and Calculations)
San JoseThe design professional of record lists deferred items on the drawing cover sheet and approves those documents before City submittal; installation waits for Building Division approval.—Form #319 Deferred Submittal Form (12/09/2020), p. 2, Requirements for Deferred Submittals
San JoseDeferred packages must be stamped by a registered design professional and marked reviewed by the professional of record; single-family dwellings and shear wall holdown systems are not accepted as deferred.—BDN 02 Deferred Submittals Review Procedure (Feb. 1, 2023)
SeattleCurtain walls, post-tensioned systems, prefabricated stairs, plated wood trusses and storage racks 6 ft+ need post-permit shop drawings, stamped by the designer and reviewed by the engineer of record.SBC 106.5.2.2; SBC 202 (registered design professional)Screening Standards - Post-Permit Submittals (Index 16), Shop Drawing Requirements
DenverEvery item to be deferred (typically specialty engineering such as precast concrete, trusses, shop-fabricated stairs or fire alarm systems) must be listed together in the project's initial code analysis and referenced on the relevant discipline sheets; each deferred item still needs its own permit and inspection before a certificate of occupancy will issue.—Commercial Building Permit Guide, Deferred and Phased Construction section
PortlandRoof/floor trusses, I-joists, manufactured guardrail systems and specialized stairways may be deferred, but geotechnical-related items -- excavation/shoring plans, helical anchors, retaining walls, deep foundations other than micropiles, and shallow foundations -- may not; every deferred sheet and calculation cover page needs an Oregon-registered design professional's seal.OSSC 107.3.4.1Deferred Submittal Guidelines, Eligible/Ineligible Items and Sealing
PortlandThe Engineer or Architect of Record must review deferred submittal drawings and calculations and add a notation such as 'No Exceptions Taken,' 'Approved' or 'Reviewed' directly on the drawings; 'Revise and Resubmit' or 'Rejected' notations, or stamps on transmittal letters alone, are not accepted.OSSC 107.3.4.1Deferred Submittal Guidelines, Review Stamps
PhoenixStructural notes must identify every deferred submittal item, such as joists, trusses or alternate stairs, and the roof framing plan must include the loading and reactions assumed for those deferred elements.IBC 107.3.4.1, 107.3.4.2Plan Review Checklist, Structural, items 1 and 4
BostonFire alarm and special-suppression system plans (Tier II) are a separate submittal reviewed by the Fire Department, distinct from the Tier I architectural plans ISD uses to issue the building permit, and must reference acceptance by the Tier I design professional of record.—Boston Fire Department ePlan Submittal Requirements, General Content Requirements item 1
AustinList deferred submittal items on the City's Deferred Submittal Request Form signed by the Registered Design Professional in Responsible Charge; the engineer or architect of record must review and annotate the deferred documents and submit them as a permit revision before that work begins.—Architectural Plan Review Commercial Checklist, Section A item 4
ChicagoA project needing a variance from the Chicago Electrical Code can request Administrative Relief to obtain the permit subject to a later review and approval of shop drawings, such as for electrical switchgear, instead of holding up the entire permit for that item.—Standard Plan Review - Project Submittal Checklist (rev. 5/13/10), Electrical Items Required, Administrative Relief Request Letters

Sources reviewed September 12, 2026. Code sections are as cited on each list and follow that city’s adopted code. Confirm the current list and edition with the department.

Revise the set

What changes on the drawings, and what else to re-check

A deferred system still has to fit the main set. Put its criteria where the later designer will find them.

Deferred submittals: sheets to revise and dependent sheetsSwipe or scroll sideways to read all columns.
ChangeSheets to reviseAlso re-check
Deferred list addedCover sheetSpecification sections for delegated design, general notes on each discipline’s sheets
Truss or joist deferredStructural framing plans; design loadsMechanical equipment weights, bearing details
Fire sprinklers deferredCover sheet; fire protection notesCode analysis sprinkler basis, ceiling heights, riser room location
Guardrails or storefront deferredArchitectural details; design criteria notesStructural attachment, wind and live load criteria

Close the comment

A response the reviewer can verify

An illustrative example written for this guide, not a real project or a city’s wording. Name the sheet, the detail, and the change, so the recheck does not start with a search.

Comment

List all deferred submittals on the title sheet. Deferred submittals require approval by the building official.

Response

Revised as requested. Deferred submittals list added to G0.01: fire sprinkler system, fire alarm system, pre-engineered wood roof trusses, and exterior metal guardrails. Each will be reviewed by the architect and engineer of record before submittal. Truss design loads are on S2.01; guard load criteria are on A5.02.

How to write the whole response letter

Before you submit

Catch it before the plans examiner does

  1. List early

    Decide what will be deferred during design and put the list on the cover sheet from the first submittal.

  2. Give criteria

    Show design loads and performance criteria for each deferred system on the main set.

  3. Keep the set consistent

    Check that notes on every discipline’s sheets refer to the same deferred systems.

Groundbook compares the drawings, schedules, and specifications with the adopted code and local amendments, and links each potential issue to the sheets and sections behind it. We read the amendments governments publish online and use licensed model codes only where a license allows it. Your team verifies each finding; the jurisdiction makes every approval decision. See the pre-permit review and drawing-to-code review.

Questions, answered

Deferred submittals: questions

What systems are commonly deferred?

Fire sprinkler and fire alarm systems, pre-engineered trusses, curtain wall and storefront, and guardrails are commonly deferred, subject to the building official’s approval.

Can deferred work start before the deferred submittal is approved?

Generally no. Under IBC Section 107.3.4.1, the deferred portion is not installed until its documents are approved by the building official.

Does deferring a system reduce plan check comments?

It moves the detailed review of that system to later, but the main set still needs the criteria and space for it. Reviewers comment when those are missing.

Find the corrections before the plans examiner does

Upload the drawing set. We read the local amendments that governments publish online, and link each potential issue to its sources for your team to verify.

Check deferred submittals against the set

Trusted by hundreds of professionals